MONTHYEARML20217H5221999-09-30030 September 1999 Monthly Operating Repts for Sept 1999 for Byron Station, Units 1 & 2.With ML20212B9261999-08-31031 August 1999 Monthly Operating Repts for Aug 1999 for Byron Station,Units 1 & 2.With ML20210R3431999-07-31031 July 1999 Monthly Operating Repts for July 1999 for Byron Station, Units 1 & 2.With ML20209H3711999-06-30030 June 1999 Monthly Operating Repts for June 1999 for Byron Station, Units 1 & 2.With ML20195J8001999-05-31031 May 1999 Monthly Operating Repts for May 1999 for Byron Station,Units 1 & 2.With ML20206R6991999-04-30030 April 1999 Monthly Operating Repts for Apr 1999 for Byron Station Units 1 & 2.With ML20205P7001999-03-31031 March 1999 Monthly Operating Repts for Mar 1999 for Byron Station,Units 1 & 2.With ML20204C7671999-02-28028 February 1999 Monthly Operating Repts for Feb 1999 for Byron Station,Units 1 & 2.With ML20199E6371998-12-31031 December 1998 Monthly Operating Repts for Dec 1998 for Byron Station,Units 1 & 2.With ML20198D1501998-11-30030 November 1998 Monthly Operating Repts for Nov 1998 for Byron Nuclear Power Station,Units 1 & 2.With ML20195F8321998-10-31031 October 1998 Monthly Operating Repts for Oct 1998 for Byron Nuclear Power Station,Units 1 & 2.With ML20154L5501998-09-30030 September 1998 Monthly Operating Repts for Sept 1998 for Byron Nuclear Power Station,Units 1 & 2.With ML20197C9051998-08-31031 August 1998 Monthly Operating Repts for Aug 1998 for Byron Nuclear Power Station,Units 1 & 2.With ML20151Z9651998-08-31031 August 1998 Revised MOR for Aug 1998 for Byron Nuclear Power Station. Rept Now Includes Page 9 Which Was Omitted from Previously Issued Rept ML20237B4841998-07-31031 July 1998 Monthly Operating Repts for July 1998 for Byron Nuclear Power Station Units 1 & 2 ML20236R1531998-06-30030 June 1998 Monthly Operating Repts for June 1998 for Byron Nuclear Power Station,Units 1 & 2 ML20248M3071998-05-31031 May 1998 Monthly Operating Repts for May 1998 for Byron Nuclear Station,Units 1 & 2 ML20247J9091998-04-30030 April 1998 Monthly Operating Repts for Apr 1998 for Byron Nuclear Power Station,Units 1 & 2 ML20216D5881998-03-31031 March 1998 Monthly Operating Repts for Mar 1998 for Byron Nuclear Power Station,Units 1 & 2 ML20248L1531998-02-28028 February 1998 Monthly Operating Repts for Feb 1998 for Byron Nuclear Power Station,Units 1 & 2 ML20202G1881998-01-31031 January 1998 Monthly Operating Repts for Jan 1998 for Byron Nuclear Power Station,Units 1 & 2 ML20198P2461997-12-31031 December 1997 Monthly Operating Repts for Dec 1997 for Byron Nuclear Power Station,Units 1 & 2 ML20197F1201997-11-30030 November 1997 Monthly Operating Repts for Nov 1997 for Byron Nuclear Power Station,Units 1 & 2 ML20199D1491997-10-31031 October 1997 Monthly Operating Repts for Oct 1997 for Byron Nuclear Power Station Units 1 & 2 ML20211P8861997-09-30030 September 1997 Monthly Operating Repts for Sept 1997 for Byron Nuclear Power Station,Units 1 & 2 ML20217A9031997-08-31031 August 1997 Monthly Operating Repts for Aug 1997 for Byron Nuclear Power Station,Units 1 & 2 ML20211P9061997-08-31031 August 1997 Corrected Page 8 of Monthly Operating Rept for Aug 1997 for Byron Nuclear Power Station,Units 1 & 2 ML20210L4061997-07-31031 July 1997 Monthly Operating Repts for Jul 1997 for Byron Nuclear Power Station,Units 1 & 2 ML20149D9441997-06-30030 June 1997 Monthly Operating Repts for June 1997 Byron Nuclear Power Station,Units 1 & 2 ML20210L4111997-05-31031 May 1997 Corrected Page 6 of Monthly Operating Rept for May 1997 for Byron Nuclear Power Station,Unit 1 ML20141C3081997-05-31031 May 1997 Monthly Operating Repts for May 1997 for Byron Nuclear Power Station,Units 1 & 2 ML20141E2491997-04-30030 April 1997 Monthly Operating Repts for Apr 1997 for Byron Nuclear Power Station,Units 1 & 2 ML20141C3491997-04-30030 April 1997 Corrected Pp 4 & 10 of Monthly Operating Rept for Apr 1997 for Byron Nuclear Power Station,Units 1 & 2 ML20140D7511997-03-31031 March 1997 Monthly Operating Repts for Mar 1997 for Byron Nuclear Power Station,Units 1 & 2 ML20141C3281997-03-31031 March 1997 Corrected Page 4 of Monthly Operating Rept for Mar 1997 for Byron Nuclear Power Station,Unit 1 ML20141C3131997-02-28028 February 1997 Corrected Pp 4 & 6 of Monthly Operating Rept for Feb 1997 for Byron Nuclear Power Station,Unit 1 ML20136H5811997-02-28028 February 1997 Monthly Operating Repts for Feb 1997 for Byron Nuclear Power Station,Units 1 & 2 ML20134L8651997-01-31031 January 1997 Monthly Operating Repts for Jan 1997 for Byron Nuclear Power Station ML20133M2391996-12-31031 December 1996 Monthly Operating Repts for Dec 1996 for Byron Nuclear Power Station,Units 1 & 2 ML20132C4521996-11-30030 November 1996 Monthly Operating Repts for Nov 1996 for Byron Nuclear Power Station,Units 1 & 2 ML20134N0561996-10-31031 October 1996 Monthly Operating Rept for Oct 1996 for Byron Nuclear Power Station,Units 1 & 2 ML20129A6861996-09-30030 September 1996 Monthly Operating Repts for Sept 1996 for Byron Nuclear Power Station Units 1 & 2 ML20117N5051996-08-31031 August 1996 Monthly Operating Repts for Aug 1996 for Byron Nuclear Power Station,Units 1 & 2 ML20134N0861996-08-31031 August 1996 Revised Monthly Operating Rept for Aug 1996 for Byron Unit 2 ML20134N0631996-07-31031 July 1996 Revised Monthly Operating Rept for Jul 1996 for Byron Unit 1 ML20116M6481996-07-31031 July 1996 Monthly Operating Rept for July 1996 for Bs NPP Units 1 & 2 ML20115E2141996-06-30030 June 1996 Monthly Operating Repts for June 1996 for Byron Nuclear Power Plant Units 1 & 2 ML20117M3851996-05-31031 May 1996 Monthly Operating Repts for May 1996 for Byron Nuclear Power Station ML20117G6261996-04-30030 April 1996 Monthly Operating Repts for Apr 1996 for Byron Nuclear Power Station Units 1 & 2 ML20101R6151996-03-31031 March 1996 Monthly Operating Repts for Mar 1996 for Byron Nuclear Power Station 1999-09-30
[Table view] Category:TEXT-SAFETY REPORT
MONTHYEARML20217H5221999-09-30030 September 1999 Monthly Operating Repts for Sept 1999 for Byron Station, Units 1 & 2.With ML20217P6351999-09-29029 September 1999 Non-proprietary Rev 6 to HI-982083, Licensing Rept for Spent Fuel Rack Installation at Byron & Braidwood Nuclear Stations ML20217A1691999-09-22022 September 1999 Part 21 Rept Re Engine Sys,Inc Controllers,Manufactured Between Dec 1997 & May 1999,that May Have Questionable Soldering Workmanship.Caused by Inadequate Personnel Training.Sent Rept to All Nuclear Customers ML20212B9261999-08-31031 August 1999 Monthly Operating Repts for Aug 1999 for Byron Station,Units 1 & 2.With ML20210R3431999-07-31031 July 1999 Monthly Operating Repts for July 1999 for Byron Station, Units 1 & 2.With ML20210E2251999-07-21021 July 1999 B1R09 ISI Summary Rept Spring 1999 Outage, 980309-990424 ML20209G1751999-07-0808 July 1999 SG Eddy Current Insp Rept,Cycle 9 Refueling Outage (B1R09) ML20207H7941999-06-30030 June 1999 Rev 0 to WCAP-15180, Commonwealth Edison Co Byron,Unit 2 Surveillance Program Credibility Evaluation ML20207H8071999-06-30030 June 1999 Rev 0 to WCAP-15178, Byron Unit 2 Heatup & Cooldowm Limit Curves for Normal Operations ML20207H7851999-06-30030 June 1999 Rev 0 to WCAP-15183, Commonwealth Edison Co Byron,Unit 1 Surveillance Program Credibility Evaluation ML20207H7771999-06-30030 June 1999 Rev 0 to WCAP-15177, Evaluation of Pressurized Thermal Shock for Byron,Unit 2 ML20209H3711999-06-30030 June 1999 Monthly Operating Repts for June 1999 for Byron Station, Units 1 & 2.With ML20207H7561999-06-28028 June 1999 Pressure Temp Limits Rept (Ptlr) ML20207H7621999-06-28028 June 1999 Pressure Temp Limits Rept (Ptlr) ML20195J8001999-05-31031 May 1999 Monthly Operating Repts for May 1999 for Byron Station,Units 1 & 2.With ML20207B6481999-05-25025 May 1999 SER Accepting Revised SGTR Analysis for Byron & Braidwood Stations.Revised Analysis Was Submitted to Support SG Replacement at Unit 1 of Each Station ML20195B2591999-05-19019 May 1999 Rev 66a to CE-1-A,consisting of Proposed Changes to QAP for Dnps,Qcs,Znps,Lcs,Byron & Braidwood Stations ML20206R6991999-04-30030 April 1999 Monthly Operating Repts for Apr 1999 for Byron Station Units 1 & 2.With ML20195C7961999-04-28028 April 1999 Rev 2 to NFM9800233, Byron Station Unit 2 COLR for Cycle 8A (BY2C8A) M980023, Rev 2 to NFM9800233, Byron Station Unit 2 COLR for Cycle 8A (BY2C8A)1999-04-28028 April 1999 Rev 2 to NFM9800233, Byron Station Unit 2 COLR for Cycle 8A (BY2C8A) ML20205P7001999-03-31031 March 1999 Monthly Operating Repts for Mar 1999 for Byron Station,Units 1 & 2.With ML20205B5091999-03-26026 March 1999 SER Accepting Relief Requests 12R-24,Rev 0 & 12R-34,Rev 0, Related to Second 10-year Interval Inservice Insp for Byron Station,Units 1 & 2 ML20205C5101999-03-21021 March 1999 Revised Safety Evaluation Supporting Improved TS Amends Issued by NRC on 981222 to FOLs NPF-37,NPF-66,NPF-72 & NPF-77.Revised Pages Include Editorial Corrections ML20204G3831999-03-19019 March 1999 Safety Evaluation Accepting Second 10-yr Interval ISI Request for Relief 12R-11 M990004, Rev 0 to NFM9900043, Byron Unit 1,Cycle 10 COLR in ITS Format W(Z) Function1999-03-17017 March 1999 Rev 0 to NFM9900043, Byron Unit 1,Cycle 10 COLR in ITS Format W(Z) Function ML20206A8831999-03-17017 March 1999 Rev 0 to NFM9900043, Byron Unit 1,Cycle 10 COLR in ITS Format W(Z) Function ML20207M9231999-03-12012 March 1999 Amended Part 21 Rept Re Cooper-Bessemer Ksv EDG Power Piston Failure.Total of 198 or More Pistons Have Been Measured at Seven Different Sites.All Potentially Defective Pistons Have Been Removed from Svc Based on Encl Results ML20204H9941999-03-0303 March 1999 Non-proprietary Rev 4 to HI-982083, Licensing Rept for Spent Fuel Rack Installation at Byron & Braidwood Nuclear Stations ML20204C7671999-02-28028 February 1999 Monthly Operating Repts for Feb 1999 for Byron Station,Units 1 & 2.With ML20199G8271998-12-31031 December 1998 Rev 1 Comm Ed Byron Nuclear Power Station,Unit 1 Cycle 9 Startup Rept ML20205M7061998-12-31031 December 1998 Unicom Corp 1998 Summary Annual Rept. with ML20202F6181998-12-31031 December 1998 Cycle 8 COLR in ITS Format & W(Z) Function ML20206B4001998-12-31031 December 1998 Annual & 30-Day Rept of ECCS Evaluation Model Changes & Errors for Byron & Braidwood Stations ML20199E6371998-12-31031 December 1998 Monthly Operating Repts for Dec 1998 for Byron Station,Units 1 & 2.With ML20202F6021998-12-31031 December 1998 Cycle 9 COLR in ITS Format & W(Z) Function ML20196K6731998-12-31031 December 1998 10CFR50.59 Summary Rept for 1998 ML20207H7731998-11-30030 November 1998 Rev 0 to WCAP-15125, Evaluation of Pressurized Thermal Shock for Byron,Unit 1 ML20207H8011998-11-30030 November 1998 Rev 0 to WCAP-15124, Byron Unit 1 Heatup & Cooldown Limit Curves for Normal Operation ML20198D1501998-11-30030 November 1998 Monthly Operating Repts for Nov 1998 for Byron Nuclear Power Station,Units 1 & 2.With ML20196A4191998-11-19019 November 1998 Safety Evaluation Accepting QA TR CE-1-A,Rev 66 Re Changes in Independent & Onsite Review Organization by Creating NSRB ML20195F8321998-10-31031 October 1998 Monthly Operating Repts for Oct 1998 for Byron Nuclear Power Station,Units 1 & 2.With 05000454/LER-1998-018, Corrected LER 98-018-00:on 980912,inoperable Unit 1 DG Was Noted.Caused by Low Lube Oil Pressure Condition.Immediately Entered Into Lcoar for AC Sources TS 3.8.1.1,Action a1998-10-0909 October 1998 Corrected LER 98-018-00:on 980912,inoperable Unit 1 DG Was Noted.Caused by Low Lube Oil Pressure Condition.Immediately Entered Into Lcoar for AC Sources TS 3.8.1.1,Action a ML20207H7671998-10-0505 October 1998 Rv Weld Chemistry & Initial Rt Ndt ML20154L5501998-09-30030 September 1998 Monthly Operating Repts for Sept 1998 for Byron Nuclear Power Station,Units 1 & 2.With ML20197C9051998-08-31031 August 1998 Monthly Operating Repts for Aug 1998 for Byron Nuclear Power Station,Units 1 & 2.With ML20151Z9651998-08-31031 August 1998 Revised MOR for Aug 1998 for Byron Nuclear Power Station. Rept Now Includes Page 9 Which Was Omitted from Previously Issued Rept ML20238F6551998-08-28028 August 1998 SE Authorizing Licensee Request for Relief NR-20,Rev 1 & NR-25,Rev 0 Re Relief from Examination Requirement of Applicable ASME BPV Code,Section XI for First ISI Interval Exams ML20237E2331998-08-21021 August 1998 Revised Pages of Section 20 of Rev 66 to CE-1-A, QA Topical Rept ML20237B3361998-08-14014 August 1998 B2R07 ISI Summary Rept,Spring 1998 Outage, 961005-980518 ML20237B4841998-07-31031 July 1998 Monthly Operating Repts for July 1998 for Byron Nuclear Power Station Units 1 & 2 1999-09-30
[Table view] |
Text
_____ _.
C:mmanwcalth Edison Byron Nuclear Station ,
4450 North Gerrnan Church Road Byron, Illinois 61010 December 8, 1989 LTR: BYRON 89-1237 MLE: 2.7.200 Director, Office of Management Information and Program Control United States Nuclear Regulatory Commission Washington, D.C. 20555 ATTH: Document Control Desk Gentlemen: j
~
Enclosed for your information is the Monthly Performance Report covering Byron c Nuclear Power Station f or the period November 1 through November 30, 1989.
Sincerely,
.-/' '.
'. (Oy:t .
R. Plenlewicz Station Manager Byron Nuclear Power Station RP/RA/bb (0625M/0062M) cc A.B. Davis, NRC, Region III NRC Resident Inspector Byron Ill. Dept. of Nuclear Safety T.J. Malman/K.L. Graesser .
Nuclear Licensing Manager Nuclear Fuel Services, PWR Plant Support L. Anastasia, Station Nuclear Engineering INPO Records Center L. 01than - USNRC M
. s glp73gl% hY/8IO M vbR.- Alues - o#***YW yp g {(-
l 'g ..
BYRON NUCLEAR POWER STATION UNIT 1 AND UNIT 2 MONTHLY PERTORMANCE REPORT Cole!ONNEALTH EDISON COMPANY NRC DOCKET NO. 050-454 NRC DOCKET NO.- 050-455-LICENSE NO. NPF-37 .j LICENSE NO. NPF-66 i
q
-l ,
-i
'l
-l (0625M/0062M-2). I
m e,
- 1. M0nthly Report for Byron _ Unit 1 for tha =^=th of Mov--ur 1989_ -
A. E"= =ry of Operatino_Emperience for Unit 1 The unit began this reporting period in Mode 1 (Power Operation) at_99.3%
power. The unit operated at power levels of up;to 100% for the reporting period.
(0625M/0062M-3)
B. OPERATING DATA REPORT DOCKET NO. 050-454 UNITt Byron One DATE: 12/08/89 COMPILED BY R. Aken TELEPHONE: (815)234-5441 x2633 OPEPATING STATUS
- 1. Reporting Periodt November 1989. Gross Hours 720
- 2. Currently Authorized Power Level 3411 (MWt)
Detign Electrical Rating 1175 (MWe-gross)
Design Electrical Rating: 1120 (MWe-net)
Max Dependable Cesacity: 1105 (MWe-net)
- 3. Power Level to Which Restricted (If Any): N/A
- 4. Reasons for Restriction (If Any):
THIS MONTH YR TO DATE CUMULATIVE *
- 5. Report Period Hrs. 720 8,016 36,889
- 6. Rx Critical Hours 720 7,999 29,796
- 7. Rx Reserve Shutdown Hours 0 0 38
- 8. Hours Generator on Line 720 7,994 29,350
- 9. Unit Reserve Shutdown Hours 0 0 0
- 10. Gross Thermal Energy (MWH) 2,426,814 25,535,996 89,063,309
- 11. Gross Elec. Energy (MWH) 624,883 8,696,405 30,009,286
- 12. Het Elec. Energy (MWH) 783,667 8,249,704 28,282,212
- 13. Reactor Service Factor 100 99.8 80.8
- 14. Reactor Availability rector 100 99.8 80.9
- 15. Unit Service rector 100 99.7 79.6
- 16. Unit Availability Tactor 100 99.7 79.6
, 17. Unit Capacity Factor (MDC net) 98.5 93.1 69.4
- 18. Unit Capacity Tactor (DER net) 97.2 91.9 68.5
- 19. Unit Forced. Outage Hrs. 0 22 1057
- 20. Unit Forced Outage Rate 0 0.3 3.5
- 21. Shutdowns Scheduled Over Next 6 Monthat One
- 22. If Shutdown at End of Report Period, Estimated Date of Startupt N/A
- 23. Units in Test Status (Prior to Commercial Operation): None
- Note - The cumulative numbers do not reflect power generated prior to commercial service.-
(0625M/0062M-4)
C. AYERAGE._ DAILY UNIT POWER LEVEL DOCKET NO.: 050-454 UNIT Byron One DATE: 12/08/89 COMPILED BY: R. Aken TELEPHONE: (815)234-5441 ;
x2f13 MONTH: November, 1989 l
DAY AVERAGE DAILY POWER LEVEL (MWe-Net)
- 1. 1115 MW 16. 1111 MW
- 2. 1114 MW 17. 1094 MW
- 3. 1111 MW 18. 1079 MW +
- 4. 1103 MW 19, 1074 MW
- 5. 1101 MW 20. 1084 MW
- 6. 1Q12 MW 21. 1088 MW
- 7. 1104 MW 22. 1091 MW
- 8. 1 Q10_MW 23. 1QBl_MW ,
- 9. 1Dll MW 24. 1033_MW
- 10. 10S9 MW 25. 1092 MW
- 11. 1100 MW 26. 1099 MW
- 12. 1106 MW 27. 1088 MW
- 13. 1000_MW 28. 1093.MW
- 14. _ . . . _ _ 104B E 29. 10a9E
- 15. 1099 MW 30, 1096 MW INSTRUCTIONS On this form list the average daily unit power level in MWe-Net for each day in the reporting month. Compute to the nearest whole megawatt. These figures will be used to plot a graph for each reporting month. Note that when maximum dependable capacity is used for the net electrical rating of the unit there may be occasions when the daily average power level exceeds the 100% line (or the restricted power level line.) In such cases the average daily unit power output sheet should be footnoted to explain the apparent anomaly.
(0625M/0062M-5)
Report Period November, 1989 UNIT SHUTDOWNS / REDUCTIONS
(UNIT 1) **************************
_ IIA _ Qate Iypt_ ILquIs ERDS_qn MathQd _JJR_Nhr . System Comppnent Cause & Corrective Actign_lo Prevent Recurreg g NO SHUTDOWNS OR SIGNIFICANT REDUCTIONS IN NOVEMBER 1989 oc**LC*********
TYPE Rqasan Method System _& Component F-Forced A-Equip Failure F-Admin 1-Manual Exhibit F & H S-Sched B-Maint or Test G-Oper Error 2-Manual Scram Instructions for C-Refueling H-Other 3-Auto Scram Preparation of D-Regulatory Restriction 4-Continued Data Entry Sheet E-Operator Training 5-Reduced Load Licensee Event Report
& License Examination 9-Other (LER) File (NUREG-0161)
(0625M/G062M-6) c
E. UNIOUE REPORTING REDUIREMENTS (UNIT li for the month of November 1989
- 1. Safety / Relief valve operations for Unit One.
VALVES NO & TYPE PLANT DESCRIPTION DATE ACIWiTED AC21!All.gl CONDITIO!! Cr EVE!IT None
- 2. Licencee generated changes to ODCM. (Y/N)
No.
- 3. Indications of failed fuel. (Y/N)
Yes. Approximately 4 to 5 leaking fuel pins ruel Reliability Indicator = 1.2E 2 pCl/cc 4
(0625M/0062M-7)
F.. LICENEEE EVENT REEQRIE_LURIT 1)
The following is a tabular summary of all Licensee Event Reports for Byron Nuclear Power Station, Unit One, submitted during the reporting period, November 1 through November 30, 1989. This information is provided pursuant to the reportable occurrence reporting requirements as set forth in 10CTR 50.73.
Occurrence Lic.taset_IYent Repott_.NJnber Date ' Iltle_.ALO.crurlence l
89-009 10/05/89 Inadequate Incorporation of Steam Generator Blowdown Isolation Reguirements as Assumed in Certain Accident Analysis Caused By a )
Pre-Service Design Implementation Deficiency I
b l
(0625M/0062M-8) 1 i
- 11. Monthly =Raport for myron Unit 2 for the month of November 1989 A. Summary _of Operating Experience for Unit 2 The unit began this reporting period in Mode 1 (Power Operation) at approximately 93.9% power. On November 14 at 2250 the unit commenced shutdown for the repair of Preccurizer Safety Valve, 2RYB030C. The valve was replaced and 2RY455A was repaired. The unit was at Mode 4 on November 19 at 0324, Mode 3 on November 20 at 0049, Mode 2 on November 21 at 20354 and Mode 1 on November 22 at 0048. The unit operated at power levels of up to 99.3% for the remainder of the month.
(0625M/0062M-9)
l i
B. OPERATING DATA REPORI DOCKET NO.: 050-455 ,
UNIT: Byron Two !
DATE: 12/08/89 I COMPILED BY: R. Aken !
TELEPHONE: (815)234-5441 l x2013 l OPERATING STA7US
- 1. Reporting Period November 1989. Gross Hours: 720
- 2. Currently Authorized power Leve12 3411 (MWt)
Design Electrical Rating: 1175 (MWe-gross) {
Design Electrical Rating: 1120 (MWe-net) i Max Dependable Capacity: 1105 (MWe-net)
- 3. Power Level to Which Restricted (If Any): N/A
- 4. Reasons for Restriction (If Any):
THIS MONTH YR TO DATE CUMULATIVE *
- 5. Report Period Hrs. 720 8016 19,993 i
- 6. Rx Critical Hours $36 6316 17,321
- 7. Rx Reserve Shutdown Hours 0 0 0
- 8. Hours Generator on Line 534 6240 16,941
- 9. Unit Reserve Shutdown Hours 0 0 0
- 10. Gross Thermal Energy (HWH) 1,643,966 16,294,971 43,120,388 -
- 11. Gross Elec. Energy (MWH) 565,769 5,609,031 14,506,948 ,
- 12. Net Elec. Energy (MWH) 535,457 5,264,683 13,593,509
- 13. Reactor Service factor 74.4 78.8 86.6
- 14. Reactor Availability Factor 74.4. 78.8 86.6
- 15. Unit Service Factor 74.1 77.8 84.7
- 16. Unit Availability Factor 74.1 77.8 84.7
. 17. Unit Capacity Factor (MDC net) 67.3 59.4 61.5
- 18. Unit Capacity Tactor (DER net) 66.4 58.6 60.7
- 19. Unit Forced Outage Hrs. 186 355 818 !
- 20. Unit Forced Outage Rate 25.8 5.4 4.6 -
- 21. Shutdowns Scheduled Over Next 6 Months: None
- 22. If Shutdown at End of Report Period, Estimated Date of Startup N/A '
- 23. Units in Test Status (Prior to Commercial Operation): None
- Note - The cumulative numbers do not reflect power
-generated prior to commercial service.
(0625M/0062H-10)
- C. AVERAGE DAILY UNIT POWER LEVEL DOCKET NO.: 050-455 '
UNIT: Byron Two DATE: 12/08/89 COMPILED BY: R. Aken ,
TELEPHONE: (815)234-5441 x2013.
MONTH: November, 1989 DAY AVERAGE DAILY POWER LEVEL (MWe-Net)
- 1. 1007 MW 16. -12 MW
- 2. 1021 MW 17. -12 MW
- 3. 1093 MW 18. -12 MW
- 4. 934 MW 19. -13 MW
- 5. 918 MW 20. -13 MW
- 6. 1029 MW 21. -13 MW 7, 1110 MW 22. 620 MW
- 8. 1105 MW 23, 1077 MW_
- 9. _1107 MW 24. 1068 MW-
- 10. 1103 MVL 25. 1070 MW
- 11. 10 fib MW 26. 101 L Mt]
12, 951 MW 27. 1073 MW
- 13. 6SA ..MW 28. 1064 MW
- 14. _ ___ M_NW 29. 1096 MW _
- 15. -12._MW 30. 1091 MW INSTRUCTIONS On this form list the average daily unit power level in MWe-Net for each day in the reporting month. Compute to the nearest whole megawatt. These figures '
will be used to plot a graph for each reporting month. Note that when maximum dependable capacity is used for the net electrical rating of the unit there may be occasions when the daily everage power level exceeds the 100% line (or the restricted power level line.) In such cases the average daily unit power output sheet should be footnoted to explain the apparent anomaly.
(0625M/0062M-11)
Report Period November, 1989 UNIT SHUTDOWNS / REDUCTIONS
(UNIT 2) **************************
_ lim _ Date Type Sours Reason Methmi LEB_Eumk2I System Conmonent Case & Corrective Action to Puutggt Recurrence 13 11/14/89 F 186 A 1 --- RT 2C Press. Leak on 2C Pressurizer Safety Valve Safety V1v c*oce**********
T7PE Reasop Methqd System & Comoogent F-Forced A-Equip Failure F-Admin 1-Manual Exhibit F & H S-Sched- B-Maint or Test G-Oper Error 2-Manua? Scram Instructions for C-Refueling H-Other 3-Auto Scram Preparation of D-Regulatory Restriction 4-Continued Data Entry Sheet E-Operator Training' 5-Reduced Load Licensee Event Report
& License Examination' 9-Other (LER) File (NUREG-0161)
(0625M/0062M-12)
_ . . _ _ . . - . . . ~ .. . , ., _ . _ . . . _ _ . _ _ . _ . . . _ ___
EdHIOUE REERRIING_REQUIEEMENTS (UNIT 2) for thmnth of November 1989
- 1. Safety / Relief valve operations for Unit Two.
VALVES NO & TYPE PLANT DESCRIPTION DAIE ACTUATED ACTJATICI CONDITInt er EVENT None
- 2. Licensee generated changes to ODCM. (Y/N)
No.
- 3. Indications of failed fuel. (Y/N)
Yes. Approximately one leaking fuel pin.
ruel Reliability Indicator = 2.0E-3 pCi/cc (0625M/0062M-13)
)
F. LICENSEE EVENT REPORTS (UNIT 2)
The following is a tabular summary of all Licensee Event Reports for Byron Nuclear Power Station, Unit Two, submitted during the reporting period, November 1 through November 30, 1989. This information is provided persuant to the reportable occurrence reporting requirements as set forth in 10CTR
$0.73.
Occurrence Licensee Event Report Number Egta Title of Occurrence NONE (0625M/0062M-14)