ML20003G662

From kanterella
Jump to navigation Jump to search
IE Mgt Meeting Repts 50-443/81-04 & 50-444/81-04 on 810312. Major Areas Discussed:Qa,Substructure & Foundations, Concrete,Liners & safety-related Structures
ML20003G662
Person / Time
Site: Seabrook  NextEra Energy icon.png
Issue date: 04/02/1981
From: Brunner E, Cerne A
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML20003G661 List:
References
50-443-81-04, 50-443-81-4, 50-444-81-04, 50-444-81-4, NUDOCS 8104300455
Download: ML20003G662 (7)


See also: IR 05000443/1981004

Text

.

.

O

u.S. nuctEAR REGULATORY COMMISSION

OFFICE OF INSPECTION AND ENFORCEMENT

Region I

50-443/81-04

Report No.

50-444/81-04

50-443

Docket No.

50-444

CPPR-135

License No.

CPPR-136

Priority

Category

A

--

Licensee:

Public Service Company of New Hampshire

1000 Elm Street

Manchester, New Hampshire 03105

Facility Name: Seabrook Station, units 1 and 2

Meeting at:

Seabrook, New Hampshire

Meeting conducted:

March 12,1981

bfchI7I99)

Inspectors:

3

A.C. Cerne, Sr. Resident Inspector

date signed

date signed

date signed

Js /

Approved by:

.

date' signed

r

E.J/ Brunner, Chief, Projects Branch

No/1, DRPI

Meeting Summary:

Meeting on March 12,1981 (Combined Report Nos. 50-443/81-04 and 50-444/81-04)

Scope:

Special, announced management meeting to discuss the results of the NRC

board convened to evaluate the Licensee's Performance from January 1 to December 31,1980

as part of the NRC's Systematic Assessment of Licensee Performance (SALP) Program.

Areas addressed included:

Quality Assurance; Substructure and Foundations; Concrete;

Liners; Safety-Related Structures; Piping and Hangers; Safety-Related Components;

Electrical Equipment; Electrical; Instrumentation; Fire Protection; Preservice

Inspection; Reporting; Environmental; Training; and Management.

Results: A summary of the licensee performance evaluation was presented. Areas

of concern were discussed with corporate and site management.

No new enforcement

actions were identified. A number of areas where improvements were initiated by

licensee actions, were identified.

l

Region I Form 12

(Rev. April 77)

810480 0 6

--

..

.

..

..

.

.

DETAILS

1.

Licensee Attendees

D. N. Merrill, Executive Vice President (PSNH)

W. P. Johnson, Vice President (YAEC)

8. B. Beckley, Manager of Nuclear Projects (PSNH)

W. J. Miller, Quality Assurance Manager (YAEC)

R. P. Pizzuti, Construction Manager (YAEC)

J. DeVincer. tis, Seabrook Project Manager (YAEC)

J. H. Herrin, Site Manager (PSNH)

G. F. Mcdonald, Jr., Quality Assurance Engineer (YAEC)

J. W. Singleton, Field Quality Assurance Manager (YAEC)

2.

NRC Attendees

B. H. Grier, Director, USNRC, Region I

E. J. Brunner, Chief, Projects Branch No.1, DRPI, Region I

R. M. Gallo, Chief, Reactor Projects Section No. lA, DRPI, Region I

A. C. Cerne, Senior Resident Inspector, Seabrook

3.

Discussion

A brief summary of the Systematic Assessment of Licensee Performance (SALP)

Program was presented to explain the basis and purpose of the evaluation.

The NRC Region I evaluation board meeting was discussed, including the

assessment period, performance data and the results of the board's evaluation.

The licensee's overall performance was considered acceptable. The prescribed

regional inspection frequency will be decreased in one functional area,

due to the performance and quality record in that area. Three areas will

receive increased inspection effort by Region I to confirm that corrective

actions already initiated are effective. These three areas of concern were

identified to corporate and site management.

.

.

SYSTEMATIC ASSESSMENT OF LICENSEE PERFORMANCE

SEABROOK STATION

REGION I EVALUATION BOARD MEETING

Facility:

Seabrook Station, Units 1 and 2

Licensee:

Public Service Ccmpany of New Hampshire

Unit Identification:

Docket No.

License No./Date of Issue

Unit No.

50-443

CPPR-135

July 7,1976

Unit 1

50-444

CPPR-136

July 7,1976

Unit 2

Reactor Information:

Unit 1

Unit 2

NSSS

Westinghouse

Westinghouse

'

MWT

3425

3425

Assessment Period:

January 1 - December 31,1980

Evaluation Board Meeting Date:

February 13,1981

Evaluation Board Members:

J. M. Allan, Deputy Director, Region I

E. J. Brunner, Chief, RO&NS Branch, Region I

J. W. Devlin, Acting Chief, Safeguards Branch, Region I

(

G. H. Smith, Chief, FF&MS Branch, Region I

l

A. W. Drcmerick, Licensing Project Manager, NRR

L. E. Tripp, Acting Chief, RC&ES Branch, Region I

Other NRC Attendees:

A. C. Cerne, Senior Resident Inspector, Region I

l

l

1

l

l

l

i

'

_ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

_____________ ______________________ ______ _______-____ - - ___

__

___ _____ _

.

.

BASIC PERFORMANCE DATA

SEABROOK STATION

JANUARY 1 - DECEMBER 31,1980

A.

Number and Nature of Noncompliance Items

1.

Noncompliance category:

Unit 1

Unit 2

Violations

0

0

Infractions

9+(2)

0+(2)

Deficiences

0+(3)

0+(3)

Severity V

1

0

2.

Areas of Noncompliance:

VIO/INF/DEF/SEV V

VIC/INF/DEF/SEV V

Quality Assurance

0 (1) 0

0

0 (1)

0

0

Concrete

0

1

0

1

0

0

0

0

Liners

0

0

(1)

0

0

0 (1)

0

Safety Related Structures 0

2

0

0

0

0

0

0

'

Piping and Hangers

0

6

0

0

0

0

0

0

Environmental

'O

(1)(2)

0

0

(1)(2)

0

B.

Number and Nature of Construction Deficiency Recorts

1.

Type of Events:

Unit 1

Unit 2

A. Personnel Error

0+(1)

0+(1)

B. Design / Fabrication Error

3

0

C. External Cause

0

0

D. Defective Procedures

0+(1)

0+(1)

E. Component Failure

0+(2)

0+(2)

,

X. Other

0

0

-

Total

3+(4)

(4)

'

j

Casually-Linked Events: None identified

l

2.

Of the seven Construction Deficiency Reports submitted during the assessment

period, five were reported as potentially reportable.

Of these five, four

were evaluated by the licensee to be not reportable under 10CFR50.55(e),

while the other remains under evaluation.

.

C.

Escalated Enforcement Actions

Civil Penalties

None

m

.

_.

.-

. - -

-

.

.

Orders

None

Immediate Action Letters

.

IAL No. 80-55(12/22/80)-Recurrent items of noncompliance in the area of weld

repairs performed by the piping subcontractor (Pullman-Higgins).

Stoo work order

on weld repairs issued by licensee.

D.

Manacement Conferences Held During Past Twelve Months

No enforcement related meetings with licensee management were conducted during

the assessment period; however, the following management conferences were held:

February 6,1980 - a meeting was held at the Seabrook site at NRC request to

--

discuss details related to the establishment of the Resident Inspector

office and program.

Jaly 3,1980 - a routine meeting held with licensee management at the Seabrook

--

site at NRC request to discuss construction status, Construction Deficiency

Reporting, the NRC enforcement policy, resident insoection~and independent

measurement programs, SALP, and the licensee implementation of the Seabrook

,

QA program.

Recent insoection findings at Seabrook were discussed during the July meeting

and two specific areas were mentioned as sources of NRC concern--the civil /

,

structural subcontractor (Perini) implementation of the QA program and the

adequacy of licensee corrective actions in response to previous NRC findings.

.

E.

Licensee Activities

Activity on both units varied extensively durino the assessment period. On

March 20,1980 PSNH decided to substantially reduce the level of expenditures for

construction of Seabrook Station. This resulted in a reduction in total site

work force from approximately 5000 personnel to 2500 personnel within one

month. A June 9,1980 order by the New Hampshire PUC called for PSNH to delay

for three years the planned completion of Seabrook Unit 2.

While the licensee

has appealed this action, the level of work on Unit 2 had already been

confined to containment liner erection because of PSNH cash flow problems.

A two month ironworker strike during July ;o September,1980 further reduced

the total on-site work force to approximately 2000 personnel.

Since September,

1980, the total work force has gradually grown to approximately 3500 perscnnel

at the end of the assessment period.

Throughout these changes in personnel levels and work activities, the licensee

has maintained that the Unit 1 Fuel Load Date remains 1/1/83.

(Note: a

l

!

l

.

,

. - _

-

- _ _ ,

,

_

.

_

_

.

--

.

.

January, 1981 letter to the NRC indicates that this date may slip).

PSNH

had already indicated in August,1980 that the Unit 2 Fuel Load Date of

11/1/84 was unrealistic, but that a new schedule could not be established

until the final approval of the changes in joint ownership percentages, which

would improve PSNH cash flow.

Major construction activities for Unit 1 during the assessment period include

commencement of containment concrete wall placement, commencement of safety-

related HVAC erection, continuation of ASME Class 2 and 3 piping installation,

commencement of containment interior coating work, continuation of safety-

related structure erection, and the continuation of electrical cable tray and

conduit installation. Since the March,1980 slowdown, construction emphasis

has been directed to the completion of activities on the Primary Critical

Path.

During 1980 the percentage complete for Unit 1 and Common Areas in-

creased from 31% to 44%.

The only construction activities for Unit 2 during the assessment period

consisted of placement of the containment concrete base mat, continuation of

containment liner erection, and activities in areas common to both Units 1

and 2.

During 1980 the percentage complete for Unit 2 increased from 6%

to 8%.

F.

Inspection Activities

Eleven onsite combined inspections for both units were conducted during the

assessment period--six of these were resident inspector originated and five

were conducted by regionally based inspectors, one of whom was an environmental

specialist. A total of 595 inspector-hours were expended during 1980 in the

inspection of Unit 1 activities and 177 inspector-hours on Unit 2.

Three Region

IV Vendor Inspection Branch inspections were also conducted at the UE&C

,

corporate office in Philadelphia with a portion of those inspections directed

toward A/E activities relative to Seabrook Station. The construction resident

inspection program was implemented on May 18,1980.

Construction inspection activities have been concentrated in the areas of

civil / structural and containment liner erection, and piping and component

control and installation. Although only one inspection was directed toward the

Quality Assurance program, every construction inspection has indirectly touched

upon QA activities.

To a lesser degree, electrical activities and the licensee

reporting program have received inspection. A more detailed Summary of

Inspection Activity is enclosed as supplemental information in Attachment II.

"

.

F

r

-

w

'e

v

o.

.

SEAER00K STATION

INSPECTION PROGRAM CHANGES

INSPECTION TIME AND/02 SCOPE

CHANGE FROM PRESCRIBED INSPECTION PROGRAl

FUNCTIONAL AREA

INCREASE

NO CHANGE

DECREASE

1.

Quality Assurance

X

2. '

Substructure and Foundations

X

3.

Concrete

X

4.

Liners (Containment and othersi

X

5.

Safety-Related Structures

X

6.

Pipina and Hangers

X

(Reactor Coolant and others)

7.

Safety-Related Components

X

(Vessel, Internals and HVAJ)

8.

Electrical Equipment

X

9.

Electrical (Tray and Wire)

X

10.

Instrumentation

X

l

11.

Fire Protection

X

I

12.

Preservice Inspection

X

. . .

13.

Reporting

X

14.

Environmental

X

l

15.

Training

X

16.

Management

X

l

l

inp /

~

/Reqio'n~/1 Director

2[/E/f'/

/

Date