.-9
_-
,
iA
.
N
5*O
%o .
UNITED STATES
89
'k
' NUCLEAR REGULATORY COMMISSION
REGION 11
5-
,c
- i
e
101 MARIETTA ST., N.W., SutTE 3100
,
i
ATLANTA, oEoRot A 30303
JUL 0 81981
eNM
f
E
"
v
.
e
w
.x
4
Virginia Electric and Power Company
T,,V
! -i b( 08 [ t).
ATTN:. Mr. J. H. Ferguson
/4
-
.
Executive Vice Preside:tt-Power
-
14.] 4
l-- -
P. 0. Box'26666
' Richmond, VA 23261
\\
'j
.
. Gentlemen:
/
Subject: Report Nos. 50-338/81-lb and 50-339/81-12
~
'
'
j
This refers to the safety inspection conducted by Mr. E. H. Webster of this
!
office on May 6-f and May 26 - June 5,1981, of activities authorized by NRC
!
Operating License dos _. NPF-4 and NPF-7 for the North Anna f acility and to the
discussion of cur findings held with Mr. W. R. Cartwright, Station Manager,.at
,
[
the conclusion of the inspection.
1
l
Arecs examined during the . inspectien and - our findings are discussed in the
'
enclosed inspection report.
Within these areas, the inspection consisted of
selective examinations of procedures and representative records, interviews with
personnel, and observ:tions by the inspector.
!-
.Within the ; cope of this inspection, no violations or deviations were disclosed.
We have examined actions yea have taken with regard to previously identified
enforcement matters. These are discussed in the enclosed inspection report.
In accordance with 10 CFR 2.790 of the Commission's regulations, a copy of this
letter and the enclosed report will be placed in the NRC's Public Document Room.
If the report contains any information that you believe to be exempt from
disclosure under 10 CFR 9.5(a)(4), it is necessary that you:
(a) notify . this
office by telephone within ten days from the date of this letter of your
intention to file a request for withholding; and (b) submit within twenty-five
days from the date of this letter a written application to this office to
withhold such information.
If your receipt of this letter has been delayed such
that less than seven days are available for your review, please notify this
office promptly so that a new due date may be established.
Consistent with
section 2.790(b)(1), such application must be accompanied by an affidavit
executed by the owner of the information which identifies the document or part
thereof sought to be withheld, snd a full statement of the reasons on the basis
of which it is claimed that the information should be w thheld from public
i
disclosure.
This section further requires the statement to address with
specificity the considerations listed in 10 CFR 2.790(b)(4).
The information
sought to be withheld shall be incorporated as far as possible into a separat'e
part of the affidavit.
If we do not hear from you in this regard within the
specified periods noted above, the report will be placed in the Public Document
Room.
'
,
$GoI
$
//
.
8108040583 810708 ".
-<
PDR ADOCK 05000338
G
PDR:
o
JUL 0 81881
'
.
.
.
Virginia Electric and Power Company
2
,
Should you have any question.; concerning this letter, we will be glad to discuss
them with you.
Since ely,
/f
12
tv-
Reactor Proj(ogg, Act14g Chief
Jaul J. Ke/
ects Branch 1
Division of Resident and
Reactor Project Inspection
Enclosure:
Inspection Report Nos. 50-338/81-15
and 50-339/81-12
cc w/ enc 1:
W. R. Cartwright, Station Manager
P. G. Perry, Senior Resident Engineer
~