l OPERATING DATA REPORT 1
DOCKET NO. 50 - 352 i
DATE DECEMBER 14, 1989 COMPLETED BY PHILADELPHIA ELECTRIC COMPANY j
J. J. MURPHY REPORTS SUPERVISOR PROJECTS DIVISION LIMERICK GENERATING STATION j
TELEPHONE (215) 327-1200 EXTENSION 3752 OPERATING STATUS
- 1. UNIT NAME: LIMERICK UNIT 1 NOTES: THERE WERE TWO LOAD 1
- 2. REPORTING PERIOD: NOVEMBER. 1989 REDUCTIONS GREATER THAtt 1
a
- 3. LICENSED 7HERMAL POWER (MWT):
3293 20%
4 NAMEPLATE RATING (GROSS MWE):
1138 I
- 5. DESIGN-ELECTRICAL RATING (NET MWE):
10$$
i
- 6. CAXIMUM DEPENDABLE CAPACITY (GROSS MWE): 1092
- 7. CAXIMUM DEPENDABLE CAPACITY (NET WWE):
1055
- 8. IF CHANGES OCCUR IN CAPACITY RATINGS (ITEMS NUMBER 3 THROUGH 7) SINCE LAST REPORT. GIVE REASONS:
- 9. POWER LEVEL TO WHICH RESTRICTED. IF ANY (NET WWE):
- 10. REASONS FOR RESTRICTIONS. !F ANY:
THIS MONTH YR-TO-DATE CUMULATIVE 11. HOURS IN REPORTING PERIOD 720 8.016 33.576
- 12. NUMBER OF HOURS REACTOR WAS CRITICAL 720.0 5.040.5 26.384.8
- 13. REACTOR RE$ERVE SHUTDOWN HOURS 0.0 0.0 0.0 10 HOURS-GENERATOR ON-LINE 720.0 4.894.9 25.927.6 l
lb UNIT RESERVE SHUTDOWN HOURS 0.0 0.0 0.0 16.-GROSS THERMAL ENERGY GENERATED (WWH) 2.328,667 14,627.883 75,425.640
...s........
- 17. GROSS ELECTRICAL ENERGY GENERATED (MWH) 757.440 4.710.400 24.392.070
- 18. NET ELECTRICAL ENERGY GENERATED (MWH) 729,Ge4 4.448.612 23.291.100 PAGE 1 OF 2 9001250113 900111 PDR ADOCK 05000352 R
7-i 3901010490 t
OPERATING DATA REPORT (CONTINUED)
DOCKETNO.50-352l t
l DATE DECEMBER 14, 1989 THIS MONTH YR-TO.DATE CUMULATIVE
'19. UNIT SERVICE FACTOR 100.0 61.1 77.2
- 20. UNIT AVAILA81LITY FACTOR 100.0 61.1 77.2
- 21. UNIT CAPACITY FACTOR (USING MDC NET) 96.1 52.6 65.8
- 22. UNIT CAPACITY FACTOR (USING DER NET) 96.1 52.6 65.8 23.~ UNIT FORCED OUTAGE RATE 0.0 0.0 3.0 24 SHUTDOWNS SCHEDULED OVER NEXT 6 MONTHS (TYPE, DATE, AND DURATION OF EACH):
- 25. IF SHUTDOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF STARTUP:
- 26. UNITS IN TEST STATUS (PRIOR TO COMMERCI AL OPERATION):
FORECAST ACHIEVED INITIAL CRITICALITY 12/19/84 12/22/84 INITIAL ELECTRICITY MID APRIL 85 4/13/85 COMMERCIAL OPERATION IST OTR 86 2/01/86 PAGE 2 0F 2