Text

[M

'

  1. %g

p

g

UNITED STATES

y

g

NUCLEAR REGULATORY COMMISSION

D

E

REGION I

S

[

631 PARK AVENUE

%

,e

KING oF PRUSSIA, PENNSYLVANIA 19406

FET: "1

~,:

I

  1. y ?4

A

Docket Nos. 50-354; 50-355

/

ee@[A,

2 Il[>

&

Public Service Electric & Gas Company

E

e,,, g g l IS8f 5 -

ATTN: Mr. T. J. Martin

eggg7,

'

Vice President

G

-

Engineering and Construction

M

O

80 Park Plaza - 17C

h

b

Newark, New Jersey 07101

Gentlemen:

Subject; Combined Inspection 50-354/81-01 and 50-355/81-01

This refers to the routine safety inspection conducted by W. H. Bateman of this

office on January 5 - February 1,1981 at Hope Creek Generating Station,

Units 1 and 2, Hancock's Bridge, New Jersey of activities authorized by NRC

License Nos. CPPR-120 and CPPR-121 and to the discussions of our findings held

by Mr. Bateman with Mr. A. E. Giaroino of your staff at the conclusion of the

inspection.

Areas examined during this inspection are described in the Office of Inspection

and Enforcement _ Inspection Report which is enclosed with this letter. Within

these areas, the inspection consisted of selective examinations of procedures

and representative records, interviews with personnel, and observations by the

inspector.

Within the scope of this inspection, no items of noncompliance were observed.

In accordance with Section 2.790 of the NRC's " Rules of Practice," Part 2, Title

10, Code of Federal Regulations, a copy of this letter and the enclosed inspection

report will be placed in the NRC's Public Document Room.

If this report contains

any information that you (or your contractor) believe to be proprietary, it is

necessary that you make a written application within 20 days to this office to

withhold such information from public disclosure. Any such application must be

accompanied by an affidavit executed by the owner of the information, which

identifies the document or part sought to be withheld, and which contains a

statement of reasons which addresses with specificity the items which will be

considered by the Commission as listed in subparagraph (b) (4) of Section 2.790.

The information sought to be withheld shall be incorporated as far as possible

into a separate part of the affidavit.

If we do not hear from you in this

regard within the specified period, the report will be placed in the Public

Document Room.

81040606 8

9t

l

. . .

_

_

_

_ _ _ _

.

,

Public Service Electric & Gas Company

2

No reply to this letter is required; however, should you have any questions

concerning this inspection, we will be cleased to discuss them with you.

Sincerely,

f?./q'1 son, Chief

<

.obert T. C

Reactor Construction and Engineering

Support Branch

Enclosure:

Combined Office of Inspection and Enforcement Inspection

Report Number 81-01

cc w/ encl:

J. Boettger, General Manager, Corporate QA

f