ML20009E457
| ML20009E457 | |
| Person / Time | |
|---|---|
| Site: | Diablo Canyon |
| Issue date: | 07/14/1981 |
| From: | Crane P PACIFIC GAS & ELECTRIC CO. |
| To: | Engelken R NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV) |
| References | |
| NUDOCS 8107280224 | |
| Download: ML20009E457 (3) | |
Text
/,' {/ '-
Docket Nos. 50-275
.'.l wnr 50-323 4
s
- h. ADfppa '
ir JIJf. } fi inA o
-4 PACIFIC GAS AND E LE CZT 1%Q'3D O M PANY n We
.~
77 BE ALE STREET,%' EN
. Q F.( CISCO, C ALIFORNI A 94106 g
P. O. BOX 7 442.
} { J(Q.y ' p 4
-\\>
TELECOPIER (415) 543 7813 T E L E P H O N E (415 ) 781 4 211
.y.,._e.ss
....s.y...se ROBERYQHLBACH
- :t.;..n..t.y ::.
- .:.t.:r.*.*..
"' "o ~ ** u us a= u C e a R L e a v. v A N o e U S e N
- 'l1 7 l*.rff[/*
E:U[ N G "[j..,
pH a L Ie A C Ra N e. J R.
E'<5". '
"s*((.*.n N.'.[er [ 7[*"*
0? O't C "*""
July 14 1981
' ".M ~ rC#'~"
seNRvs.L.mLaNre
.U se t[ [."I."'..
JOHN e.OI59ON
.s.i.e s.u..es a R T MU R L. MIL L M a N. J R.
C H a R L e S W. THISSeLL E'l,17,I2*;*Il"
'*'"ff,'s.",'ff*/
oaNie L e, eiaSoN i'f;*f.'27'
- ".Pt.i".*/::t*
E:,T' : V;;;;;
ftJJ:f *;t;/l.'....
's!'.'. L*r.".. "
fr.'.17eT...
a ae a r. ea L Li N. s R.
sooepHi.neLtv
' =: :::~ "*-
rr.re:::..
.~,.,...s.a.
- =:: 7::: ~
- [::%.1:::
,,,,,,,,,,~?=",
- *. ::"""~
Mr. R. H. Engelken, Director Office of Inspection and Enforcenent Region V y
e/
U. S. Nuclear Regulatory Cmmission
'Q QM 1990 N. California Boulevard r
i I
Walnut Creek Plaza, Suite 202
/'
Walnut Creek, CA 94596
/5' gl A j /,t 1 l>
w
,j JUL 2 71981 m -
Ib: Docket No. 50-275
- u.s.NucuneesoaAross -ff.i n,
Docket No.30-323 comissam Diablo Canyon Units 1 and 2
}s
'u /
h
Dear Mr. Engelken:
'$'i "lT-The following is subnitted in reply to the request in your letter duced June 19, 1981 regarding specific infonnation concerning the Dnergency Notification Systen:
Itan 1 Access for telephone coupany represen-tatives for survey and installations.
l Access to Diablo Canyon Power Plant is obtained through Plant Security. Con-tact Mr. Robert R. Smith, on site, at (805) 595-7351 for clearance.
Item 2 Power for station packages.
I PGands has provided Pacific Telephone with access t,a its 48 Volt D.C. tele-l cmmunications battery power for all 8107280224 810714 hI-PDR ADOCK 05000275 F
pon
~
Mr. R. H. Engelken July 14, 1981 critical circuits and equipnent. We reccmnend that the new ENS equipnent proposed at the power plant site be configured for 48 Volt D.C. operation.
Its 3 Mequate cable facilities.
The existing MS circuit is served frm a 4-wire lease and telephone sets which are in pla within the power plant.
Based on a review of the material attached to your letter, Maitional cable facilities do not appear to be required. In-the event Maitional pairs are required, we will arrange to provifa cable as needed.
Its 4 Telecxmnunications planning personnel.
Either of the following two individuals cn the Cmpany's Ccmuunications Depart-ment's Staff can be cmtacted for required support and assistan :
Mr. August J. Nevolo (415) 541-5516 Mr. Albert M. Badella (415) 781-4211, ext. 3579 Its 5 A list of MS station locaticns.
The ENS station locations are as follows:
DIABID CANYCN POWER PIANT SITE (Existing) 1 i
1)
PGandE Control Rocm 2)
PGandE Shift Forman's Office, Auxiliary nnilaing
- 3) NRC - Power Plant Offi Trailer - on site
- 4) NBC - TSC Office, Buttress Cubicle - Unit 2 l
I l
Mr. R. H. Engelken July 14, 1931 OFF SITE LOCATICNS 1)
PGandE Information Center (Back up EOF), Highway 101 (Existing)
- 2) NRC Office - County Dnergency Operations Center (EOC), San Luis CSispo County Sheriff's facility, San Luis Obispo, California (Proposed)
Item 6 Planned station moves or installations to be ccrnpleted.
None, other than th. 1n.stallation at the EOC.
Item 7 Tatporary ENS station locations.
Ncme.
Itsu 8 Anticipated problems in meeting a system up-grade start date of 8/1/81.
No problens anticipated.