JAN l 01990
In Reply Refer To:
Dockets:
50-313/89-46
50 368/89-46
!
Arkansas Power & Light Company
ATTN: Gene Campbell, Vice President
i
Huclear Operations
!
P.O. Box 551
Little Rock, Arkansas 72203
.}
Gentlemen:
This refers to the inspection conducted by Mr. C. E. Johnson of this office
,
during the period December 4 through 8,1989, of activities authorized by NRC
Operating Licenses DPR-51 and NPF-6 for Arkansas Nuclear One, Units 1 and 2,
'
respectively, and to the discussion of our findings with members of your staff
et the conclusion of the inspection.
,
Areas examined during the inspection included followup on licensee event
reports (LERs), previous inspection findings, and testing of pipe supports
!
(Unit 1). Within these areas, the inspection consisted of selective
examination of procedures and re)resentative records, interviews with
r
personnel, and observations by tie inspector. The inspection findings are
documented in the enclosed inspection report.
l
Within the scope of the inspection, no violations or deviations were
[
identified.
1
Should you have any questions concerning this inspection, we will be pleased to
discuss them with you.
Sincerely,
l
Original SVwo @
!
Sunuel J. Coilins
'
S muel J. Collins, Director
Division of Reactor Projects
Enclosure:
Appendix - NRC Inspection Report
.
50-313/89-46
50-368/89-46
cc w/ enclosure:
(seenextpage)
[
C:PSS*2
D:DRSb g@l ,
M
d
f
RIV:RI:PSS*c 4
CJohnson/cjg
TStetk
LJCallah
111ns
i /ci/90-
)/cg/90
) /3 /90
90
- previously concurred
'
9001180102 900110
ADOCKOS00g3j3
_
g7
FDR
%
_,
'
.
.
,
,
.
Arkansas Power & Light Company
-2-
Arkansas Nuclear One
ATTN: Early Ewing, General Manager
Technical Support and Assessment
P.O. Box 608
Russellville, Arkansas 72801
Arkansas Nuclear One
ATTN: Neil Carns. Director
Nuclear Operations
P.O. Box 608
Russellville, Arkansas 72801
Combustion Engineering Inc.
,
ATTil: Charles B. Brinkman, Manager
Washington Nuclear Operations
12300 Twinbrook Parkway, Suite 330
Rockville, Maryland 20852
Honorable Joe W. Phillips
County Judge of Pope County
Pope County Courthouse
Russellville, Arkansas 72801
Bishop, Cook, Purcell & Reynolds
ATTN: Nicholas S. Reynolds, Esq.
1400 L Street, N.W.
Washington, D.C.
20005-3502
ATTN: Ms. Greta Dicus, Director
Division of Environmental llcalth
Protection
4815 West Markan Street
Little Rock, Arkansas 72201
Babcock & Wilcox
Nuclear Power Generation Division
ATTH: Mr. Robert B. Borsum
1700 Rockville Pike, Suite 525
Rockville, Maryland 20852
U.S. Nuclear Regulatory Commission
ATTN: Senior Resident Inspector
1 Nuclear Plant Road
Russellville, Arkansas 72801
U.S. Nuclear Regulatory Comission
ATTN: Regional Administrator, Region IV
611 Ryan Plaza Drive, Suite 1000
Arlington, Texas 76011
'
.
.
,
,
Arkansas Power & Light Company
-3-
bectoDMB(IE01)
'
bec distrib. by RIV:
,
- R. D. Martin
- Resident Inspector
- DRSS-FRPS
- SectionChief(DRP/A)
Lisa Shea, RM/ALF
- RIV File
'
- DRP
- MIS System
- RSTS Operator
- ProjectEngineer(DRP/A)
- DRS
- C. Harbuck, NRR Project Manager (HS:
13-D-18)
- C, Posiusny, NRR Project Manager (MS: 13-D-18)
- C. Johnson
- T. Stetta
'
- w/766
,
6