Responds to IE Bulletin 80-23, Failures of Solenoid Valves Mfg by Valcor Engineering Corp. All Contractors & Subcontractors Requested to Identify Valcor Valves.Any Valves Found Will Be Replaced
ML20003D253
Person / Time
Site: Satsop
Issue date: 03/02/1981
From: Dobson D
WASHINGTON PUBLIC POWER SUPPLY SYSTEM
To: Engelken R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
References
GO3-81-601, IEB-80-23, NUDOCS 8103260037
Download: ML20003D253 (1)


Text

YiL W

P Washington Public Power Supply System g A JOINT OPERATING AGENCY S

P.O. SOE 1223 ELMA. W ASHINGTON 98541 PHONE (206) 482-4428 March 2, 1981 G03-81-601 00 -

Docket Nos. 50-508 e\ C) o a f

Mr. R. H. Engelken .

g, MAR ru - -45 NRC Region V Suite 202 Walnut Creek Plaza 2 3IO81 A' u.s Do 4 f g u ra,,

  1. gs s 1900 N. California Blvd.

Walnut Creek, California 94596 q, P g' y '

Cu /

Dear Mr. Engelken:

Subject:

WPPSS NUCLEAR PROJECTS 3 AND 5 RESPONSE TO IE BULLETIN 80-23 IE Bulletin 80-23, issued on November 14, 1980, identified possible safety problems with specific models of Valcor solenoid valves.

In response to the subject bulletin, our A/E has contacted all concerned contractors and subcontracts of the subject matter, and requested them to identify if any of their Valcor solenoid valves fall into the category of the valves stated in the bulletin.

If any solenoid valves are found such that their P/N's are V70900-21 -1 and V70900-21-3 the existing coil shall be replaced according to the manufacturers recommendations. We will be informed of the contractors findings and wDi issue a supplemental response by March 20, 1981.

Very truly yours,

/

D. . DOBSON Pr gram Director (Acting) WNP-3/5 cc: H. D. Thornburg, Director Division of Reactor Operations Inspection W. Woods, NUS l