ML20004E536

From kanterella
Jump to navigation Jump to search
IE Insp Rept 50-358/81-08 on 810224-26.Noncompliance Noted: Failure to Follow Test Procedures & Provide Adequate Instrument Calibr Program
ML20004E536
Person / Time
Site: Zimmer
Issue date: 05/29/1981
From: Jackiw I, Maura F
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML20004E534 List:
References
50-358-81-08, 50-358-81-8, NUDOCS 8106120300
Download: ML20004E536 (4)


See also: IR 05000358/1981008

Text

-

.

,

.

.

O

u.S. NuCtEAR REGut4 TORR C0a 1SS10N

-

OFFICE OF INSPECTION AND ENFORCEMENT

,

REGION III

Report No. 50-358/81-08

Docket No. 50-358

License No. CPPR-88

Licensee: Cincinnati Gas and Electric Company

139 East 4th Street

Cincinnati, OH 45201

.

Facility Name:

W. H. Zimmer Nuclear Power Station

Inspection At:

W. H. Zimmer, Moscow, OH

,

Inspection Conducted: February 24-26, 1981

d. M

Inspector:

F. Maura

MAY 2 9 @@

1.N.Jalckiw,ActingChief

d' Sc/

!

iMAY 2 0 ' cot

Approved By:

Test P 'ogram Section

f

Inspection Summary

Inspection on February 24-26, 1981 (Report No. 50-358/81-08)

l

Areas Inspected: Routine, announced inspection to witness preoperational

'

testing. The inspection involved 31 inspector-hours onsite by one NRC

inspector including 24 inspector-hours onsite during off-shifts.

l

Results: Two apparent items of noncompliance were identified (failure to

follow procedures - Paragraph 2; failure to have an adequate instrument

calibration program - Paragraph 3).

l

l

8106124)]OO

.

- - - .

.

- . .

.

_.

. .

.

--

.-

. -.

DETAILS

'

.

1.

Persons Contacted

  • J. Schott, Station Superintendent
  • P. King, Assistant Station Superintendent
  • J. Wald, Station Quality Engineer
  • A. Mosbaugh, Test Coordinator

J. Woeste, Instrument and Control Engineer

W. Bruins, Acting Instrument Foreman

A. Jenkins, General Electric Site Operations Manager

J. Steininger, General Electric Test Coordinator

D. Dycus, General Ele-tric Test Engineer

The inspector also interviewed other licensee employees including

members of the technical, operating and maintenance staff.

  • Denotes those attending the exit interview of February 26, 1981.

2.

Preop Test Witnessing

The inspector observed the full core scrcm testing performed on

February 24-26, 1981. While verifying prerequisites and initial con-

ditions prior to the performance of the initial full core scram, the

inspector observed that test procedure step 7.4.3.5 had been signed

off as complete by the system engineer. The step required that fuse

IC71-F21A and IC71-F21B be installed. The inspector verified, at the

fuse blocks, that the fuses were not installed and that an outstanding

switching order required they be removed. Failure to follow the test

procedure is contrary to 10 CFR 50 Appendix B, Criterion V and Startup

'

Administrative Procedure SU. ACP.05 and is considered to be an example

.

- an item of noncompliance (358/81-08-01) of Severity Level V.

During the first two full core scrams the scram initiation signal

on the recorder failed to work. Prior to the third scram it was

determined that the cause was due to the fact that the fusas for

relays K-21A and B were not installed. The relays which are part of

the reactor protection system should have been energized as required

by test prerequisite step 5.2.2.11.

Failure to follow the test pro-

cedure is contrary to 10 CFR 50 Appendix B, Criterion V and Startup

Administrative Procedure SU.ACP.05 and is considered to be an example

of an item of noncoupliance (358/81-08-02) of Severity Level V.

3.

Instrument Calibrations

The inspector reviewed the calibration records on equipment required

for the test, compared the calibration records to the preop ' rt

records (Data Sheet 9.1) and interviewed instrument department

personnel regarding their established practices. As a result, the

following findings were made:

-2-

_

. -

-

.

.

. - .

---

.-

- - - _,__.-_. _-_- -...

- - - _ _ . - - - .

-

,

a

The Instrument Department's initial calibration includes a loop

a.

-

calibration, however prior to 1980 no data obtained during the

loop calibration was recorded. The only available data being

that obtained during individual components calibrations.

In late

1979 the licensee developed a form to record the loop calibration

data, and according to department personnel loop calibration data

exists for work done since 1980.

b.

No plans exist for the performance of loop calibrations after

the initial calibration. According to the Instrument Engineer,

loop calibrations are done only once in plant life, all subse-

quent calibrations being that of a specific component.

'

c.

Most of the instruments being used for the test had been last

.

.

calibrated approximately two years ago. For example, the CRD pump

suction pressure switches P3-C11-NOCIA and N001B had a calibration

date of January 8, 1979. There is no program for periodic loop

calibrations of instrumentation prior to licensing of the unit

for operation. After the initial calibration, no further work

is pe.rformed unless the E' stem Engineer requests a recclibration,

and {s able to " justify

t" to the satisfaction of the Instrument

Engineer, prior to the performance of the preoperational test.

a.

Data Sheet 9.1, Instrument Calibration Record contained obsolete

informati on.

The entries were initially made in early 1979 at

the start of the preop. The preop was interrupted for over a

year before resuming in late 1980. By that time, some instru-

ments had been recalibrated (i.e. , pressure switch Cll-N012 and

differential pressure indicator C11-N600) but the Systems Engi-

neer had not reviewed the latest calibration records to ensure

their acceptability and update the test records.

The lack of a program to perform periodic calibrations of essential

test equipment or to calibrate prior to its use is in violation of

ANSI N45.2 and N45.2.4/IEEE336-1971, and 10 CFR 50 Appendix B,

Criterion XII and it is considered an example of an item of noncom-

pliance (358/81-08-03) of Severity Level

V.

,

4.

Test Results

Sampling of test results obtained showed scram times of 1.5 to 1.7

,

sec, well within the acceptable limit. Two problems were noted in

'

the areas of CRD pump operation and CRD status display as follows:

a.

Daring the first full core scram several C>30) of the CRD status

display indicating lights were not working properly either because

of problems with bad data memory cards or light modules. The prob-

lems are considered an open item (358/81-u8-04) pending licensee

demonstrating the reliability of the system to accurately provide

warning of an abnormal condition.

-3-

i

._. _ . _ _ . . _ _

_ , .

--

-- --- -

'

"

'

<

,

..

..

b.

Whenever a high demand was placed on a CRD pump a low pressure

trip would. occur. The licensee was unable to filter out the low

pressure spike (<0.5 sec.) with a snubber upstream of the pressure

switch. According to General Electric personnel the pump can

operate for ten seconds with low suction pressure. The planned

corrective action is to install a three to five second time delay

relay in the CRD pump low suction pressure trip circuitry. This

is an open item (358/81-08-05) pending licensee corrective action

and satisfactory testing.

5.

Exit Interview

The inspector met with licensee representatives (denoted in Paragraph 1)

on February 26, 1981. The inspector summarized the scope and findings

of the inspection. The licensee acknowledged the statements by the

inspector with respect to the items of noncompliance.

(Paragraphs 2

and 3).

.

.

!

l

-4-

- , - -

.- ,.

,_

.-_ . .

. _ _ _ _ _ _ _ . _ . - . . - . - - _ - _ _ ,

.

.