Forwards IE Insp Repts 50-566/81-06 & 50-567/81-06 on 810507-08.No Noncompliance Noted
ML20009D786
Person / Time
Site: Yellow Creek  
Issue date: 06/18/1981
From: Robert Lewis
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: Parris H
TENNESSEE VALLEY AUTHORITY
Shared Package
ML20009D787 List:
References
NUDOCS 8107240346
Download: ML20009D786 (2)


See also: IR 05000566/1981006

Text

f

~

l

'

OFFICIAL COPY

,

.f

UNITED STATES

[

o

8^'

3s

NUCLEAR REGULATORY COMMISSION

i

3-

aE

REGION ll

k

101 M* RIETTA ST., N.W., SUfTE 3100

ATLANTA, GEor* CIA 30303

Q/g

JUN 1 B 1981

<

Tennessee Valley Authority

g[

ATTN:

H. G. Parris

-

e

- Manager of Power

th

JUL 2 31981*

500A Chestnt t Street Tower II

,,,,,m maxa q

-

    • '55"

Chattanooga, TN 37401

g-

h,

q

.o.

Gentlemen:

$

~

'

Subject: Report Nos. 50-566/31-06 and 50-567/81-06

This refers to the special inspection conducted by Mr. J .

L.

Coley of this

office on May 7-8, 1981, of activities authorized by NRC Construction Perm't

Nos. CPP."-172 and CPPR-173 for the Yellow Creek facility and to the discussion

of our findings held with Mr. G. J. Pitzl, Metals Application Supervisor, at

the conclusion of the inspection.

Areas examined during the inspection and our findings are discussed in the

enclosed inspection report-

Within these areas, the inspection consisted of

.

selective examinations of procedures and representative records, interviews with

personnel, and observations by the inspectors.

Within the scope of this inspection, no violations or deviations were disclosed.

We _ have examined actions you have taken with regard to previously identified

eaforcement matters and unresolved items. The status of these items is discussed

in the enclosed report.

In accordance with 10 CFR 2.790 of the Commission's regulations, a copy of this

letter and the enclosed report will be placed in the NRC's Public Document Room.

If the report contains any information that you believe to be exempt from

disclosure under 10 CFR 9.5(a)(4), it is necessary that you:

(a) notify this

office by telephone within ten days from the date of this letter of your

intention to. file a request for withholding; and (b) submit within twenty-five

days from tiie date of this letter a written application to this office to

withhold such information.

If your receipt of this letter has been delayed such

,

that less then seven days are available for your review, please notify this

office promptly so' that a new due date may be established.

Consistent with

sect. ion 2.790(b)(1), such apolication must be accompanied by an affadavit

executed by the owner of the information which identifies the document or part

thereof sought to be withheld, and a full statement of the reasons cn the basis

of which it.is claimed that the information should be withheld from public

,

disclosure.

This section further requires the statement to address with

specificity the considerations listed in 10 CFR 2.790(b)(4).

The information

sought to be withheld shall be incorporated as far as possible into a separate

part of the affidavit.

If we do not hear from you in this regard within the

specified periods noted above, the report will be placed in the Public Document

Room.

TW

s

1 I

-

' f!107240346 810618

PDR ADOCK 05000566

g

PDR

. /

'

l'

-t

.

t'

4

0

bl

Tennes. e

'! alley Authority-

2

i

,

Should you'have any questions concerning this letter, we will be glad to discuss

them with you.

Sincerely,

sd5 t[.

'

R. C.

wis, Acting Director

Division of Resident and

Reactor Project Inspection

Enclosure:

Inspection Report Nos. 50-566/81-06

and 50-567/81-06

cc w/ encl:

H. - J. Green, Division Director

-J. F. Cox, Supervisor, Nuclear

Licensing Section

M. M. Price, Project Manager

'M. A. McBurnett, Project Engineer

H. N. Culver, Chief, Nuclear Safety

Review Staff

.

e

,

'

k.

]