Submits Preliminary Schedule for Complex Concrete Restart Program & STP Welding Program for Reinsp & Repair of Existing Welds & Restart Plan Re safety-related Aws & ASME Welding.Requests 800913 Meeting in Arlington,Tx
ML19353A325
Person / Time
Site: South Texas  STP Nuclear Operating Company icon.png
Issue date: 09/04/1980
From: Oprea G
HOUSTON LIGHTING & POWER CO.
To: Seyfrit K
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
Shared Package
ML19353A322 List:
References
ST-HL-AE-526, NUDOCS 8101080140
Download: ML19353A325 (1)


Text

a svuatus 1 fju k

Lghiing i

i 7/ c i q O

m & Po.ver ll g\\

(OmjX1ny

,c flettric Timer September 4,1980 ff' [l..

Po lh I/00 S T -liL AE -526

[!l

(-

!!auston.Teus 7/001 SFN: B - S P,0 0 Mr. Karl Scyfrit

/7 c

' );); Mr.

! : p'o; gl[ l

w Director, Region IV l

-1

-'l NucIcar Regulatory Commission

[! J t '. '._:s{;.

t 611 Ryan Plaza Drive c

Suite 1000 p;

Arlington, Texas 76001 S ubject : South Texas Project Units 1 & 2 Safety Related \\Velding Docket Nos. STN 50-498, STN 50-499 South Texas Project Electric Generating Station,

Dear Mr. Seyfrit:

As we discussed on September 2, we are in the process of finalizing the complex concrete restart program and the STP Welding Program covering both the re-inspection and repair of existing welds and the Restart Plan for Safety Related AWS and ASME Welding.

For planning purposes, we are providing you with the following preliminary information : We intend to satisfy all prerequisites to:

A.

Start re--inspection and repair of existing AWS welds by September 22, 1980.

B.

Restart AWS welding (new welds) by September 22, 1980.

C.

Start re-inspection of existing ASME welds by September 24, 1980.

D.

Start repair of existing ASM3 ucids by October 15, 1980.

E.

Restart ASME welding (new walds) by October 15, 1980.

l F.

Restart complex concrete pours by October 13, 1980.

l We would like to schedule a meeting to review the details of these programs with you and your staff at the Region IV offices in i

Ar lington on September 13, 1930.

l Yours very truly, l

,- l l

  1. j M

f } ? g -G >r,ea,ric !'P -

--w/

e Execuf{ve Vice President GWO /sra I'l 0 1