Text

FOR DCS PROCESSING

,

famuy

Original document not available

h

UNITED STATES

to NRC

r

j

[

}

NUCLEAR REGULATORY COMMISSION Certified by j tf 7)cge N

3

c

REGION V

?

1990 N. CALWORNIA BOULEVARD

[)A/ g-g

,o'

SUITE 202, WALNUT CREEK PLAZA

  • r,,,*

WALNUT CREEK, CALIFORNIA 94596

June 23, 1981

Docket No. 50-344

fq,

v-

i~

f

l/

b( \\\\{

3

't

  1. p \\\\

b

Portland General Electric Company

197 7

121 S. W. Salmon Street

i

' #g\\p# ;3

jul 3

Portland, Oregon 97204

6,

-

1

Attention:

Mr. Bart D. Withers

Vice President - Nuclear

Gentlemen:

Subject: NRC Inspection

This refers to the inspection conducted by Mr. G. Yuhas and Mr. E. Garcia

of this office on May 11-15, 1981 of activities authorized by NRC License

No. NPF-1, and to the discussion of our findings held by Mr. G. Yuhas with

Mr. B. D. Withers and other members of your staff at the conclusbn of the

inspection.

Areas examined during this inspection are described in the enclosed inspection

report. Within these areas, the inspection consisted of selective examinations

of procedures and representative records, interviews with personnel, and

observations by the inspector.

Based on the results of this inspection, it appears that certain of your

activities were not conducted in full compliance with NRC requirements,

as set forth in the Notice of Violation, enclosed herewith as Appendix A.

With respect to Item A of the Notice of Violation, no response is required in view

of the timely manner in which you identified the problem and implemented measures to

prevent recurrence. We have no further questions on that matter.

In accordance with 10 CFR 2.790 of 'he Commission's regulations, a copy

of this letter and the enclosed 'nsr action report will be placed in the

NRC's Public Document Room.

If i h's report contains any information that

you (or your contractors) bel >v , tu be exempt from disclosure under 10 CFR 9.5(a)(4), it is necesse f

J nJ (a) notify this office by telephone

within ten (10) days from che da u

this letter of your intention to file

'

a request for withholdino and (b) submit within 25 days from the date of

this letter a written application to this office to withhold such information.

If your receipt of this letter has been delayed such that less than seven

Iggf

(7) days are available for your review. Mease notify this office promptly

so that a new due date may be est a Laed.

Consistent with section 2.790

J

(b)(1), any such application must be accompanied by an affidavit executed

, /,

by the owner of the information which identifies the document or part sought

'/I

to be withheld, and which contains a full statement of the basis on which

it is claimed that the information should be withheld from public disclosure.

8107210221 810623

PDR ADOCK 05000344

O

PDR

.

.

.

.

Portland General Electric Company

-2-

June 23, 1981

This section further requires the statement to address with specificity

the considerations listed in 10 CFR 2.790(b)(4). -The information sought

to be withheld shall be incorporated as far as possible into a separate

part of the affidavit.

If we do not hear from you in this regard within

the specified periods noted above, the report will be placed in the Public

Document Room.

Should you have any questions concerning this inspection, we will be glad

to discuss them with you.

Sincerely,

Rws

, G. S. Spencer, Director

Division of Technical Inspection

Enclosures:

A.

Notice of Violation

8.

IE Inspection Report

No. 50-344/81-12

cc w/o enclosure B:

C. P. Yundt, PGE