ML20009B090

From kanterella
Jump to navigation Jump to search
Forwards IE Insp Repts 50-329/81-06 & 50-330/81-06 on 810318 & 0512.No Noncompliance Noted
ML20009B090
Person / Time
Site: Midland
Issue date: 05/22/1981
From: Norelius C
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Jackie Cook
CONSUMERS ENERGY CO. (FORMERLY CONSUMERS POWER CO.)
Shared Package
ML20009B091 List:
References
NUDOCS 8107140766
Download: ML20009B090 (2)


See also: IR 05000329/1981006

Text

d

pne

f

o

UNITED STAYES

gk

i

~

8

NUCLEAR REGULATORY COMMISSION

n

[

$

E

REGION lli

()$l[-

799 ROOSEVELT ROAD

0,

g

GLEN ELLYN. ILLINOIS 60137

% * * * . * o-

g3

.MAY 2 21981

Docket No. 50-329

m

Docket No. 50-330

A

Consumers Power Company

B

ATTN:

Mr. James W. Cook

-

-

Vice President

&

JUI. O S

-

Midland Project

3

u.s,

b .M

1945 West Parnall Road

aDC83 ,D

g

Jackson, MI 49201

{#

b

Gentlemen:

g

This refers to the routine safety inspection conducted by Mr. K. D. Ward

of this office on March 18, and May 12, 1981, of activities at the Midland

Plant authorized by NRC Construction Permits No. CPPR-81 and No. CPPR-82

and to the discussion of our findings with Mr. D. Turnbull at the conclusion

of the inspection.

The enclosed copy of our inspection report identifies areas examined during

the inspection. Within these areas, the inspection consisted of a selective

examination of procedures and representative records, observations, and

interviews with personnel.

No items of noncompliance with NRC requirements were identified during

the course of this inspection.

In accordance with 10 CFR 2.790 of the Commission's regulations, a copy of

this letter and tLe enclosed inspection report will be placed in the NRC's

Public Document Loom.

If this report contains any information that you or

your contractors believe to be exempt from disclosure under 10 CFh 9.5(a)(4),

it is necessary that you (a) notify this office by telephone within seven (7)

,

days from the date of this letter of your intention to file a request for

withholding; and (b) submit within twenty-five (25) days from the date of

this letter a written application to this office to withhold such infor-

mation. Section 2.790(b)(1) requires that any such application must be

accompanied by an affidavit executed by the owner of the information which

identifies the document or part sought to be withheld, and which contains

a full statement of the reasons on the basis which it is claimed that the

8107140766 810522

.

PDR ADOCK 05000329

G

PDR

F

l.

Consumers Power Company

-2-

'M

,

2 2 Gst

information should be withheld from public disclosure. This section further

requires the statement to address with specificity the considerations listed

in 10 CFR 2.790(b)(4). The information sought to be withheld shall be

incorporated as far as possible into a separate part of the affidavit.

If

we do not hear from you in this regard within the specified periods noted

above, a copy of this letter and the enclosed inspection report will be

placed in the Public Document Room.

We will gladly discuss any questions you have concerning this inspection.

Sincerely,

C. E. Norelius, Acting Director

Division of Engineering and

Technical Inspection

Enclosure:

IE Inspection

Report No. 50-329/81-06

and No. 50-330/81-06

cc w/ encl:

Central Files

Reproduction Unit NRC 20b

Resident Inspector, RIII

PDR

Local PDR

NSIC

TIC

Ronald Callen, Michigan

Public Service Comission

Myron H. Cherry

,

RIII

RIII

RI

RIII

-

RI'I

,

'jp

e

n

Sp sard

B d

N rel

y

5/21/81

p

/

h/