UNITED STATES
4,
-* 1
NUCLEAR REGULATORY COMMisslON
.,f
h
REGION I
en
'g
631 PARK AVENUE
E
KthG OF PRUSSI A, PENNSYl.V ANI A 19406
c,
January 15, 1981
Docket No. 50-320
eie f
Metropolitan Edison Company
O*
M
6
ATTN: Mr. Gale Hovey
Vice President and
(g
EgJ
Director of TMI-2
g.
P
100 Interpace Parkway
g
J-
-
r
Parsippany, New Jersey 07054
S
-
Gentlemen:
O
Subject:
Inspection 50-320/80-16
m
This refers to the special inspection conducted by Dr. M. Shanbaky of
this office on September 15 - October 27, 1980, of activities authorized
by NRC License No. DPR-73 and to the discussions of our findings held by
Dr. Shanbaky with Mr. J. Brasher of your staff at the conclusion of the
inspection.
Areas examined during this inspection are described in the Office of
Inspection and Enforcement Report which is enclosed with this letter.
Within these areas, the inspection consisted of selective examinations
of procedures and representative records, interviews with personnel, and
observations by the inspector.
Within the scope of this inspection, no items of noncompliance were
observed.
However, the recovery quarterly progress report (QPR) for the
third quarter of 1980 which you submitted to this office October 15, 1980,
describes several corrective actions to be taken for the Unit 2 Radiologica'l
Controls Program. This inspection revealed that many due dates for
completion of corrective action were overdue without new dates provided
and/or explanation for why these commitment dates were not met. We are
concerned about your failure to meet comitment dates in this area
without updating and/or explanatien. Accordingly in your next status
report (dueJanuary 15,1981) for each overdue outstanding item please
address with specificity the reason for delay and provide a new but finn
completion date.
An item should be considered overdue if it was not
corrected by the date provided in the QPR for the first quarter 1980.
81030907t5
Q
.
.
.
,
Metropolitan Edison Company
2
January 15, 1981
In accordance with Section 2.790 of the NRC's " Rules of Practice,"
Part 2, Title 10, Code of Federal Regulations, a copy of this letter and
the enclosed inspection report will be placed in the NRC's Public
Document Room.
If this report contains any information that you (or
your contractor) believe to be proprietary, it is necessary that you
make a written application within 20 days to this office to withhold
such information from public disclosure.
Any such application must be
accompanied by an affidavit executed by the owner of the information,
which identifies the document or part sought to be withheld, and which
contains a statement of reasons which addresses with specificity the
items which will be considered by the Comission as listed in subpara-
graph (b) (4) of Section 2.790. The information sought to be withheld
shall be incorporated as far as possible into a separate part of the
If we do not hear from you in this regard within the specified
period, the report will be placed in the Public Document Room.
No reply tr.; this letter is required; however, should you have any
questions concerning this inspection, we will be pleased to discuss them
with you.
Sincerely,
,
H. Grier
Director
Enclosure:
1.
Office of Inspection and Enforcement Inspection Report
Number 50-320/80-16
cc w/ enc 1:
,
J. J. Barton, Manager Site Operations, TMI-2
E. D. Fuller, TMI-2 Licensing Supervisor
E. G. Wallace, PWR Licensing Manager
J. B. Liberman, Esquire
G. F. Trowbridge, Esquire
Ms. Mary V. Southard, Chairman, Citizens for a Safe Environment (Without Report)
.
"-'