Forwards IE Safety Insp Rept 50-328/81-20 on 810428-0501 & 0505-08.No Noncompliance Noted
ML19350E762
Person / Time
Site: Sequoyah Tennessee Valley Authority icon.png
Issue date: 06/04/1981
From: Robert Lewis
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: Parris H
TENNESSEE VALLEY AUTHORITY
Shared Package
ML19350E763 List:
References
NUDOCS 8106230502
Download: ML19350E762 (2)


See also: IR 05000328/1981020

Text

_ - _ _ _ _ _

W

-.

. . .

'

,

%-

"%c

'

. . ' "

NUCLEAR REGULATORY COMMISSION

o

2

i

REGION 11

"

8

101 MARIETTA ST., N.W.. SulTE 3100

ATLANTA. GEORGIA 30303

.....

M 0 4 1981

o>

e

Tennessee Valley Authority

9

ATTN: Mr. H. G. Parris

JUN ~o o N "

-

Manager of Power

c

~

7

500A Chestnut Street Tower II

'

y,,'EIuD 12

Chattanooga, TN 37401

'G

,

Gentlemen:

e

y

Subject: Report No. 50-328/81-20

This refers to the routine safety inspection conducted by Mr. M. D. Hunt of this

office on April 28 - May 1, 1981 and May 5-8, 1981, of activities authorized bv

NRC Construction Permit No. CPPR-73 for the Sequoyah Nuclear Plant facility ano

to the discussion of our findings held with Mr. J. M. McGriff, Assistant Plant

Superintendent, at the conclusion of the inspection.

Areas examined during the inspection and our findings are discussed'in the

enclosed inspection report.

Within these areas, the inspection consisted of

selective examinations of procedures and representative records, interviews with

personnel, and observations by the inspectors.

Within the scope of this inspection, no violations or deviations were disclosed.

We have examined actions you have taken with regard to previously identified

enforcement matters and unresolved items. The status of these items is discussed

in the enclosed report.

Two new unresolved items resulted from this inspection and are discussed in the

enclosed report. These items will be examined during subsequent inspections.

In accordance with 10 CFR 2.790 of the Commission's regulations, a copy of this

letter and the enclosed report will be placed in the NRC's Public Document Room.

If the report contains any information that you believe to be exempt from disclo-

sure under 10 CFR 9.5(a)(4), it is necessary that you: (a) notify this office by

telephone within ten days from the date of this letter of your intention to file

a request for withholding; and (b) submit within twenty-five days from the date

of this letter a written application to this office to withhold such information.

If your receipt of this letter has been delayed such that less than seven days

are available for your review, please notify this office promptly so that a new

due date may be established. Consistent with section 2.790(b)(1), such applica-

tion must be acccmpanied by an affidavit executed by the owner of the information

which identifies the document or part thereof sought to.be withheld, and a full

statement of the reasons on the basis of which it is cl.imed that the information

should be withheld from public disclosure.

This section further requires tM

statement to address with specificity the considerations listed in 10 CFR 8106230602.

.

.

_

]

'

,

"O

.

  • .

..

. o,

.-Tennessee Valley Authority

2'

,

'2.790(b)(4). The information sought to be withheld shall be incorporated as far

as possible into a separate part of the affidavit. If we do not hear from you in

.this' regard within the'specified.perieds noted above, the report will be placed

in the Public Document Room.

Sho'ald you have'any questions concerning this letter, we will be glad to discuss

them with you.

Sincerely,

l

.t7.

I

.C.

wis, Acting Director

Division of Resident and

4

Reactor Project Inspection

Enclosure:

Inspection Report No. 50-328/81-20

cc w/ancl:

H. J. Green, Division Director

G. G. Stack, Project Manager -

J. M. Ballentine, Plant

,

Superintendent

J. F. Cox, Supervisor, Nuclear

Licensing Section

M. J. Burlynski, Project Engineer

H. N. Culver, Chief, Nuclear Safety

Review Staff

1

s

j

I

-

. . ,

, . .

-+c-

- - - - -

.ee-