ML19353A357

From kanterella
Jump to navigation Jump to search
Ack Receipt of 800922 & 1027 Ltrs Informing NRC of Steps Taken to Correct Violation Noted in IE Insp Repts 50-518/80-17 & 50-520/80-17.Disagrees W/Response Refuting Items of Noncompliance
ML19353A357
Person / Time
Site: Hartsville  Tennessee Valley Authority icon.png
Issue date: 12/05/1980
From: Murphy C
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: Parris H
TENNESSEE VALLEY AUTHORITY
Shared Package
ML19353A358 List:
References
NUDOCS 8101080267
Download: ML19353A357 (4)


See also: IR 05000518/1980017

Text

o

UNITED STATES

[b

!';3 ,7

j

NUCLEAR REGULATORY COMMISSION

,y

s

REGION 11

o, -

'[

i31 MARIETT A ST., N.W., SUIT E 3100

  • \\

j'

ATLANTA, G EORGI A 30303

DEC

5 1980

In Reply Refer To:

  1. Enh

0-520/80-17f

Tennessee Valley Authority

ATTN:

H. G. Parris

Manager of Power

500A Chestnut Street Tower II

Chattanooga, TN 37401

Gentlemen:

Thank you for your letters of September 22, and October 27,1980, informing

us of steps you have taken to correct the items of noncompliance concerning

activities under NRC Construction Pennit Nos. CPPR-150 and CPPR-152 brought

to your attention in our letter of August 28, 1980.

We have examined your corrective actions and plans as detailed in your letter

of response. As a result of this review, the following coments are made:

1.

We do not concur with your response to infraction 518, 529/80-17-01,

" Inadequate Magnetic Particle Examination Program," for the following

reasons:

a.

(Re:

TVA letter dated October 27) Both the NRC inspector and the

TVA level III examiner witnessed the magnetic particle examination

(itT) of the anchor bolt chair weld. After the MT uas completed,

the NRC inspector identified three major discrepancies in the

examination and discussed these with the TVA level III examiner.

l

The three major discrepancies discussed were:

(1) not observing

the powder formation during application; (2) vigorous blowing to

remove excess powder; and (3) inadequate overlap of the test

prods. At the time of this discussion, the TVA level III examiner

concurred with the NRC inspector.

b.

(Re:

TVA letter dated October 27) Regarding the authorized

Nuclear Inspector's position, it should be noted that during

the MT the Authorized Nuclear Inspector (ANI) assisted the MT

examiner in performing the examination. The ANI held the light

source for the examiner and assisted in the evaluation of the

test results.

It is, therefore, questionable how the ANI can

~

x

ro

form an objective opinion of the examination when he had a part

$

1:n perfonning the examination.

i

a

b

h

k

1

1.}

. D!

'

!#5

8

l

w

a

1

'

&

.

a 2 0108 0967

.

.

.

DEC

5 1980

.-

.

.

e

Tennessee Valley Authority

-2-

,

c.

(Re: TVA letter dated October 27 and TVA letter dated September 22)

With regard to the MT written procedure, it is agreed that the

training function is of utmost importance and that examiner

candidates learn such things as applying and removing MT powder

and the amount of overlap required for 100 percent coverage of

the test surface. However, pertinent infonnation, such as the

methods of applying and removing the MT powder, needs to be part

of the written procedure in order to reinforce the training aspects

and to make the specified methods mandatory.

In addition, examination

procedures should include all steps necessary for the accomplishment

of the examination, not just those items specified by the applicable

code. The need for additional steps is evidenced by the failure to

properly accomplish the test. The same can be said of prod overlap.

Different size pipe welds, weld preps, fittings, fillet welds,

fasteners, etc., all require a somewhat different grid pattern to

ensure 100 percent coverage.

Detailed procedures are required to

eliminate the need for an examiner to remember all this from

training, particularly when some items may not be examined very

often. The use of a field indicator to assure coverage is good

practice, however, this does not necessarily identify the dead

zone near the prods, nor is it practical to expect the examiner

to use it in the field for every prod position on complex shapes

to ensure coverage. This sort of testing is normally done in a

laboratory and the results plotted graphically and made part of

the written procedure for the examiner to follow in the field.

d.

(Re: TVA letter dated September 22) With regard to the lighting

of the test surface, NRC agrees that ASME does not specifically

require a " beam of light" to always be directed on the test surface

during testing. However, ASME does specify observation of the test

surface during application of the MT powder and it does require

adequate lighting for this observation. Since it is difficult, if

not impossible, to observe the test surface in a darkened environ-

ment, the source of light should be directed in a manner that would

permit observation of the test surface.

During the MT of the subject

welds, the light source at times was directed on top of the yoke

holders hand and did not illuminate the test surface.

e.

(Re: TVA letter dated September 22) Regarding the tests by

manometer of powder blowers used by TVA, the NRC inspector

advised the level III examiner that the test setup did not comply

with that recomended in SE-109 of ASME,Section V.

NRC agrees

that the test conducted by TVA on the manometer produced an air

pressure less than that specified as a maximum in ASME.

However,

using TVA's setup with an even larger funnel, even less air pressure

would be produced, and if the funnel was made large enough, the air

pressure from the MT bulb would have no effect at all on the water

column. Yet the same MT bulb would be used and it would discharge

the same air pressure. Therefore, TVA's argument that their

sample tests by manometer proved the MT bulbs produced less air

pressure than that specified in ASME is invalid.

,.

_

.

_

.-

DEC

5 1980

'

Tennessee Valley Authority

-3-

f.

,(Re: TVA letter dated September 22) With regard to the overlap

being sufficient because only an excavation of a weld repair

was being examined, no dissagreement exists for coverage of the

excavation. However, the excavation was on one side of the tee

weld, while the other side of the tee weld had what appeared to

be a completed weld for the entire length of the vertical member.

Furthemore, more than just one excavation was examined; both

sides of the weld joining the member in the horizontal position

were examined in addition to the opposite side of the vertical

member.

2.

We do not concur with your response to Infraction 518, 520/80-17-02,

" Inadequate qualification requirements for visual examiners,?" for the

following reasons:

a.

(Re:

TVA letter dated September 22) With regard to the three year

requalification for~ visual evaminers, the NRC inspector asked the

TVA level III examiner whether his program required a three year

requalification and he said no.

b.

(Re:

TVA letter dated September 22) With regard to the minimum of

ten check points specified for the practical examination, the NRC

inspector was advised that numerous checkpoints were used but were

not formally documented.

In your response you indicate that the

checkpoints were not formally documented. Unless fomal documen-

tation exists, accomplishment of the program cannot be verified.

c.

(Re:

TVA letter dated October 27 and TVA letter dated September 22)

With regard to workmanship samples and training / qualification samples,

information in your response is not in agreement with that provided

the NRC inspector at the time of the inspection. There were no

samples available at the time of the NRC inspection that represented

acceptable / unacceptable surface conditions of coarse ripples, grooves,

abrupt ridges and valleys.

Furthemore, during the inspection, the

NRC inspector asked 1hether the taper at the end of a counterbore

was discussed in training and if samples were available that depicted

acceptable / unacceptable transitions.

The inspector raised this

question while reviewing a pipe sample with an unacceptable taper

condition at tne end of a counterbore. The TVA level III examiner

advised the NRC inspector that this condition had not been considered

in training or qualificathn and that he had no samples specifically

depicting the condition. However, in your response dated October 27,

you state that th:n are three examples of 3-1 transitions that are

used in the training program.

_

r

'

DEC

5 1980

.

Tennessee Valley Authority

-4-

It is pointed out that the NRC inspector described each of the infractions

in detail during the exit interview. No discussion or rebuttal of the

discrepancies described was made by TVA attendees.

In view of the a bve,

the Notice of Violation transmitted to you on August 28, 1980, remains

unchanged. Section 2.201 requires you to submit to this office a writtee

statement or explanation in reply including:

(1) corrective steps which

have been taken by you and the results achieved; (2) corrective steps which

will be taken to avoid further noncompliance; and (3) the date when full

compliance will be achieved.

We appreciate your cooperation With us.

,

Sincerely,

Charles E. iiurphy, C ief

Reactor Construction and

Engineering Support Branch

'

cc:

R. T. Hathcote, Project Manager

J. F. Cox, Supervisor, Suclear

Licensing Section

J. E. Wills, Project Engineer

H. N. Culver, Chief, Nuclear

Safety Review Staff

!

,

, . , , .

,--4. . . . , . .

,-.n..,-

,..,wa--

, - , . -

, . -

,.

,_.