ML19351F201
| ML19351F201 | |
| Person / Time | |
|---|---|
| Site: | Comanche Peak |
| Issue date: | 10/16/1980 |
| From: | Seidle W NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV) |
| To: | Gary R TEXAS UTILITIES ELECTRIC CO. (TU ELECTRIC) |
| Shared Package | |
| ML19351F202 | List: |
| References | |
| NUDOCS 8101100247 | |
| Download: ML19351F201 (2) | |
See also: IR 05000445/1980023
Text
1
'
~
7LC
i
J
%,
UNITED STATES
4
[,)
NUCLEAR REGULATORY COMMISSION
" j;
/ l
REGION IV
.
[
811 RYAN PLAZA DRIVE, SUITE 1000
,,,
,, ,,a
ARLINGTON, TEXAS 79011
October 16, 1980
.
In Reply Refer To:
1
O
RIV
Docket No. 50-445/80-23
$
,:
50-446/80-23
7e
.
,
w
-
Nh
0:
1
o
0
UI
"
d
F3
~.9
Texas Utilities Generating Company
O
w
g
ATTN: Mr. R. J. Gary, Executive Vice
^
-
President and General Manager
2001 Bryan Tower
Dallas, Texas
75201
Gentlemen:
This refers to the inspection conducted by our Resident Reactor Inspector,
Mr. R. G. Taylor, of activities authorized by NRC Construction Permit No.
CPPR-126 for the Comanche Peak Steam Electric Station, Unit No. 1, and to
the discussion of our findings by the inspector with members of your staff
on October 9, 1980.
During the inspection, it was found that certain activities under your license
appear to be in noncompliance with Part 50, Title 10, of the Code of Federal
Regulations. The item of noncompliance and references to the pertinent
requirements are identified in the enclosed Notice of Violation.
Details of
this item will be included in an inspection report to be issued in the near
future and identified as Inspection Report No. 50-445/80-23; 50-446/80-23.
This notice is sent to you pursuant to the provisions of Section 2.201 of the
NRC's " Rules of Practice," Part 2, Title 10, Code of Federal Regulations.
Section 2.201 requires you to submit to this office, within 30 days of your
receipt of this notice, a written statement or explanation in reply including:
(1) corrective steps which have been taken by you, and the results achieved;
(2) corrective steps which will be taken to avoid further noncompliance; and
(3) the date when full compliance will be achieved.
Should you have any questions concerning this inspection, we will be pleased
to discuss them with you.
Sincerely,
b
^
- -
W. C. Seidle, Chief
Reactor Construction and
Engineering Support Branch
,
6101100,87
Q
4
.
,
Texas Utilities Generating
Company
-2-
October 16, 1980
Enclosure:
Appendix A, Notice of Violation
cc: w/ enclosure
Texas Utilities Generating Company
ATTN: Mr. H. C. Schmidt, Project Manager
2001 Bryan Tower
Dallas, Texas 75201