ML20003B965

From kanterella
Jump to navigation Jump to search
Responds to NRC 801230 Ltr Re Violations Noted in IE Insp Rept 50-187/80-02.Corrective Actions:Performed & Documented Systematic Performance Evaluations for Licensed Reactor Supervisor as Required
ML20003B965
Person / Time
Site: 05000187
Issue date: 01/26/1981
From: Crandall W
NORTHROP RESEARCH & TECHNICAL CENTER
To: Crews J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
Shared Package
ML20003B962 List:
References
327-81-02, 327-81-2, NUDOCS 8102260278
Download: ML20003B965 (1)


Text

, - {'

327-81-02

/

, qNIUII7N

g. q %

January 26, 1931 f9 * <f' 9 5!

k S hqdkp $h U.S. I!ucigar Regulatory Comission

.segion s w/g, gg 1990 :1. California Boulevard Suite 202, Walnut Creek Plaza Walnut Creek, California 94596 Attention: ,1 L. Crews, Chief Reactor Operations and fluclear Support Branch

Reference:

Docket tio. 50-187 Gentl e.nen :

Pursuant to tne provisions of Section 2.201, of the flRC's " Rules of Practice," Part 2, Title 10, Code of Federal Regulations. Section 2.201 requires us to submit to your office, within twenty-five (25) days of the date of your notice, a written statement or explanation in reply including (1) corrective steps wnich have been taken by us and the resuits acnieved; (2) corrective steps which will be taken to avoid further violations; and (3) che date when full compliance will be aclieved.

Contrary to the requirenents of 10 CFR 50, Paragraph 50.G4 (i-1),

the periodic and systematic performance evaluations for the licensed Reactor Supervisor had not been performed and not documented as re-ouired by Paragraph VII of the liRC approved Operator Requalification Training Program.

(1) Corrective steps which have been taken and results achieved; Systemtic performance evaluations for the licensed Reactor Supervisor has been performed and documented as required.

(2) Corrective steps which were taken to void further violations; Periodic file system has been established to review the status of all Heactor personnel's training and performance evaluations.

(3) Date when full compliance was achieved was January 13, 1981.

If you should have any questions concerning this letter, please contact the undersigned.

M -W[g -- -

  1. 2 Walter E. Crandall, Chairman Corporate Radiation Committee N ortheop Cos porarmn . Enht op De,wt h .ind Technutoqy Ccater . One lhear, h Pyk e Palos Verdes Peninsula, Cahf. 90274

,8202200378