Forwards IE Insp Rept 50-285/81-10 on 810427-30.No Noncompliance Noted
ML20004B969
Person / Time
Site: Fort Calhoun Omaha Public Power District icon.png
Issue date: 05/11/1981
From: Seidle W
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To: William Jones
OMAHA PUBLIC POWER DISTRICT
Shared Package
ML20004B970 List:
References
NUDOCS 8106010366
Download: ML20004B969 (2)


See also: IR 05000285/1981010

Text

_

_.

,

[.

'%

UNITED STATES

[

\\

NUCLEAR REGULATORY COMMISSION

'

REGloN IV

-

/

k,

611 RYAN PLAZA DRIVE. SUITE 1000

,,8

')

ARLINGTON. TEXAS 76011

May 11, 1981

In Reply Refer To:

Docket 50-285/81-10

.

Omaha Public Power District

ATTN: Mr. W. ' C. Jones, Division Manager

Production Operations

1623 Harney Street

Omaha, Nebraska 68102

Gentlemen:

This refers to the inspection conducted by Messrs. J. P. Jaudon and J. E.

l

Cumins of our staff during the pariod April 27-30, 1981, of activities

authorized by NRC Facility Operating License DPR-40 for the Fort Calhoun

Station and to discussion of our findings by the inspectors with Mr. R. L.

Andrews and other members of your staff at the conclusion of the inspection.

l

Areas examined during the inspection and our findings are discussed in the

enclosed inspection report. Within these areas, the inspection consisted of

selective examination of procedures and representative records, interviews

with personnel, and observations by the inspectors.

Within the scope of the inspection, no violations or deviations were identi-

fied.

We have also examineri actions you have taken with regard to a previously

identified inspection finding. The status of this item is identified in

paragraph 2 of the enclosed report.

In ac.:ordance with 10 CFR 2.790 of the Commission's regulations, a copy of

this letter and the enclosed inspection report will be placed in the NRC's

Public Document Room.

If this report contains any information that you

believe to be exempt from disclosure under 10 CFR 9.5(a)(4), it is necessary

j

that you (a) notify this office by telephone within 10 days from the date of

'

this letter of your intention to file a request for withholding; and (b) sub-

i

mit within 25 days from the date of this letter a written applicatior to this

l

office to withhold such information.

If your receipt of this letter has been

l

delayed such that less than seven days are available for your review, please

'

l

notify this office promptly so that a new due date may be- established.

'

Consistent with Section 2.790(b)(1), any such application must be accompanied

by an affidavit executed by the owner of the information which identifies the

document or part sought to be withheld, and which contains a full statement of

the reasons on the basis which it is claimed that the infonnation should be

witnheld from public disclosure. This section further requires the statement

bo\\

\\

5

o

I

'

y u..m

.

- - -

.

-

-

-.

-. --

.

.

.

.

Omaha Public Power District

2

May 11,1981

'

to address with specificity the considerations listed in 10 CFR 2.790(b)(4).

The infonnation sought to be withheld shall be incorporated as far as possible

into a separate part of the affidavit.

If we do not hear from you in this

regard within the specified periods noted above, the report will be placed in

the Public Document Room.

Should you have any questions concerning this inspection, we will be pleased

to discuss them with you.

Sincerely,

.-

W. C. Sei

e, Chief

Engineering Inspection Branch

Enclosure:

IE Inspection Report No. 50-285/81-10

cc w/ enclosure:

S. C. Stevens, Manager

Fort Calhoun Station

Post Office Box 98