Forwards IE Insp Rept 50-155/76-03 on 760105-09 & 0202-06. Noncompliance Noted
ML20002D731
Person / Time
Site: Big Rock Point File:Consumers Energy icon.png
Issue date: 03/05/1976
From: Fiorelli G
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Dewitt R
CONSUMERS ENERGY CO. (FORMERLY CONSUMERS POWER CO.)
Shared Package
ML20002D732 List:
References
NUDOCS 8101220254
Download: ML20002D731 (2)


See also: IR 05000155/1976003

Text

-

s-

.

lKJm

  • '

UNITED STATES

NUCLEAR REGULATORY COMMISSION

,(

REGION lli

~

799 ROOSEVELT ROAD

CLEN ELLYN. ILLINOIS 60137

MAR

5 1976

-

Consumera Power company

Docket No. 50-155

AITNs Mr. R. B. DeWitt

Manager of Eucicar

Plant Operations

212 West Michigan Avenua

Jackson, Michigan

49201

Centlemen

This refers to the inspection conducted by Mr. D. R. Hunter

of this office on Janucry 5-9 and February 2-6, 1976,

and Mescrc. J. A. Finn and L. J. Hueter of this office on

February 3-5, 1976, of activities at Big Rock Point Nuclear

Plant authorized by Reactor Operating License No. DPR-6 and to

the discussion of cur findings with Mr. Hartman and others at

the conclusion of the inopcetion.

The inspection consisted of en examination of your implementa-

tion of your retraining for licensed operators in responsc to

a ret;ucst for inspection by one of your employcos. A copy of

our inspection report is snelosed.

During this inspection, certain of your activitics appeared to

be in noncot:pliance with URC requirements, as described under

Enforcement Items in the Summary of Findings section of the

anclosed inopection report.

Thic notice is sent to you pursuant to the provisions of

Section 2.201 of the NRC's " Rules of Practice," Part 2, Title

10, Code of Federal Regulations. Section 2.201 requires you

to submit to thin office within twenty days of your receipt

of this notice a written statement or explanation in reply,

including for cach iten of noncompliance 2 (1) corrective

action taken and the results echieved; (2) corrective action

to be taken to avoid further noncompliance; and (3) the date

when full compliance will be achieved.

.

<

t/b/ASb A G

.

.

..

. .

-

..

.

. .

.

-

.

.

~

MAR

5 1976

. Constucers Power Company

-2-

f

.

In accordance with Section 2.790 of the ERC's " Rules of

Practice," Part 2. Title 10 Code of Federal Regulations, a

copy of thio notice, the enclosed inspection report, and your

response to this votice will be pinced in the URC's Public

Document Ecom, except as follows. If this report contains

inforration that you or your contractors believe to be

proprictary, you cust apply in uriting to this office, within

,

twenty days of your receipt of this motice, to withhold such

information from public disclosure. The application must

'

include a full statement of the reasons for which the infor-

,

r.ation is considered proprietary, and should be prepared so

'

that proprietary inforr.2 tion identified in the application

is contained in an enclorure to the application.

We vill gladly discuss any questions you have concerning this

inspection.

Sincerely yours,

,

Caston Fiore111, Chief

Reactor Operations and

Nuclear Support Branch

Enclocures

IE Inspection Report No.

050-155/76-03

.

ec w/enci:

Mr. C. J. Eartnan

Plant Superintendent

Mr. S. A. Crelisle

Shift Supervisor

bec w/ enc 1:

PDR

Local PDR

,

NSIC

TIC

Ronald Callen, Michigan Public

Service Commission

Anthony Roisman, Esq., Attorney

.

(

.