Forwards FSAR Prepared by Inel for Acceptance Review. Completion Date Tentatively Scheduled for 801101.W/o Encl
ML19351D368
Person / Time
Site: Perry  FirstEnergy icon.png
Issue date: 09/25/1980
From: Houston M
Office of Nuclear Reactor Regulation
To: Lyon R
EG&G IDAHO, INC., EG&G, INC.
References
EV-141, NUDOCS 8010100035
Download: ML19351D368 (1)


Text

-~

[f (o,

UNITED STATES CS.23

+

'(( h NUCLEAR REGULATORY COMMISSION g*

g.

E WASHINGTON, D. C. 20555 k

O o

SEP 25 pggo Mr. R. E. Lyon Reliability and Statistics Division EGEG Idaho, Inc.

P. O. Box 1625 Idaho Falls, Idaho 83415

Dear Mr. Lyon:

In accordance with the INEL technical assistance program (FIN A 6422) with the Division of Licensing (NRR), we are forwarding three copies of the Perry Nuclear Power Plant, Units 1 and 2 FSAR to you for the acceptance review. The tentative scheduled completion date for this review is November 1,1980.

If you have any questions concerning this matter, please contact me at FTS 492-8507.

Sincerely, 9 7). o d 4 s %So%'

M. Dean Houston, Project Manager Licensing Branch No. 2 Division of Licensing cc: Mr. C. E. Williams, Manager U. S. Department of-Energy Idaho Operations Office 550 Second Street Idaho Falls, Idaho 83401 Mr. C. F. Obenchain EG&G Idaho, Inc.

P. O. Box 1625 Idaho Falls, Idaho 83415 8010100 03 6 N

.