ML20003F051

From kanterella
Jump to navigation Jump to search
IE Insp Repts 50-321/80-48 & 50-366/80-48,on 801210-12. Noncompliance Noted:Inadequate Procedure for Placement of Intake Structure Backfill & Failure to Follow Procedure in Amending Design Change
ML20003F051
Person / Time
Site: Hatch  Southern Nuclear icon.png
Issue date: 02/12/1981
From: Conlon T, Lenahan J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML20003F045 List:
References
50-321-80-48, 50-366-80-48, NUDOCS 8104200045
Download: ML20003F051 (6)


See also: IR 05000321/1980048

Text

-

</" D ucgk

UNITED STATES

  • f'

p'l

NUCLEAR REGULATORY COMMISSION

2

/ .. E

REGION 11

"

101 MARIETTA ST., N.W.. SUITE 3100

[

ATLANTA, GEORGI A 30303

.....

Report Nos. 50-321/80-48 and 50-366/80-48

Licensee: Georgia Power Company

270 Peachtree Street

Atlanta, GA 30303

Facility Name: Hatch Nuclear Plant

Docket Nos. 50-321 and 50-366

License Nos. DPR-57 and NPF-5

Inspection at Hatch site near Baxley, Georgia

M

h

c4

/

[/

Inspect h

-

J. J. Lenahan

Dite Signed

'

Approved C

M

d;7 - / $ - 9 /

T. E. Co'nlon, Section Chief, RC&ES Branch

Date Signed

SUMMARY

Inspection on December 10-12, 1980

Areas Inspected

This special, announced inspection involved 18 inspector-hours on site in the

areas of follow-up IE Bulletin 80-11, backfill replacement for support of RHR and

service water piping at the intake structure, and licensee action on previcus

inspection findings.

Results

Of the three areas inspected, no violations or deviations were identified in one

area; two violation were found in two areas (Inadequate procedure for placement

of intake structure backfill

paragraph 3; Failure to follow procedures in

amending design change and writing nonconformances

paragraph 6).

810420006

~-

,

.

.

DETAILS

1.

Persons Contacted

Licensee Employees

  • C. E. Belflower, QA Site Supervisor
  • J. M. Watson, Senior QA Field Representative
  • C. R. Miles, QA Field Supervisor
  • M .Manry, Plant Manager
  • D. A. McCusker, QC Supervisor
  • R. M. Herrington, Senior QC Specialist
  • J. Rearden, Junior Engineer
  • T. Green, Assistant Plant Manager
  • C. E. Rand, Manager, Field Operations Construction

M. Meeks, Civil Engineer, (telephone conversation)

J. Jordan, Licensing Engineer, (telephone conversation)

Other Organizations

T. Morrison, Electrical Engineer, Southern Services Company

  • L. Young, Geotechnical Engineer, Law Engineering
  • A. Lancaster, Senior Geotechnical Engineer, Law Engineering

G. Kosi, Civil Engineering Group Supervisor (telephone conversation)

R. Gladsby, Project Engineer, Bechtel (telephone conversation)

C. Feltmar, Electrical Engineering Group Supervisor (telephone conversation)

  • Attended exit interview

j

2.

Exit Interview

The inspection scope and findings were summarized on December 12, 1980 with

those persons indicated in Paragraph 1 above. The violations described in

paragraphs 3 and 6 were discussed during the exit interview.

3.

Licensee Action on Previous Inspection Findings

(Closed) Unresolved Item 321/80-26-01 and 366/80-26-01 " Plant Service Water

and RHR Service Water Intake Structure and Associated Piping Backfill

Controls". The inspector reviewed the procedures which addressed placement

of backfill around the intake structure. The procedure did not specify the

l

j

required QC test frequency, and permitted fill placement in lifts of

'

thickness which were excessive for good compaction control. The results of

the detailed investigation conducted by the licensee on the backfill

l

materials under the RHR and service water lines showed that the placement

and quality control testing of the fill was inadequate.

There were no

i

l

records of any QC tests being performed on fill materials below the RHR and

service water piping. This item is closed as Unresolved Item 321/80-26-01

and 366/80-26-01 and upgraded to Violation Item 321/80-48-01 and

366/80-48-01," Inadequate Procedure for Placement of Intake Structure

l

Backfill".

-- .

-

.

.

.,

2

4.

Unresolved Items

Unresolved items are matters about which more information is required to

determine whether they are acceptable or may involve noncompliance or

deviations.

New unresolved items identified during this inspection are

discussed in paragraph 6.

5.

Independent Inspection Effort

There was no idependent inspection effort conducted during this inspection.

6.

Licensee Identified Item (LER): Settling of Fill Under Plant Service Water

and RHR Service Water Piping

a.

Background

On June 12, 1980, the licensee notified Region II that an investigation

into the cause of pavement deflection beneath a crane outrigger pad

disclosed that settling of backfill from under the RHR and Service

l

water intake lines had occurred. This was reported to Region

.'I as LER

l

50-321/1980-062. The settlement was observed under an approximate 12

foot continuous section of the pipelines.

After discovering this

problem, the licensee initiated an extensive investigation to determine

I

the extend of this problem. This investigation included soil borings,

I

test pits, installation of piezameters, and field and laboratory soils

testing. The investigation, which was performed by Law Engineering,

'

disclosed that the fill materials supporting the RHR and service water

!

lines did not meet design requirements from the intake structure to a

point approximately 100 feet south of the structure. The licensee and

f

its Architect-Engineer, Bechtel, prepared plans and specifications

detailing the method for correcting the problem. A contract for the

repair work was awarded to Spencer White and Prentis, Inc..

During

this inspection, the inspector reviewed drawings, quality control and

work procedures, the work completed to date, and quality records

>

associated with the repair work.

The details examined are stated in

the following paragraphs.

,

b.

Review of drawing and procedures for accomplishment of Intake Backfill

Repair Work

The repairs to the backfill are being completed under a Design Change

Request number DCR 80-279.

The inspector examined the following

l

documents which control the backfill repair activities:

(1)

Law Engineering: " Procedure for Field Quality Control

for

Construction and Backfilling of a Braced Excavation for the Intake

Structure Service Water Piping and Utilities for E.

I. Hatch

Nuclear Plant Units 1 and 2".

l

l

--,= -

.

.

.

3

(2) Bechtel: " Technical Specification for Design, Construction and

Backfilling of a Braced Excavation for the Intake Structure

Service Water Piping and Utilities for E. I. Hatch Power Plant

Units 1 and 2".

(3) Bechtel: "Proceoure for Monitoring Horizontal and Vertical

Movement".

(4) Georgia Power procedure: " External Surface Coating of Underground

Metallic Pipe".

(5) Bechtel: " Technical Specification for External Surface Treatment

of Underground Metallic Pipe".

(6) Spencer White and Prentis, Inc.: drawing number 2654-1 through

2654-6, " Intake Structure-Utility Underpinning".

(7) Design Change Request number DCR 80-279.

Review of the above documents disclosed the following unresolved item:

Paragraph 17.5 of the Bechtel specification for design, construction,

and backfilling of the excavation states that the K-Krete shall have a

minimum unit weight of 120 to 130 pcf and a minimum 7-day unconfined

compressive strength of 10 to 30 psi. This requirement needs clarifi-

cation to specify the acceptability of K-Krete with unit weights

greater than 130 pcf and unconfined compressive strengths greater than

30 psi. Also the maximum elasped time between batching and placing of

the K-Krete is not specified in the specification. Law engineers stated

that the time limit they are currently using is one and one-half hours,

which is the same as for concrete.

The apparent unclear acceptance

criteria in the specification was identified to the licensee as

Unresolved item 321/80-48-04 and 366/80-48-04, "K-Krete QC Require-

ments", pending further review by NRC and the licensee.

c.

Examination of Intake Backfill Repair Work Completed to Date

The inspector examined the excavation and K-Krete placed as of the

inspection date.

K-Krete had been placed to within 1 foot of the

bottom of the pipe on approximately 50 linear feet of the west lines

cnd 40 linear feet of the east lines. The inspector observed wrapping

of protective coating material on the west lines and discussed the

methods of application of the protective coating materials with

craftsmen performing the work.

The inspector also discussed QC

inspection of the work with Law engineers and licensee QC personnel.

During the examination of the completed work the inspector noted that

the details of the excavation and the temporary supports for the pipes

were different than shown on the construction drawings. The inspector

discussed the justification for these changes with Bechtel and licensee

engineers and reviewed a memorandum and attached sketch showing the

details of che changes. These above discussions and review of

- - - - -

y

.

,

o

4

completed work disclosed the following examples of failure to follow

procedure:

Georgia Power procedure number HNP-809 requires that changes to Design

Change Raquests (DCR) be reviewed by the Plant Review Board (PRB)

before being implemented. The repair to the intake backfill is being

pe-formed under DCR-80-279.

Discussions with licensee engineers

disclosed that the change to DCR 80-279 concerning the details of

excavation and the method of temporary support of the pipes had not

been reviewed and approved by the PRB.

During inspection of the exposed pipes the inspector noted the

following apparent deviations from original design requirements;

(1) The protective coating materials were improperly applied on pipe

joints on the RHR and service water lines during the original pipe

installation.

(2) Protective coating materials were damaged at several spots on the

RHR and Service water lines.

(3) During the original pipe installation two 2-inch pipe lines were

supported by pieces of angle iron which had been welded to one of

the 18" RHR lines.

Discussions of these problems with licensee personnel disclosed that

these problems had not been documented on a Nonconformance Report as

required by procedure HNP-801.

Failure to obtain approval prior to implementing a change to a DCR and

failure to initiate a nonconformance report on deviations to design

requirements was identified to the licensee as violation Item

321/80-48-02 and 366/80-48-02.

d.

Review of Quality Records Related to the Intake Backfill Repair

The inspector reviewed the following quality records relating to the

intake backfill repair:

(1) Results of the investigation performed to determine the extent of

the backfill problem, including soil borings and test pit logs,

piezometer data, and soil testing data.

(2) Results of the testing program which was performed to determine -

the properties of the K-Krete backfill replacement material.

(3) Daily shift QC Inspector Records for November 20, November 24-26,

December 1-5, and December 8-10, 1980.

--

.

,,

s

5

(4) Subgrade Inspection Sign-off Sheet.

(5) Unconfined compressive strength and bulk unit weight data for 3 x

6 inch K-Krete cylinders from pour numbers 3, 4, 5, 6, and 7.

This LER remains open pending completion of the intake backfill repair.

No deviations were identified.

,

7.

(0 pen) IE Bulletin 80-11, Masonry Wall Design - Units 1 and 2

The inspector examined Southern Company procedure, " Surveillance Procedure

for Concrete Masonry Walls for Georgia Power Company for E. I. Hatch Nuclear

i

i

Plant - Units 1 and 2".

This procedure addresses the work to be performed

t

in the Field to complete IE Bulletin 80-11 requirements. The inspector also

discussed methods used to identify masonry walls in proximity of safety

related equipment and preparation of masonry walls as-built drawing with

l

i

Southern Company engineers. This bulletin remains open.

No deviations or violations were identified.

I

4

,96

i

t

l

!

,

I