ML20009B728

From kanterella
Jump to navigation Jump to search
Affidavit Re Shoreham Opponents Coalition Contention 12 (Part 2).Final Fatigue Evaluation Results Scheduled for Submittal to NRC in Aug 1981
ML20009B728
Person / Time
Site: Shoreham File:Long Island Lighting Company icon.png
Issue date: 07/13/1981
From: Mccaffrey B
LONG ISLAND LIGHTING CO.
To:
Shared Package
ML20009B708 List:
References
NUDOCS 8107170100
Download: ML20009B728 (4)


Text

%

UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION Before the Atomic Safety and Licensing Board In the Matter of

)

)

LONG ISLAND LIGHTING COMPANY

)

Docket No. 50-322

)

(Shoreham Nuclear Power Station

)

Unit 1)

)

AFFIDAVIT OF BRIAN R. MCCAFFREY CONCERNING SOC CONTENTION 12 (PART TWO)

Brian R.

McCaffrey, being duly saorn, states as follows:

1.

I am Manager, Project Engineering for Shoreham for the Long Island Lighting Company.

A s.tatement of my professional qualifications is attached to LILCO's Motion for Summary Disposition of SOC Contention 3.

2.

The Shoreham downcomer design has always included bracing of the downcomers.

In contrast, the original design of the LaSalle and Zimmer plants did not have a downcomer bracing system.

As a result of the hydrodynamic loads identified in the Mark II program, a decision was made to install a downcomer bracing system similar to Shoreham's.

3.

A structural review of the downcomer bracing system response to hydrodynamic loads in combination with seismic and other design basis loads was initiated in compliance with NRC Acceptance Criteria issued in October 1978.

To reduce the 8107170100 810713 PDR ADOCK 05000322 0

pog

impact loads on the bracing caused by water level increases during pool swell, the bracing was lowered to just above normal water level in 1979.

Before deciding to reconnect the bracing system-to the containment, extensive annlysis was conducted.

That analysis indicated that interconnection of downcomers without restraint ties to the pedestal or containment structure is the optimum configuration for Shoreham.

This optimization was based on the overall = tress, despite the fa -t that the calculated stress due to seismic.' cads is higher when the downcomers are disconnected. Thus, the bracing system at Shoreham was not connected to the reactor vessel pedestal.

The current margin of safety (code allowable minus maximum calculated stress) for the Shoreham downcomers is approximately 70% of the maximum calculated stress.

4. The submerged structure loads described in Shoreham Design Assessment Report (DAR) Revision 4, Appendix K have been l

included in the assessment of the downcomer bracing.

The contro'lling loads for downcomer bracing are pool swell leads and not submerged structure loads.

This is explained in Section 8.5 of DAR Revision 4.

Because this is so, the bracing system safety margins are not significantly affected by changes in the submerged structure load def...

-ions.

5.

The Shoreham SER open item on steam condensation l

l lateral loads, SER section 1.7 (item 27), concerned Shoreham's use of the Mark II Long Term Program (LTP) methodology

urrently under NRC review. The NRC has already approved l

.. interim Mark II acceptance criteria in NUREG-0487.

But LILCO analyzed Shoreham using the criteria te be applied in the long term program, which, at the time the SER was issued, had not yet been approved by the NRC.

Subsequently, in a Mark II Owners Group /NRC meeting on May 29, 1981, the NRC Staff indicated its intention to accept the LTP methodology for steam condensation lateral loads and to document this acceptance in a forthcoming NUREG.

As noted above, Shoreham used this 1.

methodology and it shows that the Shoreham design can accomodate steam condensation lateral loads.

6.

The Shoreham SER c,sen item on steam condensation oscillation and chugging loads, SER section 1.7 (item 28), also involved Sh..

3 decision to vce a load definition similar to the final LTP generic load definition.

Shoreham's load definition is more conservative than the NRC interim criteria al.J, therefore, the current analysis for Shoreham is more stringent than uhat now required by the Staff on an interim bas 4s. Thus, the Shoreham design is adequate to accom.nodate condensation oscillation and chugging loads.

7.

Another SER issue re.'.ated to the downcomers involves tatigue analysis.

LILCO has committed to perform such an analysis and the work is in progress.

Preliminary results presented to the NRC on June 3, 1981, sh;wed a considerable i

l l

3

.. safety margin in the fatigue usage factor. Final fatigue evaluation results are scheduled for submittal to the NRC in August 1981.

Thus, fatigue failure is not a problem at Shoreham.

Brian R. McCaffrey Manager Project Engineering, Shoreham Nuclear Power Station LONG ISLAND LIGHTING COMPANY July 13, 1981 i

l l

l i

l l

l t

l l

,/