ML19351G001

From kanterella
Jump to navigation Jump to search
Forwards IE Insp Repts 50-518/80-25 & 50-520/80-25 on 801112-14.No Noncompliance Noted
ML19351G001
Person / Time
Site: Hartsville  Tennessee Valley Authority icon.png
Issue date: 12/30/1980
From: Murphy C
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: Parris H
TENNESSEE VALLEY AUTHORITY
Shared Package
ML19351G002 List:
References
NUDOCS 8102200756
Download: ML19351G001 (2)


See also: IR 05000518/1980025

Text

-

-

- =- - - -

.

J

/ JC1.

s ua

A

o

UNITED STATES

g

NUCLEAR REGULATORY COMMISSION

y '; ) ,

g

c

REGION 11

.k'W

\\ D[e[

L1 i -

101 MARIETTA ST., N.W., SulTE 3100

o,

ATLANTA, GEORCI A 30303

OEC 0 ' 19;?

In Reply Refer To:

c0

RII:hL

__

g

0-5'18/80-25 )

p

<-*

-

0-520/80-J5 /

g

Tennessee Valley Authority

-

C o/8g7

ATTN:

H. G. Parris

%

-b

^-

'

Manager of Power

~

,

  • ~

500A Chestnut Street Tower II

'O

l

Chattanooga, TN 37401

9

,\\

(\\

Gentlemen:

4

ro

This refers to the inspection conducted by Nick Economos of this office on

l

November 12-14, 1980 of activities authorized by NRC Construction Permit Nos.

'

CPPR-150 and CPPR-152 for the Hartsville facility, and to the discussion of our

findings held with R. T. Hathcote at the conclusion of the inspection.

Areas examined during the inspection and our findings are discussed in the

enclosed inspection report.

Within these areas, the inspection consisted of

selective examinations of procedures and representative records, interviews with

personnel, and observations by the inspector.

Within the scope of this inspection, no items of noncompliance were disclosed.

In accordance with Section 2.790 of the NRC's " Rules of Practice", Part 2,

Title 10, Code of Federal Regulations, a copy of this letter and the enclosed

inspection report will be placed in the NRC's Public Document Room.

If_this

,

report contains any information thet you (or your contractor) believe to be

I

proprietary, it is necessary that you make a written application within 20 days

to this office to withhold such information from public disclosure.

Any such

'

application must include a full statement of th

reasons on the basis of which

l

it is claimed that the

nformation is proprietary, and should be prepared so

that proprietary information identified in the application is contained in a

l

separate part of the document. If we do not hear from you in this regard within

l

the specified period, the report will be placed in the Public Document Room.

Should you have any questions concerning this letter, we will be glad to discuss

them with you.

i

l

l

l

Sincerely,

.

  • 154

-

Charles E. Murphy, Chief

Reactor Construction & Engineering

Support Branch

t

!

.

l

Enclosure:

(See page 2)

t

)

[

.-

. .

.

_. _ ._.,

--

4

.

w

Tennessee Valley Authority

-2-

OL; e

15c

Enclosure:

Inspection Report Nos.

50-518/80-25, 50-520/80-25

cc w/ enc 1:

R. T. Hathcote, Project Manager

J. F. Cox, Supervisor, Nuclear

Licensing Section

J. E. Wills, Project Engineer