Responds to 810313 Inquiry Into Status of NRC Review of CP Application.Nrc Hopes to Complete Evaluation of Application, Including Eia Issuance,By June 1981.Consultant Retained to Assist in Eia Preparation
ML20003D711
Person / Time
Site: Bailly
Issue date: 03/27/1981
From: Goldberg S
NRC OFFICE OF THE EXECUTIVE LEGAL DIRECTOR (OELD)
To: Vollen R
VOLLEN, R.J. & WHICHER, J.M.
References
NUDOCS 8103310237
Download: ML20003D711 (1)


Text

_~

- ~.. -..

=

_=

p

c e

y, oq'o, UNIT ED STAT ES NUCLEAR REGULATORY COMMISSION e

o

$.{

C W@HNG T ON, D. C. 20Z5 k U,/

March 27, 1981

\\M(/g;

}

i ObSA!{h Robert J. Vollen, Esq.

g MA!{ li c ;rq ;,

c/o BPI 8a.a%

l

%$F" /i/

i 10 North Dearborn Street k

[.' '.

Chicago, IL 60602

'&l In the Matter of j

florthern Indiana Public Service Company l

(Bailly Generating Station, Nuclear-1)

Docket No. 50-367 (Construction Permit Extension)

Dear Mr. Vollen:

On March 20, 1981, I received your March 13 inquiry into the status of the Staff review of the Bailly construction pennit applic.ation and the date by which it expects to issue its environmental impact appraisal (EIA) in this matter.

As indicated in my January 16, 1981 letter to the Board, the Staff had decided to retain a consultant to assist in the preparation of the EIA.

That centract was executed on March 19, 1981.

l The press of competing Staff assignments, including the priority reduction in the backlog of near-tenn operating license applicaticast make it difficult to assign a date by which the Staff review of the pretent application will be concluded with certainty.

Nonetheless, with the aforementioned contract now in effect, the Staff hopes to complete its evaluation of this application, including the issuance of an EIA, by I

carly June,1981.

Sincerely,

{k 'ik!

('

Steven C. Goldberg Counsel for NRC Staff cc: