Final Revised Deficiency Rept,Originally Reported 800415,re Auxiliary Feedwater Response Time.Mods Will Not Be Completed Per Date Specified in 800512 Rept But Will Be Completed Before Initial Fuel Loading
ML20003B667
Person / Time
Site: Sequoyah Tennessee Valley Authority icon.png
Issue date: 01/21/1981
From: Mills L
TENNESSEE VALLEY AUTHORITY
To: James O'Reilly
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
References
10CFR-050.55E, NCR-SQN-NEB-800, NUDOCS 8102250132
Download: ML20003B667 (1)


Text

.

'C'

TI? ?: E35EE ' t IY

-.a-400 Chestnrt Street Tcwer II January 21, 1981 86 -OI1-03V Mr. James P. O'Reilly, Director Office of Inspection and Enforcement U.S. Nuclear Regulatory Commission Region II - Suite 3100 101 Marietta Street Atlanta, Georgia 30303

Dear Mr. O'Reilly:

.SEQUOYAH NUCLEAR PLANT UNIT 2 - AUXILIARY FEEDWATER RESPCNSE TIME -

NCR SQN NE3 8009 - ADDITIONAL INFCRMATICN The subject deficiency was initially reported to NRC-0IE Inspector C. R. McFarland en April 15, 1980, in accordance with 10 CFR 50.55(e).

A final report was submitted en May 12, 1980.

We have been unable to complete the modifications in accordance with the schedule specified in our final repert; therefore, we are revising our schedule commitment. The modificatiens cutlined in our final report will be cc=plete before initial fuel leading.

If you have any questions, please get in touch with D. L. Lambert at FTS 857-2581.

Very truly yours, TENNESSEE VALLEY AUTHORITY

.,h j. k( l 6 'q. '. E, C...'

L. M. Mills, Manager Nuclear Regulation and Safet -

e

~

cc:

Mr. Victor Stello, Director

[

(g Office of Inspection and Enforcement AT U.S. Nuclear Regulatory Commission Efg'9

(/ 'p3

- 8,SSi Washington, DC 20555 S. u,,, %, %r ~

/

r

' 'X

%n iz1

\\&,t Y&Y k+' 1

,y t e.u. cog'.

81022sois.1 g

. _