ML19351C742

From kanterella
Jump to navigation Jump to search
Ile ES-201-1
ML19351C742
Person / Time
Site: Byron  
Issue date: 01/29/2019
From: Chuck Zoia
Exelon Generation Co
To:
NRC/RGN-III/DRS/OLB
Shared Package
ML17164A344 List:
References
Download: ML19351C742 (2)


Text

ES-201 Facility:

Date of Examination:

Developed:

Written:

Facility:

NRC:

// Operating: Facility:

NRC:

Days from Exam Target Date*

Chief Examiner's Initials

-240 05/12/2018 CDZ

-210 06/11/2018 CDZ

-210 06/11/2018 CDZ

-210 06/11/2018 CDZ

-210 06/11/2018 CDZ

-195 06/26/2018 CDZ

-150 08/10/2018 CDZ

-136 08/24/2018 CDZ

-75 10/26/2018 CDZ

-75 10/26/2018 N/A

-60 11/08/2018 CDZ

-50 11/18/2018 CDZ

-35 12/03/2018 CDZ

-35 12/10/2018 CDZ

-30 12/08/2018 CDZ

-14 12/24/2018 CDZ

-7 12/31/2018 CDZ

-7 12/31/2018 CDZ

-7 12/31/2018 CDZ

-7 12/31/2018 CDZ

-7 12/31/2018 CDZ

17. Request facility licensee management feedback on the examination (C.2.l).
18. Final applications reviewed; one or two (if more than 10) applications audited to confirm qualifications/eligibility; and examination approval and waiver/excusal letters sent (C.2.k; Attachment 5; ES-202, C.3.j; ES-204).
19. Proctoring/written exam administration guidelines reviewed with facility licensee (C.3.k).
20. Approved scenarios and job performance measures distributed to NRC examiners (C.3.i).
12. Written exam and operating test reviews completed (C.3.f).

13b. The NRC and the facility licensee conduct exam preparatory week.

14. Preliminary license applications and waiver/excusal requests, as applicable (NRC Form 398) due (C.1.m; C.2.i; ES-202).
15. Final license applications and waiver/excusal requests, as applicable (NRC Form 398), due and Form ES-201-4 prepared (C.1.m; C.2.k; ES-202).
16. Written examinations and operating tests approved by the NRC supervisor (C.2.j-k; C.3.h).

13a. Examination review results discussed between the NRC and facility licensee (C.1.i; C.1.k-l; C.2.h; C.3.g).

7. Operating test outline(s) and other checklists due, including Forms ES-201-2, ES-201-3, ES-301-1, ES-301-2, ES-301-5, and ES-D-1, as applicable (C.1.e-f; C.3.d-e).
8. Operating test outline(s) reviewed by the NRC and feedback provided to facility licensee (C.2.h; C.3.d-e).
9. Proposed examinations (written, JPMs, and scenarios, as applicable) and outlines (Forms ES-301-1, ES-301-2, ES-D-1, ES-401-1/2 or ES-401N-1/2, and ES-401-3 or ES-401N-3); supporting documentation (including Forms ES-301-3, ES-301-4, ES-301-5, ES-301-6, ES-401-6, ES-401N-6, and any Form ES-201-2 and ES-201-3 updates); and reference materials due (C.1.e-h; C.3.d).
10. Examinations prepared by the NRC are approved by the NRC supervisor and forwarded for facility licensee review (C.1.i; C.2.h; C.3.f-g).
11. Preliminary waiver/excusal requests due (C.1.m; C.2.c; ES-202).

Task Description (Reference)

1. Examination administration date confirmed (C.1.a; C.2.a-b). For NRC-prepared exams, arrangements are made for the facility to submit reference materials (C.1.e; C.3.c; Attachment 3).

Form ES-201-1 BYRON NUCLEAR GENERATING STATION Examination Preparation Checklist January 7 - January 25, 2019

2. NRC examiners and facility contact assigned (C.1.d; C.2.f).
3. Facility contact briefed on security and other requirements (C.2.c). As applicable, the facility contact submits to the NRC any prescreened K/As for elimination from the written examination outline, with a description of the facilitys prescreening process (ES-401, D.1.b).
4. Reference material due for NRC-prepared exams (C.1.e; C.3.c; Attachment 3).
5. Corporate notification letter sent (C.2.e).
6. NRC-developed written examination outline (ES-401-1/2 or ES-401N-1/2 and ES-401-3 or ES-401N-3) sent to facility contact (must be on the exam security agreement) (C.1.e-f; C.2.h; C.3.d-e).

Exam Date:

01/07/2019

  • Target dates are based on facility prepared examinations and the examination date identified in the corporate notification letter. These dates are for planning purposes and may be adjusted on a case by case basis in coordination with the facility licensee.