Revised Monthly Operating Rept for Nov 1980
ML20002D295
Person / Time
Site: North Anna Dominion icon.png
Issue date: 12/26/1980
From: Rogers L
VIRGINIA POWER (VIRGINIA ELECTRIC & POWER CO.)
To:
Shared Package
ML15030A326 List:
References
NUDOCS 8101200285
Download: ML20002D295 (2)


Text

-__

O VIRGINIA ELECTRIC AND POWER COMPANY NORTH ANNA POWER STATION MONTHLY OPERATING REPORT MONTH November YEAR 3 (Revised 12-26-80) l APPROVED:

STATION MANAGER V

81012oo475

s OPERATING DATA REPORT DOCKET NO.

50-338 DATE 12-26-87 COMPLETED BY cers TELEPHONE 3

-51bl X2520 OPERATING STATUS fly 16yr-to-dateand

1. Unit Name:

North Anna Unit 1 N "a4e

  • 100n
2. Reporting Period:

0 Cumulative have been adjuste i

3. Licensed Thermai Power (MWt): 277ti for Burnup over estimation
4. Nameplate Rating (Gross MWe):

947 during October.

5. Design Electrical Rating (Net MWe): 907
6. Maximum Dependable Capacity (Gross MWe):

ERO

7. Maximum Dependable Capacity (Net MWe):

850

8. If Changes Occ= in regis-ity katings (Items Nu nber 3 Through 7) Since Last Report, Give Reasons:

N/A

9. Power Level To Which Restricted,!f Any (Net MWe):

N/A

10. Reasons For Restrictions.If Any:

N/A This Month Yr..to.Date Cumulative

11. Hours In Reporting Period 770 A nan 21.817
12. Number Of Hours Reactor Was Critical 770 7 1 c;t; c:

17 7?n_R

13. Reactor Reserve Shutdown Hours 0

' 64.3

'21 3.1

14. Hours Generator On-Line 720 6.441 7 16.996.4
15. Unit Reserve Shutdown Hours 0

0 0

16. Gross Thermal Energy Generated (MWH) 1.793,316 17.346.043 43.625.956
17. Gross Electrical Energy Generated (MWH) 582,355,_,

5,585,018 13.913.367

18. Net Electrical Energy Generated (MWH) 549,449 5,256.749 13.110.195 100 86.4 77.9
19. Unit Service Factor
20. Unit Availability Factor 100 86.4 77.9
21. Unit Capecity Factor (Using MDC Net) 89.8 76.9 70_7
22. Unit Capacity Factor (Using DER Net) 84 I 72 1 AA 1 0

7.5 6.I

23. Unit Forced Outage Rate
24. Shutdowns Scheduled Over Next 6 Months (Type. Date,and Duration of Each t:

Refnplinn TMT and Firo prntar+4nn un A 4 r 4,. o 4,,,,,. Decomhar 11. 10Rn. A wantee

~

Maintenancet May 1. 1981: 10 davs

25. If Shut Down At End Of Report Period. Estimated Date of Startup:

N/A

26. Units In Test Status (Prior to Commercial Operation):

Forecast Achieved INITIAL CRITICALITY INITIAL ELECTRICITY COMMERCIAL OPERATION (4/77)

-.