ML20002D459

From kanterella
Jump to navigation Jump to search
IE Insp Rept 50-458/80-12 on 801118-21.Noncompliance Noted: Insufficient Lighting of Concrete Placement & Water/Cement Ratio Exceeded Max Allowable
ML20002D459
Person / Time
Site: River Bend Entergy icon.png
Issue date: 12/05/1980
From: Crossman W, Randy Hall, Tapia J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To:
Shared Package
ML20002D444 List:
References
50-458-80-12, NUDOCS 8101210075
Download: ML20002D459 (3)


See also: IR 05000458/1980012

Text

.

/

%)

.

.

U. S. NUCLEAR REGULATORY COMMISSION

OFFICE OF INSPECTION AND ENFORCEMENT

REGION IV

Report No. 50-458/80-12

Docket No. 50-458

Category A2

Licensee:

Gulf States Utilities

Post Office Box 2951

Beaumont, Texas 77704

Facility Name:

River Bend, Unit No. 1

Inspection at:

River Bend Site

Inspection Conducted:

November 18-21, 1980

. Inspector:

y d-

JA[5[80

-J. I. Tapia Rea'ctorIn}4ector,EngineeringSupport

Dat'e

Section

Other Accompanying:

Personnel:

W. B. Jones, Engineering Aide (Co-op)

/2/[/dPD

Approved:

Ov -

W. A. Crossman, Chief, Projects Section

Date

/

/

TU

,-

R. E.~ Hall, Chief, Engineering Support Section

patt

Inspection Summary:

Inspection on November 18-21, 1980 (Report No. 50-458/80-12)

Areas Inspected:

Routine, unannounced inspection of concrete and backfill

placement activities.

The inspection involved twenty-eight hours by one NRC

Inspector.

Results:

In the areas inspected, two Violations were found in the area of

concrete placement (Violation - insufficient lighting of concrete placement -

paragraph 3; and Violation - water / cement ratio exceeded the maximum allowable -

paragraph 3).

8102s2007S

.

'

'

DETAILS

1.

Persons Contacted

Principal Licensee Employees

  • T. C. Crouse, Director of Quality Assurance

J. R. Dungelberg, Assistant Superintendent of Site Construction

P. D. Graham, QA Engineer

J. E. Wimberly, Superintendent of Site Construction

Other Personnel (Stone and Webster)

D. Castleberry, Senior QC Engineer - Structural Steel Welding

  • A. Kamdor, Resident Engineer

S. King, QC Inspection Supervisor - Soils

H. Patton, Senior QC Inspector - Cadwelds

S. Salowitz, Senior QC Inspector - Civil

D. Wells, Chief QC Inspection Supervisor

The IE Inspector also talked with other licensee employees and contractor

personnel including members of the QA/QC and engineering staffs.

  • Denotes those attending the exit interview.

2.

Backfill Placement

Placement of Category I backfill in the areas north and east of the

Diesel Generator Building was observed during this inspection. Work

activities were found to conform with the requirements of S&W Construction

Methods Procedure No. 2.2, Revision 0, " Earthwork," and Quality Assurance

Directive No. 10.4, Revision A, " Earthwork Inspections." Maximum loose

lift thickness and minimum compactor passes were specifically addressed.

Stone & Webster Specification No. 210.100, Revision 1, " Site Development

Work," delineates the requirements and acceptance criteria contained in

the implementing procedures for both bt.ckfill placement and testing.

The

IE Inspector reviewed the results of five relative density tests per-

formed during the period November 12-19, 1980.

The tests were performed

in accordance with ANSI / ASTM D 2049-69, " Standard Test Method for Relative

Density of Cohesionless Soils." Five test results from the same period

performed in accordance with ANSI / ASTM D 422-63 (1972), " Standard Method

for Particle - Size Analysis of Soils," were also reviewed.

The Calibra-

tion Checklist for the Vibratory Table used in the relative density tests

wcs also reviewed.

All records reviewed were found to indicate con-

formance with the design specification requirements.

No violations or deviations were identified.

2

..

3.

Concrete Placement

The IE inspector observed portions of concrete placement No. SC4-W-85-7;

a 3'-6" extegior radigs wall in the No. 1 Standby Cooling Tower, between

azimuths 150 and 180 and extending from elevation 64'-6" to 84'-6".

During the inspection, it was observed that the bottom of the form was

dark, such that the consolidation of the concrete could not be adequately

determined from the top of the form where the S&W QC Inspector was observed

to be performing his inspection.

The S&W QC Inspector did not have a

flashlight for observing the consolidation.

S&W Specification No. 210.370,

Revision 5, " Placing Concrete and Reinforcing Steel," requires that lighting

that can improve the placemer.t of concrete be used wherever practicable.

This requirement was applicable to the placement in question since it was

a twenty foot deep wall which resulted in poor visibility on the date of

placement.

In addition, the failure of the QC Inspector to carry a

flashlight indicates that the consolidation and therefore placement of the

concrete was not improved but rather left to judgements conducted in poor

visibility.

This constitutes a Violation, in that the specification

procedure was not followed.

In process testing results at the field QC station were also reviewed

during placement No. SC4-W-85-7.

A review of the batch tickets disclosed

that ticket No.14335 indicated that 10 additior.al gallons of water were

allowed for jogging at the pumping station.

The ticket indicated that 12

gallons were actually added.

The actual water to cement ratio, computed

from the information on the batch ticket, was 0.397.

The maximum allowable

water to cement ration for this mix H3 is 0.394, in accordance with

S&W Specification No. 210.350, " Specification for Mixing and Delivering

Concrete." S&W Quality Assurance Directive No. 10.2, Revision B,

" Inspection of Batch Plant, Concrete, Reinforcing Steel, and Grout," requires

that water additions be checked to assure the maximum amount allowed by

Specification No. 210.350 is not exceeded.

The fact that the maximum

amount of water allowed was exceeded, and that the concrete was subse-

quently placed, represent a failure to follow quality control procedures.

This is a V1olation.

4.

Exit Interview

The IE Inspector met with the licensee and contractor representatives

denoted in paragraph 1 at the conclusion of the inspection on November 21,

1980.

The scope and findings of the inspection were summarized.

3