l I L* '
.,
/[
'o,,
UNITED STATES
NUCLEAR REGULATORY COMMISSION
o
5
~s
REGION 111
799 ROOSEVELT ROAD
GLEN ELLYPs, ILLINOIS 60137
.....
MAY I 91981
4
%( NL.Jg f/f
g
Docket No. 50-329
(
Docket No. 50-330
-
Consumers Power Company
M 2 6198lm I.
'
8
ATTN: Mr. James W. Cook
" W _moaman
Vile President
\\
"
Midland Project
N/
1945 West Parnall Road
'l1
j
g
Jackson, MI 49201
~
Gentlemen:
This refers to the routine safety inspection conducted by Mr. R. N. Sutphin
of this office on January 27-29, 1981 and April 14-16, 1981, of activities
at Midland Nuclear Power Plant, Units 1 and 2, authorized by-NRC Construction
Permits No. CPPR-81 and No. CPPR-82 and to the discussion of our findings with
Mr. D. B. Miller, Jr. , Mr. D. M. Turnbt.ll and others at the conclusion of the
inspection.
The enclosed copy of our inspection report identifies areas examined during
the inspection. Within these areas, the inspection consisted of a selective
examination of procedures and representative records, observations, and
interviews with personnel.
No items of noncompliance with NRC requirements were identified during the
course of this inspection.
In accordance with 10 CFR 2.790 of the Commission's regulations, a copy of
this letter and the enclosed inspection report will be placed in the NRC's
Public Document Room.
If this report contains any information that you or
your contractors believe to be exempt from disclosure under 10 CFR 9.5(a)(4),
it is necessary that you (a) notify this office by telephone within seven (7)
days from the date of this letter of your intention to file a request for
withholding; and (b) submit within twenty-five (25) days from the date of
this letter a written application to this office to withhold such infor-
nation. Section 2.790(b)(1) requires that any such application must be
accompanied by an affidavit executed by the owner of the information which
identifies the document or part sought to be withheld, and which contains
81062900%
4
O
.
NWAY f o .nq
Consumers Power Company
-2-
a full statement of the reasons on the basis which it is claimed that the
information should be withheld from public disclosure. This section further
requires the statement to address with specificity the considerations listed
in 10 CFR 2.790(b)(4). The information sought to be withheld shall be
incorporated as far as possible into a separate part of the affidavit.
If
we do not hear from you in this regard within the specified periods noted
above, a copy of this letter and the enclosed inspection report will be
placed in the Public Document Room.
We will gladly discuss any questions you have concerning this inspection.
Sincerely,
f}$$'YY
Q
C. E. NorElius, Acting Director
Division of Engineering and
Technical Inspection
Enclosure:
IE Inspection
Report No. 50-329/81-03
and No. 50-330/81-03
,
l
cc w/ encl:
Central Files
Reproduction Unit NRC 20b
~
Resident Inspector, RIII
1
Local PDR
Ronald Callen, Michigan
Public Service Commiscion
'
Myron M. Charry