ML20004C246

From kanterella
Jump to navigation Jump to search
Proposes Change in Daniel Const Force Organization, Reassigning Const Monitor to Report to New Piping/Welding Manager.New Job Titles Include Electrical Manager,Mechanical Manager & Civil Manager
ML20004C246
Person / Time
Site: Wolf Creek Wolf Creek Nuclear Operating Corporation icon.png
Issue date: 05/14/1981
From: Koester G
KANSAS GAS & ELECTRIC CO.
To: Madsen G
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
Shared Package
ML20004C242 List:
References
KMLNRC-81-079, KMLNRC-81-79, NUDOCS 8106020390
Download: ML20004C246 (1)


Text

47

  • a KANSAS GAS AND ELECTRIC COMPANY tw sus.r=c cumv auen= w<ossrs.

x.....,. -.

May 14, 1981 Mr. G. L. Madsen, Chief Reactor Projects Branch i

U. S. Nuclear Regulatory Consnission Region IV 611 Ryan Plaza Drive Suite 1000 i

Arlington, TX 76011 1

10tLNRC 81-079 i

Subj: Change in Daniel Organization of Construction Forces & Reassignment of Construction Monitor Re Koester Letter to Seidle dated December 16, 1980 Dear Mr. Madse.nz The organization of Daniel's construction work force at Wolf Cree.k is being l

changed to enhance the management of the project. Under the new structure l

there are four managers reporting to the Construction Manager. Job titles l

for the new managers are: Piping / Welding Manager, Electrical Manager, i

Mechanical Manager and Civil Manager. Each of these managers will be res-pensible for their discipline and will have under their direction Field Supervision, Craft Labor and Engineering personnel. The old position of Construction Engineering Manager har been eliminated. The direction of the work force and field engineering is now vested in the new Construction Manager.

This organizational change has been discussed with NRR and a revision is being made to the " Quality Assurance Program for Design and Construction" l

to describe the new organization.

Under the new organization the Piping / Welding Manager is responsible for the total piping construction effort (creft and engineering).

It, there fore,

appears appropriate that the Construction Monitor who coordinates and verifies pipe cleanliness activities, as described in the above-referenced letter, should report to the new Piping / Welding Manager.

Please advise me if you have any objections to this proposed change in the reporting relationship of the Construction Monitor.

Yours very trul/,

[

/

l.'as j W4

\\

' -s GLK:cks I

cc: '"7andel (NRC Site Inspecror) 5=t 81*suo390 x, n.,

x.,,, - --,,:,a uas --o-mo, - m.~.: n.. c-. a,e, u.us,

.