Forwards LER 81-053/03L-0
Date released: 01/23/2020 Download: ML20009D656


LER 81-053/03L-0:on 810625,mgt Review Revealed That Electric & Diesel Fire Pump Flow & Pressure Tests Per Tech Specs Were Not Conducted within Required Time Period.Caused by Failure to Place Surveillance Tests on Schedule.Tests Performed