ML19352A812

From kanterella
Jump to navigation Jump to search
Forwards IE Insp Rept 50-373/81-18 on 810415,20-23,27-30 & 0501.No Noncompliance Noted
ML19352A812
Person / Time
Site: LaSalle Constellation icon.png
Issue date: 05/19/1981
From: Norelius C
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Reed C
COMMONWEALTH EDISON CO.
Shared Package
ML19352A813 List:
References
NUDOCS 8106020166
Download: ML19352A812 (2)


See also: IR 05000373/1981018

Text

.

.

Ild -

[*aaeg%,

UNITED STATES

8

NUCLEAR REGULATORY COMMISSION

o

E

,E

REGION 111

.

(%

e"[

s

790 ROOSEVELT ROAD

GLEN ELLYN. ILLINOIS 80137

...**

.MM

9:981

,

/G

.q,

v'/

g

Docket No. 50-373

(

/ g@/4 ']T

Commonwealth Edison Company

m

/

ATTN:

Mr. Cordell Reed

US

Vice President

\\

Post Office Box 767

Chicago, IL 60690

,jQ,

Gentlemen:

This refers to the routine safety inspection conducted by

Messrs. K. A. Connaughton, I. N. Jackiw and D. L. Robinson of this

office on April 15, 20-23, 27-30, and May 1, 1981, of activities

at LaSalle County Station authorized by NRC Construction Permit

No. CPPR-99 and to the discussion of our findings with R. Holyoak

and others of your staff at the conclusion of the inspection.

The enclosed copy of our inspection report identifies areas examined

during the inspection. Within these areas, the inspection consisted

of a selective examination of procedures and representative records,

observations, and interviews with personnel.

No items of noncompliance with NRC requirements were identified during

the course of this inspection.

In accordance with 10 CFR 2.790 of the Commission's regulations, a copy

(

of this letter and the enclosed inspection report will be placed in the

l

NRC's Public Document Room.

If this report contains any information

l

that you or your contractors believe to be exempt from disclosure under

l

10 CFR 9.5(a)(4), it is necessary that you (a) notify this office by

telephone within seven (7) days from the date of this letter of your

i

'

intention to file a request for withholding; and (b) submit within

twenty-five (25) days from the date of this letter a written applica-

I

tion to this office to withhold such information. Section 2.790(b)(1)

I

requires that any such application must be accompanied by an affidavit

executed by the owner of the information which identifies the document

8106020/6(a

p

t

,

Commonwealth Edison Company

-2-

buX 1 9 S B1

_

or part sought to be withheld, and which contains a full statement of

the reasons on the basis which it is claimed that the information

should be withheld from public disclosure. This section further re-

quires the statement to address with specificity the considerations

listed in 10 CFR 2.790(b)(4). The information sought to be withheld

shall be incorporated as far as possible into a separate part of the

affidavit.

If we do not hear from you in this regard within the

specified periods noted above, a copy of this letter and the enclosed

inspection report will be placed in the Public Document Room.

We will gladly discuss any questions you have concerning this

inspection.

Sincerely,

. E.

oreli s, Acting Director

Division of Engineering and Technical

Inspection

Enclosure:

IE Inspection

Report No. 50-373/81-18

cc w/ encl:

J. S. Abel, Director

of Nuclear Licensing

L. J. Burke, Site

Construction Superintendent

T. E. Quaka, Quality

Assurance Supervisor

R. H. Holyoak, Station

Superintendent

B. B. Stephenson

Project Manager

Central Files

Reproduction Unit NRC 20b

AEOD

Resident Inspector, RIII

PDR

Local PDR

NSIC

TIC

Mary Jo Murray, Office of

Assistant Attorney General