- UNITb STATES
Do
'
l'
NUCLEAR REGULATORY COMMISSION
-
o
3
- E
REGION 111
799 ROOSEVELT ROAD
o,
8
g ' .A
GLEN ELLYN. lLLINOIS 60137
,o
. ...
FJUL
o mm
e / g' /
e
Docket No. 50-373
Docket No. 50-374
(
3-
%
~ ) j-
.
'
v
.
'k
UL
'
'
Commonwealth Edison Company
.9
'
ATTN:
Mr. Cordell Reed
2
JUL 2 01981 *
Vice President
e m on
2
.-
Post Office Box 767
couum"
Chicago, IL 60690
4..
y
Gentlemen:
Vl
This refers to the routine safety inspection conducted by
Messrs. K. A. Connaughton, K. R. Baker, R. D. Schulz, M. L. Gildner,
M. M. Holzmer, and J. M. Peschel of this effice on April 6-10, April 13-17,
April 27 through May 1, and May 26-E , 1981, of activities at LaSalle County
Station authorized by NRC Const uction Permits No. CPPR-99 and No. CPPR-100
,
'
and to the discussion of our fi.idings with Mr. B. Stephenson, Mr. J. Maley,
and others of your staff at the conclusion of the inspection.
This was an indepth inspection to review the implementaticn of your Quality
Assurance program in selected areas to determine the facility's readiness for
operation with respect to Quality Assurance as discussed in the enclosed copy
of our inspection report. Within this area, the inspection consisted of a
selective examination of procedures and representative records, observations,
and interviews with personnel.
Durine this inspection, certain of your activities appeared to be in noncom-
pliance with NRC requirements, as described in the enclosed Appendix A.
With
respect ta item one, the inspection showed that action had been taken to correct
the identified noncompliance and to prevent recurrenct
Consequently, no reply
to this item of noncompliance is required and we have no
.rther questions
regarding this matter at this time.
Regarding the remaining items, a written
response is required.
In accordance with 10 CFR 2.790 of the Commission's regulations, a copy of
this letter and the enclosed inspection report will be placed in the NRC's
Public Document Room.
If this report contains any information that you or
your contractors believe to be exempt from disclosure under 10 CFR 9.5(a)(4),
it is necessary that you (a) notify this office by telephone within seven (7)
days from the date of this letter of your intention to file a request for
16.O/
s
/ f
,
8107210133 010708
PDR ADOCK 05000373
o
_
-
_
--
.
,
.-
_ _ _ -
_
.
-- .
s
2-
tJUL
8 N81
Commonwealth Edison Company
-
withholding; and (b) submit within twenty-five (25) days from the date of this
letter a written application to this office to withhold such information.
Section 2.790(b)(1) requires that any such application must be accompanied by
an affidavit executed by the owner of the information which identifies the
document or part sought to be withheld, and which contains a full statement of
the reasons on the basis which it is claimed that the information should be
withheld from public disclosure. This section further requires the statement
to address with specificity the considerations listed in 10 CFR 2.790(b)(4).
The information sought to be withheld shall be incorporated as far as possible
into a separate part of the affidavit.
If we do not hear from you in this
regard within the specified periods noted above, a copy of this letter and the
enclosed inspection report will be placed in the Public Document Room.
>
We will gladly discuss any questions you have concerning this inspection.
Sincerely,
'
6.f. Y N
C. E. Norelius, Acting Director
Division of Engineering and
Technical Inspection
Enclosures:
1.
Appendix A, Notice
of Violation
2.
IE Inspection Reports
'
No. 50-373/81-22 and
No. 50-374/81-12
cc w/encls:
J. S. Abel, Director
i
of Nuclear Licensing
L. J. Burke, Site
.
Construction Superintendent
T. E. Quaka, Quality
Assurance Supervisor
R. H. Holyoak, Station
Superintendent