_i' r
Dzpartmcnt of Nucletr Enginsering O%
Rensselaer Polytechnic Institute Troy, New York 12181
.lbrch 1, 1981'
,,{-
Qf Director
> %%%h ~IQ
- Division of Reactor Licensing
'.,T/ N
.U.S. Nuclear Regulatory Commission J.D /M j'] h(Qf Washington, DC 20545 S\\
Re: Rensselaer Polytechnic Institute Q
,O,,
Facility License CX-22 6 Y#
Docket-50-225 D
Report of Tests and Experiments y
~,.
Dear Sir:
This' report of tests and experiments-is, submitted, in accordance with Title 10 of the Code of Federal Regulations Part 50.59, for the period lbrch 1,1980 to March 1, 1981.
'The fuel plates used comprised a core loading of 152 MTR type, flat, stationary j.
. plates and 24 MTR type flat, control rod plates. Ten stationary and 2 control rod plates are stored in the fuel vault.. All of the fuel plates are leased by the U.S. Department of Energy under contract DE-AC02-76ER03457.
Through periods March 1, 1980 to April 23, 1980 and July'7, 1980 to August.13,
'1980 the Facility was used to conduct a graduate level course on reactor experi-
.ments for classes of 12 and 7 students respectively. The Facility was also used-for two days as.part of the Rensselaer Polytechnic Institute's summer course-for-industry on reactor. design.. Further, three students were involved in project work at the Facility to: satisfy. degree requirements. The reactor experiments course is currently being taught and three students are working on projects (two
-masters and one senior project).
.' Routine scheduled maintenance was performed in June, January and February.
~
Two projects were completed during the report period. The core was successfully.
reconfigured within the license limits and the neutron activation analysis
.. project was completed.
070 S
I O.
810.819.06 W k
t-The experimants, operations, and topics covered in association with the use of the facility remain the same as described in previous reports.
- All-activities and experiments have been conducted in accordance with our NRC reactor license CX-22.
There have been no changes to our Technical Specifications and our activities did not involve any unreviewed safety questions.
Sincerely yours,
.I
\\
'ji\\h i $6.71 Peter R. Nelson,. Supervisor RPI Critical Experiments Facility L. David Walthousen Laboratory mam cc:
'D.
R. Harris R. T. Lahey, Jr.
R. E. Scammell t