Text
Q Alabama Power Company 600 North 18th Street i
rest Offics Box 2641
)
Birmingn3m, AIabam2 35291 l
Telephone 203 250-1000 m
F. L. CLAYTON, JR.
Senior Vice President Alabama Power the southem entrx:s, stem February 20, 1981 50 m
Docket No. 50-348 Docket No. 50-364 o
7 ~..
4 Director of Nuclear Reactor Regulation SV;d D
U. S. Nucleae Regulatory Comission i"
m Washington, D. C.
20555 ij tj W
w Attention: Mr. Harold Denton fe:
J. M. Farley Nuclear Plant Security Plan
Dear Sir:
Enclosed is a complete text of our Security Plan, Revision 2.
This submittal constitutes our 10CFR50.54(P) report for changes made as indicated in my August 18, 1980 letter. This revision also includes several other needed changes.
Due to the failure of the vendor to resolve outstanding problems for certain computer-controlled portions of our security system, Alabama Power Company has had to cancel the contract. We are not attempting to place a
-new vendor under contract in order to make all portions of our system function in accordance with design as soon as possible.
Tnerefore, the February 23, 1981 date contained in my August 18, 1980 letter has had to be changed to June 1, 1981. We will continue to use approved compensatory measures until we can activate the full system as designed.
Also, enclosed is a chronological listing of actions taken to complete the computer-controlled portions of our security system.
We request that this information be maintained as proprietary and withheld from public disclosure pursuant to section 9.12 of 10CFR and section 2.790(d) of 10CFR.
Yours very,t g,
/
WF. L. Clayton, Jr.
FLCJr/JGS:wm Enclosures - Five _(5) copies of Revision Two-to the MASP 8 l 02260(oV3 f
a.
y
+
w w
s 2
cc: Mr. J. P. O'Reilly, Region II Mr. G. F. Trowbridge Mr. R. A. Thomas Y
d
ALABAKA POWER COMPANY Act' ions Taken to. Complete Computer-Controlled Portions of Security System DATE ACTION April 5, 1979 Met with vendor and compiled a{lisE
~
of outstanding items and dates"for resolution.
Obtained a signed agree-ment as a result of the meeting.)
July 10, 1979 Letter was sent to vendor outlining in detail documentation problems and requesting resolution.
August, 1979 Completed the indepth System Preop Test FNP-1-ETP-101.
Identified de-ficiencies requiring corrective action.
September, 1979 Design change requests written, ex-pedited, tracked to correct system test deficiencies.
October 16, 1979 Letter was sent to vendor requesting copies of proprietary information re-quired to troubleshoot and maintain the system.
$g November 8, 1979 Distributed copies of the Unit 1 Security, System Completion Punchlist containing s
all items required to complete the system $O November 28, 1979 Letter to vendor outlining outstanding 1
problemsandreiteriatingpreviousletters\\.
and problems,
.h December 18, 1979 Distributed copies of the Unit 1 Security System Completion Punchlist Update.
January 8, 1980 Letter to vendor listing items still need-ing resolution and referencing previous letters.
January 10, 1980 Letter to vendor. transmitting comments on
.g a Non-disclosure Agreement J.'
February 21, 1980 Transmitted signed copies of Non-disclosure Agreement to vendor.
March 11, 1980 Held meeting to resolve door hardware pro-blems.
Placed new hardware on order and initiated design change.
(2)
May 5, 1980 Obtained approval to hire a consultant to appraise the security system problems and resolutions.
May 27-29, 1980 Had consultant come onsite to appraise security system.
July 24, 1980 Formulated a plan of action to take several steps to resolve the remaining items on the security system.
August 22, 1980 Had meeting onsite to discuss problems. Vendor was confirmed to be in attendance but did not attend.
September 19, 1980 Wrote letter to vendor outlining list of out-standing problems and requesting action be taken to resolve.
September 23, 1980 Letter from the vendor responding to the outstand-ing problems.
October 22, 1980 Meeting between vendor and Bechtel Engineering to discuss resolution of problems.
November 11, 1980 Transmitted a draft supplemental legal agreement to vendor in an attempt to secure assurance of fullfilling contract commitments.
November 19, 1980 Vendor transmitted revised supplemental legal agreement to Alabama Power Company.
November 25, 1980 Letter from APCo V.P. Nuclear Generation to vendor sending revised supplemental' legal agreement for execution.
December 16, 1980 Letter from vendor giving status of work in progress but no mention of the agreement.
January 9, 1981 Letter from APCo V.P. to vendor cancelling the contract.
January 16, 1981 Letter from vendor still wanting to try to complete work on the problems.
February 3, 1981-Had another security system vendor visit the site and discussed possible backfit.
February _ 24, 1981-A meeting is scheduled with another vendor onsite to discuss possibilities of backfit.
. March 18, 1981 Target date for awarding another contract for the completion of the security system.