Text
.
TIC-
- pa atouq'o
UNITED STATES
g
l'
NUCLEAR REGULATORY COMMISSION
n
6,
.E
REGION V
o, ;
-
1990 N. CALIFORNIA BOULEVARD
SUITE 202, WALNUT CREEK PLAZA
o
- ,,,*
WALNUT CR E E K, CALIFORNI A 94596
MAY 131981
.ocket No. 50-460, 50-513
5
O
fe,@@s
05'1934 F
Washington Public Power Supply System
V
- D
b0 George ashington Way
Richicnd, Washington 99352
p
Attention: Mr. D. W. Mazur
os
'
Program Director, WNP-1/4
Gentlemen:
Subject: NRC Inspection of Washington Nuclear Projects 1 and_4
This refers to the inspection conducted by Messrs. J. O. Elin and A. D' Angelo
of this office on April 13-16, 1981 of activities authorized by NRC Construction
Permit Nos. CPPR-134 and CPPR-174, and to the discussion of our findings held by
Messrs. Elin and D' Angelo with you and other members of your staff at the
conclusion of the inspection.
Areas examined during this inspection are described in the enclosed
inspection report. Within these areas, the inspection consisted of
selective examinations of procedures and representative records, inter-
views with personnel, and observations by the inspector.
No items of noncompliance with NRC requirements were identified within
the scope of this inspection.
In accordance with 10 CFR 2.790 of the Commission's regulations, a copy of
l
this letter and the enclosed inspection report will be placed in the NRC's
Public Document Room.
If this report contains any information that you
believe to be exempt from disclosure under 10 CFR 9.5(a)(4), it is necessary
that you (a) notify this office by telephone within ten (10) days from the
date of this letter of your intention to file a request for withholding; and
(b) submit within 25 days from the date of this letter a written application
!
l
to this office to withhold such information.
If your receipt of this letter
l
has been delayed such that less than seven (7) days are available for your
i
l
l
810 6 0 8 O lM
9
' Washington Public Power Supply System
-2-
MAY 131981
d
review, please notify this office promptly so that a new due date may
be established. Consistent with section 2.790(b)(1), any such application
must be accompanied by an affadavit executed by the owner of the information
which identifies the document or part sought to be withheld, and which contains
a full statement of the reasons on the basis which it is claimed that the
information should be withheld from public disclosure. This section further
requires the statement to address with specificity the considerations listed
in10CFR2.790(b)(4). The information sought to be withheld shall be
incorporated as far as possible into a separate part of the affadavit.
If
we do not hear from you in this regard within the specified periods noted
above, the report will be placed in the Public Document Room.
Should you have any questions concerning this inspection, we will be glad
to disuss them with you.
Sincerely,
d7
B. H. Faulkenber '^N
Chief, Reactor onstruction rojects
Branch
Enclosure:
IE Inspection Report
Nos. 50-460/81-04
50-513/81-04
cc w/o enclosure:
R. B. Glasscock, Quality Assurance Director