ML19350D138
| ML19350D138 | |
| Person / Time | |
|---|---|
| Site: | Limerick |
| Issue date: | 02/27/1981 |
| From: | Robert Carlson NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I) |
| To: | Kemper J PECO ENERGY CO., (FORMERLY PHILADELPHIA ELECTRIC |
| Shared Package | |
| ML19350D135 | List: |
| References | |
| NUDOCS 8104130512 | |
| Download: ML19350D138 (2) | |
See also: IR 05000352/1981001
Text
,
.
.
UNITED STATES
t
[
o
NUCLEAR REGULATORY COMMisslON
y ,7,
'
nEcion i
lj
[ j
$31 PAFK AVENUE
KING OF PRUSSI A. PENNSYLVANIA 19406
'.....
FEB 2 7 793g
Docket Nos. 50-352
50-353
'
Philadelphia Electric Company
. ATTN: Mr. John S. Kemper
Vice President
Engineering and Research
2301 Market Street
Philadelphia, Pennsylvania
19101
Gentlemen:
Subject: Combined Inspection 50-352/81-01; 50-353/81-01
This refers to the routine safety inspection conducted by Mr. J. P. Durr of this
office on January 5-30, 1981 at the Limerick Generating Station, Unit Nos. I and
2, at Limerick, Pennsylvania and the PhiladelpFia Electric Company's Corporate
Office of activities authorized by NRC License Nos. CPPR-106 and CPPR-107 and to
the discussions of our findings held by Mr. Durr with R. C. Mulford and J. M.
Corcoran of your staff at the conclus_ ion of the inspection.
Areas examined during this inspection are described in the Office of Inspection
and Enforcement Inspection Report which is enclosed with this letter.
Within
these areas, the inspection consisted of selective examinations of procedures
and representative records, interviews with personnel, measurements made by the
inspector, and observations by the inspector.
Based on the results of this inspection, it appears that certain of your activities
were not conducted in full compliance with NRC requirements, as set forth in the
Notice of Violation, enclosed herewith as Appendix A.
These items of noncompliance
have been categorized into the levels described in the Federal Register Notice
(45 FR 66754) dated October 7, 1980.
You are required to respond to this letter
and in preparing your response, you should follow the instructions in Appendix
A.
In accordance with Section 2.790 of the NRC's " Rules of Practice," Part 2, Title
10, Code of Federal Regulations, a copy of this letter and the enclosures will
be placed in the NRC's Public Document Room.
If this report contains any information
that you (or your contractor) believe to be proprietary, it is necessary that
you make a written application within 25 days to this office to withhold such
infomation from public disclosure. Any such application must be accompanied by
an affidavit executed by the owner of the information, which identifies the
document or part sought to be withheld, and which contains a statement of reasons
which addresses with specificity the items which will be considered by the
E104180[jg
--
- - - -
.
-
-_
.
.
,Phil5delphiaElectricCompany
2
.
Commission as listed in subparagraph (b) (4) of Section 2.790.
The information
sought to be withheld shall be incorporated as far as possible into a separate
part of the affidavit.
If we do not hear from you in this regard within the
specified period, the report will be placed in the Public Document Room.
Should you have any questions concerning this inspection, we will be pleased
to discuss them with you.
Sincerely,
f
b^
Robert T. Carlson, Chief
Reactor Construction and Engineering
Support Branch
Enclosures:
1.
Office of Inspection and Enforcement Combined Inspection
Report Number 50-352/81-01; 50-353/81-01
2.
Appendix A, Notice of Violation
cc w/encis:
V. S. Boyer, Senior Vice President, Nuclear Power