Forwards IE Insp Repts 50-352/81-01 & 50-353/81-01 on 810105-30 & Notice of Violation
ML19350D138
Person / Time
Site: Limerick  Constellation icon.png
Issue date: 02/27/1981
From: Robert Carlson
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Kemper J
PECO ENERGY CO., (FORMERLY PHILADELPHIA ELECTRIC
Shared Package
ML19350D135 List:
References
NUDOCS 8104130512
Download: ML19350D138 (2)


See also: IR 05000352/1981001

Text

,

.

.

UNITED STATES

t

[

o

NUCLEAR REGULATORY COMMisslON

y ,7,

'

nEcion i

lj

[ j

$31 PAFK AVENUE

KING OF PRUSSI A. PENNSYLVANIA 19406

'.....

FEB 2 7 793g

Docket Nos. 50-352

50-353

'

Philadelphia Electric Company

. ATTN: Mr. John S. Kemper

Vice President

Engineering and Research

2301 Market Street

Philadelphia, Pennsylvania

19101

Gentlemen:

Subject: Combined Inspection 50-352/81-01; 50-353/81-01

This refers to the routine safety inspection conducted by Mr. J. P. Durr of this

office on January 5-30, 1981 at the Limerick Generating Station, Unit Nos. I and

2, at Limerick, Pennsylvania and the PhiladelpFia Electric Company's Corporate

Office of activities authorized by NRC License Nos. CPPR-106 and CPPR-107 and to

the discussions of our findings held by Mr. Durr with R. C. Mulford and J. M.

Corcoran of your staff at the conclus_ ion of the inspection.

Areas examined during this inspection are described in the Office of Inspection

and Enforcement Inspection Report which is enclosed with this letter.

Within

these areas, the inspection consisted of selective examinations of procedures

and representative records, interviews with personnel, measurements made by the

inspector, and observations by the inspector.

Based on the results of this inspection, it appears that certain of your activities

were not conducted in full compliance with NRC requirements, as set forth in the

Notice of Violation, enclosed herewith as Appendix A.

These items of noncompliance

have been categorized into the levels described in the Federal Register Notice

(45 FR 66754) dated October 7, 1980.

You are required to respond to this letter

and in preparing your response, you should follow the instructions in Appendix

A.

In accordance with Section 2.790 of the NRC's " Rules of Practice," Part 2, Title

10, Code of Federal Regulations, a copy of this letter and the enclosures will

be placed in the NRC's Public Document Room.

If this report contains any information

that you (or your contractor) believe to be proprietary, it is necessary that

you make a written application within 25 days to this office to withhold such

infomation from public disclosure. Any such application must be accompanied by

an affidavit executed by the owner of the information, which identifies the

document or part sought to be withheld, and which contains a statement of reasons

which addresses with specificity the items which will be considered by the

E104180[jg

--

- - - -

.

-

-_

.

.

,Phil5delphiaElectricCompany

2

.

Commission as listed in subparagraph (b) (4) of Section 2.790.

The information

sought to be withheld shall be incorporated as far as possible into a separate

part of the affidavit.

If we do not hear from you in this regard within the

specified period, the report will be placed in the Public Document Room.

Should you have any questions concerning this inspection, we will be pleased

to discuss them with you.

Sincerely,

f

b^

Robert T. Carlson, Chief

Reactor Construction and Engineering

Support Branch

Enclosures:

1.

Office of Inspection and Enforcement Combined Inspection

Report Number 50-352/81-01; 50-353/81-01

2.

Appendix A, Notice of Violation

cc w/encis:

V. S. Boyer, Senior Vice President, Nuclear Power