Revised Final Deficiency Rept,Originally Reported on 800619, Re Safety Injection Pump Breaker lockout.Seal-in Contact of 1X Relays Will Be Removed from Circuit Breakers in 6,900- Volt Shutdown Boards
ML20009F750
Person / Time
Site: Sequoyah Tennessee Valley Authority icon.png
Issue date: 06/09/1981
From: Mills L
TENNESSEE VALLEY AUTHORITY
To: James O'Reilly
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
References
10CFR-050.55E, 10CFR-50.55E, NUDOCS 8107310504
Download: ML20009F750 (2)


Text

.

O,?l9r

/

o ss TENNESSEE VALLEY AUT.HORITY Q

k CHATTANCOGA. TEr4NESSEE 37401 400 Chestnut Street J'ower II

'..: n jf June 9, 1981

  • OJ j

Mr. James P. O'Reilly, Director (1

(\\

I

?.

Office of Inspection and Enforcement Jul 01931 % -

U.S. Nuclear Regulatory Comission i

v, a auw m,2.,

    • =

Region II - Suite 3100 101 Marietta Street 7

Atlanta, Georgia 30303

/'% -Qb

Dear Mr. O'Reilly:

SEQUOYAH NUCLEAR PLANT UNIT 2 - SAFETY INJECTION PUMP BREAKER LOCKOUT -

NCR 27P - REVISED FINAL REPORT The subject deficiency was initially reported to NRC-0IE Inspector M. T'omas on June 19, 1980, in accordance with 10 CFR 50.55(e).

An c

interim report as submitted on July 18, 1980. Our final report (submitted August 25, 1980) stated that work in this deficiency would be completed by November 3, 1980. This commitment has not been met. Enclosed is our revised final report which clarified our safety implication and revises our commitment to complete work on this deficiency.

If you have any questions, please get in touch with D. L. Lambert at FTS 857-2581.

Very truly yours, TENNESSEE VALLEY AUTHORITY L M N l.$$4hMIL L. M. Mills, Manager Nuclear Regulation and Safety Enclosure cc:

Mr. Victer Stello, Director (Enclosure)

Office of Inspection and Enforcement U.S. Nuclear Regulatory Comission Washington, DC 20555 6'i l l

l 8107310504 910609 PDR ADOCK 05000328 l

S PDR An Eaual Opcortun.a E.ap.ove

J.

oo.

ENCLOSURE SEQUOYAH NUCLEAR PLAdi' UNIT 2 SAFETY INJECTION PUMP BREAKER LOCK 0iTI NCR 27P 10 CFR 50.55(e)

REVISED FINAL REPORT

)

Description of Deficiency s,

During preoperational testing of Sequoyah unit ? safety injection pumps (2A-A and 2B-B) it was found that if the pumps,were given a closed (start) signad ihr *grea'cer un 0 32 seonnds while a p' imp trip condition existed, the 6900V breakers would lock out, preventing pump start. There is no

+

visual or audio indication to operations employees when this lockout

\\

condition exists. Tne breakers appear to be available for service when they actually are not.

Safety Implications The lack of an indication of the locked-out ocedition of the circuit breakers could preclude the operator from recognizing and correctin& the condition. This could result in a failure of the safety injection pumps to start automatically under emergency conditions. This could result in less core cooling capability than was assumed in the plant safety analysis, jeopardizing the safe operation of the plant. This condition also applies to the breakers for other loads on the 6 9 kV shutdown boards.

Corrective Action TVA has investigated this problem and has found it to be common only to Sequoyah and Watts Bar Nuclear Plants.

'o alleviate the problem, the seal-in contact of the 1X relays will be removed from the circuit breakers in the 6900V shutdown boards. This will provide the operator with indication of the condition and allow him to take simple corrective action from the main control room (i.e.. operation of the handswiten for the affected load).

l In our previous response, it was indicated that the corrective action specified above would be completed before November 3,1980. Based npon a recent design review, TVA determined that the work has not been completed.

This condition has been evaluated for significance to plant safety; as a result, it was determined that most of the affected loads are not required for fuel loading of Sequoyah enit 2.

The relays for the Sequoyah unit 2 centrifugal charging pumps will be corrected before fuel loading *or that unit. The other affected relays of that unit will be corrected before plant heatup. Both Watts Bar units will be corrected before fuel loading.