Letter to Southern Nuclear Operating Company Regarding Nrc'S Stretch Goal for the 10 CFR 52.103(g) Finding on Vogtle Electric Generating Plant Units 3 and 4
ML20006D963
Person / Time
Site: Vogtle  Southern Nuclear icon.png
Issue date: 01/08/2020
From: Mark King
NRC/NRR/VPOB
To: Yox M
Southern Nuclear Operating Co
James Gaslevic Ex. 2776
References
Download: ML20006D963 (6)


Text

January 8, 2020 Mr. Michael J. Yox, Director Regulatory Affairs Southern Nuclear Operating Company, Inc.

7825 River Road Waynesboro, GA 30830

SUBJECT:

STRETCH GOAL FOR THE 10 CFR 52.103(G) FINDING ON VOGTLE UNITS 3 AND 4

Dear Mr. Yox:

The U.S. Nuclear Regulatory Commission (NRC) staff recently held two Category 1 public meetings with Southern Nuclear Operating Company (SNC) at NRC Headquarters to identify ways to safely reduce the time required by the NRC for making the Title 10 of the Code of Federal Regulations (10 CFR) Section 52.103(g) finding following receipt of an all inspection, test, analysis, and acceptance criteria (ITAAC) complete notification (required by 10 CFR 52.99(c)(4)) for the Vogtle Electric Generating Plant Units 3 and 4.

On August 13, 2019, the NRC staff presented a best-case stretch goal processing timeline which assumed all prerequisites were met (as shown on the NRC meeting slides in the Agencywide Documents Access and Management System (ADAMS) under Accession Number ML19224A924). The staff discussed the prerequisites and compared the stretch goal timeline against the timeline shown in NRR-LIC-114 / NRO Office Instruction NRO-REG-106, Title 10 of the Code of Federal Regulations (10 CFR) Section 52.103(g) Finding and Communication Process, (ADAMS Accession Number ML18267A001), that projects a 17-day timeline to complete the process. The meeting summary can be found at ADAMS Accession No. ML19234A061.

On September 10, 2019, the NRC staff presented draft notifications to be submitted on the 10 CFR 52.103(g) finding process for SNC's Vogtle Electric Generating Plant Units 3 and 4, as well as different scenarios that could affect the expected time to process the 10 CFR 52.103(g) finding. The meeting summary can be found at ADAMS Accession No. ML19259A065. During this meeting, SNC discussed the prerequisites that the NRC would need from SNC in order to safely reduce the 52.103(g) processing time. The meeting slides submitted by SNC can be found under Accession Number ML19249C726.

As discussed in the meetings, the NRC will prioritize safely reducing the administrative processing time for making the 10 CFR 52.103(g) finding to the minimum time necessary. The minimum time necessary could vary from the best-case stretch goal timeline to up to 17 days, as describe in the office instruction, depending on the degree to which the prerequisites are able

M. Yox to be satisfied by SNC. The NRC staff acknowledge that all prerequisites may not be fully achievable due to the realities of a dynamic construction environment and encourage SNC to keep NRC staff informed of potential challenges in meeting the prerequisites.

If you have any questions, please contact James Gaslevic at (301) 415-2776 or James.Gaslevic@nrc.gov.

Sincerely,

/RA/

Michael King, Director Vogtle Project Office Office of Nuclear Reactor Regulation Docket Nos.: 52-025 and 52-026 cc: see next page

ML20006D963 NRR-106 OFFICE NRR/VPO:PM NRR/VPO:LA NRR/VPO: BC NRR/VPO:D NAME JGaslevic RButler VHall MKing DATE 1/6/2020 1/7/2020 1/7/2020 1/8/2020 Vogtle Mailing List (Revised 11/12/2019) cc:

Resident Manager Resident Inspector Oglethorpe Power Corporation Vogtle Plant Units 3 & 4 Alvin W. Vogtle Nuclear Plant 8805 River Road 7821 River Road Waynesboro, GA 30830 Waynesboro, GA 30830 Mr. Barty Simonton Office of the Attorney General Team Leader 40 Capitol Square, SW Environmental Radiation Program Atlanta, GA 30334 Air Protection Branch Environmental Protection Division Southern Nuclear Operating Company 4244 International Parkway, Suite 120 Document Control Coordinator Atlanta, GA 30354-3906 3535 Colonnade Parkway Birmingham, AL 35243 Brian H. Whitley Regulatory Affairs Director Anne F. Appleby Southern Nuclear Operating Company Olgethorpe Power Corporation 3535 Colonnade Parkway, BIN N-226-EC 2100 East Exchange Place Birmingham, AL 35243 Tucker, GA 30084 Mr. Michael Yox County Commissioner Site Regulatory Affairs Director Office of the County Commissioner Vogtle Units 3 & 4 Burke County Commission 7825 River Road, Building 302 (ESB)

Waynesboro, GA 30830 Bin 6031 Waynesboro, GA 30830 Mr. Wayne Guilfoyle Commissioner District 8 Augusta-Richmond County Commission 4940 Windsor Spring Rd Hephzibah, GA 30815 Gwendolyn Jackson Burke County Library 130 Highway 24 South Waynesboro, GA 30830 Mr. Reece McAlister Executive Secretary Georgia Public Service Commission Atlanta, GA 30334 Page 1 of 3

Vogtle Mailing List Email aagibson@southernco.com (Amanda Gibson) acchambe@southernco.com (Amy Chamberlian) awc@nei.org (Anne W. Cottingham) becky@georgiawand.org (Becky Rafter) bhwhitley@southernco.com (Brian Whitley)

Bill.Jacobs@gdsassociates.com (Bill Jacobs) corletmm@westinghouse.com (Michael M. Corletti) crpierce@southernco.com (C.R. Pierce) dahjones@southernco.com (David Jones) david.hinds@ge.com (David Hinds) david.lewis@pillsburylaw.com (David Lewis) dlfulton@southernco.com (Dale Fulton) ed.burns@earthlink.net (Ed Burns) edavis@pegasusgroup.us (Ed David)

G2NDRMDC@southernco.com (SNC Document Control)

George.Taylor@opc.com (George Taylor) harperzs@westinghouse.com (Zachary S. Harper) james1.beard@ge.com (James Beard)

JHaswell@southernco.com (Jeremiah Haswell) jim@ncwarn.org (Jim Warren)

John.Bozga@nrc.gov (John Bozga)

Joseph_Hegner@dom.com (Joseph Hegner) karlg@att.net (Karl Gross) kmstacy@southernco.com (Kara Stacy) kroberts@southernco.com (Kelli Roberts)

KSutton@morganlewis.com (Kathryn M. Sutton) kwaugh@impact-net.org (Kenneth O. Waugh) markus.popa@hq.doe.gov (Markus Popa) mdmeier@southernco.com (Mike Meier) media@nei.org (Scott Peterson)

Melissa.Smith@Hq.Doe.Gov (Melissa Smith) mike.price@opc.com (M.W. Price)

MKWASHIN@southernco.com (MKWashington) mphumphr@southernco.com (Mark Humphrey)

MSF@nei.org (Marvin Fertel) nirsnet@nirs.org (Michael Mariotte)

Nuclaw@mindspring.com (Robert Temple)

Paul@beyondnuclear.org (Paul Gunter) pbessette@morganlewis.com (Paul Bessette) ppsena@southernco.com (Peter Sena,III) r.joshi15@comcast.net (Ravi Joshi) rwink@ameren.com (Roger Wink) sabinski@suddenlink.net (Steve A. Bennett) sara@cleanenergy.org (Sara Barczak)

Page 2 of 3

Vogtle Mailing List sblanton@balch.com (Stanford Blanton)

Shiva.Granmayeh@hq.doe.gov (Shiva Granmayeh) sjackson@meagpower.org (Steven Jackson) sjones@psc.state.ga.us (Shemetha Jones) skauffman@mpr.com (Storm Kauffman) slieghty@southernco.com (Steve Leighty) sroetger@psc.state.ga.us (Steve Roetger) syagee@southernco.com (Stephanie Agee)

TomClements329@cs.com (Tom Clements)

Vanessa.quinn@dhs.gov (Vanessa Quinn) wayne.marquino@gmail.com (Wayne Marquino) weave1dw@westinghouse.com (Doug Weaver)

William.Birge@hq.doe.gov (William Birge)

X2edgran@southernco.com (Eddie R. Grant) x2gabeck@southernco.com (Gary Becker)

X2hagge@southern.com (Neil Haggerty)

X2wwill@southernco.com (Daniel Williamson)

Page 3 of 3