Text
.
Duxn POWER COMPANY Powru 13cnwiso 422 Sourn Cnunen STnEcT, CnAHwTTE, N. C. 2a242 WI LLI AM O. PAR M ER,,J R, Vect PersiorNT TELgpwows:Anta 704 src. p.coucno.
July 16, 19b1 373 40 3
' g /
Mr. Harold R. Denton, Director Office of Nuclear Reactor Regulation U. S. Nuclear Regulatory Commission
/[
y*'
' ) [%,
Washing, ton, D. C.
20555 f
JUL 2 01981
- 7^2 Attention:
Ms. E. G. Adensam, Chief Licensing Branch ho. 4
}I cuin es*f0" o3 CounA151CN
,y)
Re: McGuire Nuclear Station Docket Nos. 50-369, 50-370
<, /
.N
Dear Mr. Denton:
Mr. Robert L. Tedesco's letter of May 19, 1981 outlined the NRC Staff position on natural circulation training for licensed operators on the second unit of a two unit station and further requested that Duke Power Company provide a re-sponse to this position. The purpose of this letter is to provide that re-sponse.
The McGuire simulator will be programmed to permit operation under natural cir-culation conditions.
The results of the McGuire Unit I natural circulation testing will then be used as a benchmark to determine the adequacy of the McGuire simulator to simulate natural conditions. If. acceptable, the simulator will then be used to train Unit 2 operators.
If it is determined that the simulator can-not be adequately programmed for natural circulation conditions, then the Unit 2 operator training requirements would 1e satisfied by in-plant training.
If there are further questions regarding this matter, please advise.
Ve y truly yours,
{-
6_
/ William O. Parker, Jr.
GAC:pw cc:
Ms. M. J. Graham Mr. James P. O'Reilly, Director Resident Inspector - NRC U.S. Nuclear Regulatory Commission McGuire Nuclear Station Region II S Oo /
S
/ O
~
8107210383 810716 PDR ADOCK 05000369 V
.