| | | Reporting criterion |
|---|
| 05000346/LER-1980-001, Forwards LER 80-001/01T-0 | Forwards LER 80-001/01T-0 | |
| 05000346/LER-1980-001-01, /01T-0:on 800103,during Plant Heatup,Safety Features Actuation Sys Channels 1 & 3 Tripped at 1,600 Psig, Causing Level 2 Actuation.Operators Correctly Tripped Reactor Coolant Pumps.Caused by Procedural Deficiency | /01T-0:on 800103,during Plant Heatup,Safety Features Actuation Sys Channels 1 & 3 Tripped at 1,600 Psig, Causing Level 2 Actuation.Operators Correctly Tripped Reactor Coolant Pumps.Caused by Procedural Deficiency | |
| 05000346/LER-1980-002, Forwards LER 80-002/03L-0 | Forwards LER 80-002/03L-0 | |
| 05000346/LER-1980-002-03, /03L-0:on 800103,after Actuating of Safety Features Actuation Sys Level 2,demin Water Valve DW68318 Did Not Indicate Closed & Monitor Light Did Not Indicate Properly.Caused by Maladjusted Position Indicator Switch | /03L-0:on 800103,after Actuating of Safety Features Actuation Sys Level 2,demin Water Valve DW68318 Did Not Indicate Closed & Monitor Light Did Not Indicate Properly.Caused by Maladjusted Position Indicator Switch | |
| 05000346/LER-1980-003-03, /03L-0:on 800103,during Auxiliary Feedwater Pump Test,Pump l-1 Was Declared Inoperable.Caused by Improperly Adjusted Slip Clutch Between Governor Manual Speed Adjustment Shaft & Remotely Controlled Speed Changer Motion | /03L-0:on 800103,during Auxiliary Feedwater Pump Test,Pump l-1 Was Declared Inoperable.Caused by Improperly Adjusted Slip Clutch Between Governor Manual Speed Adjustment Shaft & Remotely Controlled Speed Changer Motion | |
| 05000346/LER-1980-003, Forwards LER 80-003/03L-0 | Forwards LER 80-003/03L-0 | |
| 05000346/LER-1980-004-03, /03L-0:on 800107,control Rod 5-11 Absolute Position Indication Declared Inoperable Due to Fluctuating Signals.Possibly Caused by Isolation of Position Indication Cabling & Electrical Penetration | /03L-0:on 800107,control Rod 5-11 Absolute Position Indication Declared Inoperable Due to Fluctuating Signals.Possibly Caused by Isolation of Position Indication Cabling & Electrical Penetration | |
| 05000346/LER-1980-004, Forwards LER 80-004/03L-0 | Forwards LER 80-004/03L-0 | |
| 05000346/LER-1980-005, Forwards LER 80-005/03L-0 | Forwards LER 80-005/03L-0 | |
| 05000346/LER-1980-005-03, /03L-0:on 800110,Tech Spec Late Date Passed W/O Performance of Boric Acid Flowpath Heat Tracing Weekly Test. Caused by Known Deficiency in Design of Sys Resulting in Inability to Maintain Min Temp Necessary During Startup | /03L-0:on 800110,Tech Spec Late Date Passed W/O Performance of Boric Acid Flowpath Heat Tracing Weekly Test. Caused by Known Deficiency in Design of Sys Resulting in Inability to Maintain Min Temp Necessary During Startup | |
| 05000346/LER-1980-006-03, /03L-0:on 800112,found Fiberglass Insulation Stuffed Into Open Wall Ventilator Between Water Treatment Bldg & Svc Water Valve Room,Causing Fire Damper to Be Inoperable.Figerglass Removed | /03L-0:on 800112,found Fiberglass Insulation Stuffed Into Open Wall Ventilator Between Water Treatment Bldg & Svc Water Valve Room,Causing Fire Damper to Be Inoperable.Figerglass Removed | |
| 05000346/LER-1980-006, Forwards LER 80-006/03L-0 | Forwards LER 80-006/03L-0 | |
| 05000346/LER-1980-007, Forwards LER 80-007/03L-0 | Forwards LER 80-007/03L-0 | |
| 05000346/LER-1980-007-03, /03L-0:on 800116,ref Position Verification for Group 5,rod 11,was Made 1-h & 40 Minutes Late.Caused by Operator Oversight Due to Lack of Adequate Reminder Sys. Multiple Timer Sys Will Prevent Recurrence | /03L-0:on 800116,ref Position Verification for Group 5,rod 11,was Made 1-h & 40 Minutes Late.Caused by Operator Oversight Due to Lack of Adequate Reminder Sys. Multiple Timer Sys Will Prevent Recurrence | |
| 05000346/LER-1980-008-03, Gap Discovered in Wall Where Five two-inch Conduits Go from Electrical Penetration Room 2 to Cable room.Six-inch Gap Around Ventilation Duct Also Found.Caused by Improper Initial Installation | Gap Discovered in Wall Where Five two-inch Conduits Go from Electrical Penetration Room 2 to Cable room.Six-inch Gap Around Ventilation Duct Also Found.Caused by Improper Initial Installation | |
| 05000346/LER-1980-008, Forwards Revised LER 80-008/03L-1 | Forwards Revised LER 80-008/03L-1 | |
| 05000346/LER-1980-009, Forwards LER 80-009/03L-0 | Forwards LER 80-009/03L-0 | |
| 05000346/LER-1980-009-03, /03L-0:on 800122,discovered That NI-7 Indication on Computer Group 38 Was Reading Less than Heat Balance Power,Putting NI-7 Below Instrumentation Operability Limit Line.Caused by Extremely Tight Calibr Band at 100% Power | /03L-0:on 800122,discovered That NI-7 Indication on Computer Group 38 Was Reading Less than Heat Balance Power,Putting NI-7 Below Instrumentation Operability Limit Line.Caused by Extremely Tight Calibr Band at 100% Power | |
| 05000346/LER-1980-010-01, /01T-0:on 800214,reanalysis of RCS Pipe Restraints Per IE Insp Rept 50-346/79-23 Revealed Design Deficiency on Two Reactor Coolant Hot Leg Pipe Whip Restraints at Top of Each RCS Hot Leg.Caused by Design Error | /01T-0:on 800214,reanalysis of RCS Pipe Restraints Per IE Insp Rept 50-346/79-23 Revealed Design Deficiency on Two Reactor Coolant Hot Leg Pipe Whip Restraints at Top of Each RCS Hot Leg.Caused by Design Error | |
| 05000346/LER-1980-010, Forwards LER 80-010/01T-0 | Forwards LER 80-010/01T-0 | |
| 05000346/LER-1980-011, Forwards LER 80-011/03L-0 | Forwards LER 80-011/03L-0 | |
| 05000346/LER-1980-011-03, /03L-0:on 800131,during Normal Operation, Operations Personnel Received Half Trip on Steam & Feedwater Rupture Control Sys Channels 1/3.Caused by Spurious Trip from +25 Volt Dc Power Supply PS03 in Sglic Channel 1 | /03L-0:on 800131,during Normal Operation, Operations Personnel Received Half Trip on Steam & Feedwater Rupture Control Sys Channels 1/3.Caused by Spurious Trip from +25 Volt Dc Power Supply PS03 in Sglic Channel 1 | |
| 05000346/LER-1980-012-03, /03L-0:on 800201,operator Noticed Loss of Control Room Position Indication for Letdown Cooler Isolation Valve MU2A.Caused by Design Deficiency.Apparently,Someone Brushed Up Against Disconnect Breaker Switch.Switch Reposition | /03L-0:on 800201,operator Noticed Loss of Control Room Position Indication for Letdown Cooler Isolation Valve MU2A.Caused by Design Deficiency.Apparently,Someone Brushed Up Against Disconnect Breaker Switch.Switch Repositioned | |
| 05000346/LER-1980-012, Forwards LER 80-012/03L-0 | Forwards LER 80-012/03L-0 | |
| 05000346/LER-1980-013, Forwards LER 80-013/03L-0 | Forwards LER 80-013/03L-0 | |
| 05000346/LER-1980-013-03, /03L-0:on 800208,w/reactor Startup in Progress, Personnel Noted Control Rod 5-11 Absolute Position Indication Was Not Responding.Caused by Blown Fuse F14 in Position Ref Panel | /03L-0:on 800208,w/reactor Startup in Progress, Personnel Noted Control Rod 5-11 Absolute Position Indication Was Not Responding.Caused by Blown Fuse F14 in Position Ref Panel | |
| 05000346/LER-1980-014, Forwards LER 80-014/03L-0 | Forwards LER 80-014/03L-0 | |
| 05000346/LER-1980-014-03, /03L-0:on 800208,pressurizer Sample Sys Containment Isolation Valve RC240B Failed to Close Twice. Caused by Improper Torque Switch Setting & Stripped Screw on Closing Contactor.Settings Readjusted & Switch Replaced | /03L-0:on 800208,pressurizer Sample Sys Containment Isolation Valve RC240B Failed to Close Twice. Caused by Improper Torque Switch Setting & Stripped Screw on Closing Contactor.Settings Readjusted & Switch Replaced | |
| 05000346/LER-1980-015, Forwards LER 80-015/03L-0 | Forwards LER 80-015/03L-0 | |
| 05000346/LER-1980-015-03, /03L-0:on 800210,during Normal Startup,Control Rod 5-11 Absolute Position Indication Declared Inoperable.Caused by Numerous Asymmetric Rod Alarms.Data from Current Failure Evaluated | /03L-0:on 800210,during Normal Startup,Control Rod 5-11 Absolute Position Indication Declared Inoperable.Caused by Numerous Asymmetric Rod Alarms.Data from Current Failure Evaluated | |
| 05000346/LER-1980-016, Forwards LER 80-016/03L-0 | Forwards LER 80-016/03L-0 | |
| 05000346/LER-1980-016-03, /03L-0:on 800213,while Reviewing Station Log,Shift Foreman Discovered That Containment Airlock Seal Leakage Test Had Not Been Performed After Last Entry Into Containment During Startup.Caused by Procedural Inadequacy | /03L-0:on 800213,while Reviewing Station Log,Shift Foreman Discovered That Containment Airlock Seal Leakage Test Had Not Been Performed After Last Entry Into Containment During Startup.Caused by Procedural Inadequacy | |
| 05000346/LER-1980-017-03, /03L-0:on 800217,operations Personnel Noted That Safety Features Actuation Sys Channel 3 Borated Water Storage Tank Level Indication Was Six Feet Higher than Other Meters.Caused by Freezing of Transmitter Sensing Line | /03L-0:on 800217,operations Personnel Noted That Safety Features Actuation Sys Channel 3 Borated Water Storage Tank Level Indication Was Six Feet Higher than Other Meters.Caused by Freezing of Transmitter Sensing Line | |
| 05000346/LER-1980-017, Forwards LER 80-017/03L-0 | Forwards LER 80-017/03L-0 | |
| 05000346/LER-1980-018-03, /03L-0:on 800226,safety Features Actuation Sys Channel 3 Borated Water Storatge Tank Level Indication Was Discovered Reading Four Feet Higher than Other Three Channels.Caused by Inadequate Design of Freeze Protection | /03L-0:on 800226,safety Features Actuation Sys Channel 3 Borated Water Storatge Tank Level Indication Was Discovered Reading Four Feet Higher than Other Three Channels.Caused by Inadequate Design of Freeze Protection | |
| 05000346/LER-1980-018, Forwards LER 80-018/03L-0 | Forwards LER 80-018/03L-0 | |
| 05000346/LER-1980-019, Forwards LER 80-019/01T-0 | Forwards LER 80-019/01T-0 | |
| 05000346/LER-1980-019-01, /01T-0:on 800325 Reactor Flux/Flow Trip Setpoints Were Not Verified to Be Properly Reset within 4-h of Manual Shutdown of Rcp.Caused by Attention Given to Feedwater Swings.Trip Setpoints Verified Later | /01T-0:on 800325 Reactor Flux/Flow Trip Setpoints Were Not Verified to Be Properly Reset within 4-h of Manual Shutdown of Rcp.Caused by Attention Given to Feedwater Swings.Trip Setpoints Verified Later | |
| 05000346/LER-1980-020, Forwards LER 80-020/03L-0 | Forwards LER 80-020/03L-0 | |
| 05000346/LER-1980-020-03, /03L-0:on 800306,control Operator Noted No Control Room Indication for Containment Vacuum Relief Isolation Valve CV5072.Caused by Breaker BE1139 Being Closed,Probably Resulting from Someone Bumping Into Breaker | /03L-0:on 800306,control Operator Noted No Control Room Indication for Containment Vacuum Relief Isolation Valve CV5072.Caused by Breaker BE1139 Being Closed,Probably Resulting from Someone Bumping Into Breaker | |
| 05000346/LER-1980-021, Forwards LER 80-021/03L-0 | Forwards LER 80-021/03L-0 | |
| 05000346/LER-1980-021-03, /03L-0:on 800313,during Diesel Fire Protection Pump Weekly Test,Pump Could Not Be Stopped W/Control Button. Once Stopped,Pump Could Not Be Started.Cause Not Determined by Scheme Check.Retrial of Pump Proved Successful | /03L-0:on 800313,during Diesel Fire Protection Pump Weekly Test,Pump Could Not Be Stopped W/Control Button. Once Stopped,Pump Could Not Be Started.Cause Not Determined by Scheme Check.Retrial of Pump Proved Successful | |
| 05000346/LER-1980-022-03, /03L-0:on 800317,operations Personnel Noticed Loss of Control Room Indication for Containment Dihydrogen Analyzer 2 Discharge Line Valve CV5010E.Caused by Const Personnel Accidentally Opening Breaker | /03L-0:on 800317,operations Personnel Noticed Loss of Control Room Indication for Containment Dihydrogen Analyzer 2 Discharge Line Valve CV5010E.Caused by Const Personnel Accidentally Opening Breaker | |
| 05000346/LER-1980-022, Forwards LER 80-022/03L-0 | Forwards LER 80-022/03L-0 | |
| 05000346/LER-1980-023, Forwards LER 80-023/03L-0 | Forwards LER 80-023/03L-0 | |
| 05000346/LER-1980-023-03, /03L-0:on 800327,discovered That Control Rod Groups 3 & 4 Were Moving in on Their Own.Group 3 Was 0% Withdrawn.Group 4 Was 90% Withdrawn.Caused by Component Failure.Component Replaced | /03L-0:on 800327,discovered That Control Rod Groups 3 & 4 Were Moving in on Their Own.Group 3 Was 0% Withdrawn.Group 4 Was 90% Withdrawn.Caused by Component Failure.Component Replaced | |
| 05000346/LER-1980-024-03, /03L-0:on 800327,following Normally Initiated Reactor Trip,Auxiliary Feed Pump Turbine 1-2 Main Steam Isolation Valve MS-107 Closed.Cause Unknown.Further Investigation of Valve & Operator Will Be Pursued | /03L-0:on 800327,following Normally Initiated Reactor Trip,Auxiliary Feed Pump Turbine 1-2 Main Steam Isolation Valve MS-107 Closed.Cause Unknown.Further Investigation of Valve & Operator Will Be Pursued | |
| 05000346/LER-1980-024, Forwards LER 80-024/03L-0 | Forwards LER 80-024/03L-0 | |
| 05000346/LER-1980-025-03, /03X-1:on 800330,control Rod Group 5,rod 11 Absolute Position Indication Declared Inoperable.Caused by Fluctuating Signals Resulting in Numerous Asymmetric Rod Alarms Due to Defective Reed Switch Assemblies | /03X-1:on 800330,control Rod Group 5,rod 11 Absolute Position Indication Declared Inoperable.Caused by Fluctuating Signals Resulting in Numerous Asymmetric Rod Alarms Due to Defective Reed Switch Assemblies | |
| 05000346/LER-1980-025, Forwards LER 80-025/03X-1 | Forwards LER 80-025/03X-1 | |