Enclosure 3 - Draft Environmental Site Audit Schedule
ML19353C719
Person / Time
Site: SHINE Medical Technologies
Issue date: 12/19/2019
From: Jennifer Davis
NRC/NMSS/DREFS/ENRB
To:
SHINE Medical Technologies
Davis J
Shared Package
ML19353C687 List:
References
Download: ML19353C719 (1)


Text

SHINE ENVIRONMENTAL SITE AUDIT SCHEDULE Tuesday, February 4, 2020 Travel day for U.S. Nuclear Regulatory Commission (NRC) Staff Wednesday, February 5, 2020 The NRC staff arrive at SHINE Headquarters.

SHINE Presentations:

  • Overview presentation of the radioisotope production process that highlights the changes in the production process and changes in facility layout.

General Site Tour - view construction that is under way.

Tour of Building One Resource-specific meetings regarding information needs SHINE Headquarters.

Thursday, February 6, 2020 Resource-specific meetings on information needs Exit meeting.

Friday, February 7, 2020 Travel day for NRC staff.

ENCLOSURE 3