Interim Deficiency Rept Re Potential Morrison-Knudsen Structural Steel Problem,Initially Reported on 810128. Malpractice & Structural Steel Insp Documentation Problems Combined Into One Evaluation.Final Rept by 810815
ML19350E277
Person / Time
Site: Satsop
Issue date: 05/07/1981
From: Leddick R
WASHINGTON PUBLIC POWER SUPPLY SYSTEM
To: Faulkenberry B
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
References
10CFR-050.55E, 10CFR-50.55E, GO3-81-1027, NUDOCS 8106170232
Download: ML19350E277 (3)


Text

. g .. . ', .

N IP Washington Public Power Supply System

], A JOINT CPERATING AGENCY

(

P. O. BOE 1223 (LM A. W ASHINCTON 98541 HOkt(2061249-5001 jf..I , 39 ,

A ta y-

.,l' -

ld-f. ?

May 7,1981 G03-81-1027

,,-@ [

Nuclear Regulatory Commission, Region V Suite 202, Walnut Creek Plaza 1990 North California Boulevard <'

I9

/

Walnut Creek, California 94595 x,'f ' g$ 3 Attention: Mr. B. H. Faulkenberry bk D$

Chief, Reactor Construction 7 h c[r$5 .N k Projects Branch 9

, c' d:

Gentlemen: ",, i

., x  ;%

Subject:

PROJECT N05. 3 AND 5 b.,,&w a--

INTERIM REFORT OF 10CFR50.55(e) CONDITION

References:

1) Supply System Record of Telephora Conversation, J. C. Lockhart to G. S. Spencer, Potential 50.55(e)

Morrison-Knudsen Structural Steel Problem, dated January 28, 1981.

2) G03-81 -503, letter, D. E. Dobson to R. H. Faulkenberry, same subject, dated February 19, 1981.

Reference 2 stated we would submit a final report by May 1,1981. As we are unable to provide that final report, the following is a status of actions taken.

We have combined the malpractice and structural steel inspection docu-mentation problems into one for evaluation as 10CFR50.55(e).

All of the corrective actions required by the Contractors Corrective Action Request have not been completed. These actions are anticipated to be complete by June 15, 1981.

O V 0 d

810617oa y es -ss.

~

Mr. B. H. Faulkenberry Page 2 The corrective actions for Unit 5 ': ave been completed and the discrep-ancies documented on NCR's 5500 through 5505. Upon completion of the actions required for Unit 3, all applicable NCR's will be submitted to Ebasco for evaluation for significance. Our current estimate for completing the required engineering analysis and evaluation of the sub-ject condition is 60 days. We expect to submit our final report on this matter to your office no later than August 15, 1981 Very truly yours, I

~ R..S. Leddick t

ELS:tp Program Director, WNP-3/5 cc: D. Smithpeter - BPA Ebasco - Elma WNP-3/5 Filed - Richland 4

0 .

4 i

-, -- , --,.,-.--,.,-7.-+.,-----e-, -

,- =, -- y.. , - - -v-, .mr.. n,-.<. -m-+-- -,-.-- m.

. - y - . --- -

.m

R. S. LEDDICK, Being first duly sworn, deposes and says: That he is the Program Director, WNP-3/5, for the WASHINGTON PUBLIC POWER SUPPLY SYSTEM, the applicant herein; that he is authorized to submit the fore-going on behalf of said applicant; that he has read the for. going and knows the contents thereof; and believes the same to be true to the best of his knowledge.

DATED h I!)t , 1981.

d / .

R.'S. LEDDICK STATE OF WA.HIrlGTON )

) ss COUtlTY OF GRAYS HARBOR )

On this day personally appeared before me R. S. LEDDICK to me 'nown to-be theindividual who executed the foregoing inst'rument and acknowledged that he signed the same as his free act and deed for the uses and purposes therein mentioned.

GIVEN under my hand and seal this day of K44Ar , 1981.