Forwards IE Insp Repts 50-282/81-01 & 50-306/81-01 on 810105-08 & Notice of Violation
ML19350C983
Person / Time
Site: Prairie Island  Xcel Energy icon.png
Issue date: 03/09/1981
From: Heishman R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Gilberts D
NORTHERN STATES POWER CO.
Shared Package
ML19350C984 List:
References
NUDOCS 8104130030
Download: ML19350C983 (2)


See also: IR 05000282/1981001

Text

o

UNITED STATES

8

NUCLEAR REGULATORY COMMISSION

o

8

L

.E

REGION lli

Y

799 ROOSEVELT ROAD

GLEN ELLYN, ILLINOIS So137

.....

March 9, 1981

"

c5

b

Docket No. 50-282

'l

Docket No, 50-306

P

_

N

/ A.

Northern States Power Company

~

k,\\

<! % ,

ATTN:

Mr. Dennis E. Gilberts

s

Vice President

.f

p

Power Production and

9

System Operation

4

=

414 Nicollet Mall

Minneapolis, MN 55401

Gentlemen:

This refers to the closeout inspection conducted by Messrs. I. N. Jackiw,

R. D. Schulz and J. A. Grobe of this office on January 5-8, 1981, of activities

at Praicie Island Nuclear Generating Plant, Units 1 and 2, authorized by NRC

Operating Licenses No. DPR 42 and No. DPR-60 and to the discussion of our

findings with Mr. F. P. Tierney at the conclusion of the inspection.

The enclosed copy of our inspection report identifies areas examined during

the inspection. Within these areas, the inspection consisted of a selective

examination of procedures and representative records, observations, and

interviews with personnel.

During this inspection, certain of your activities appeared to be in non-

compliance with NRC requirements, as described in the enclosed Appendix A,

and a written response is required. With regard to storage and handling

of material, we are concerned with the laxity of quality assurance controls

exhibited in this area.

Therefore, in addition to the response to item 3

of Appendix A, please describe the immediate actions you plan to take to

preclude the inadvertent use of unauthorized material and equipment.

In accordance with Section 2.790 of the NRC's " Rules of Practice," Part 2,

Title 10, Code of Federal Regulations, a copy of this letter, the enclosures,

and your response to this letter will be placed in the NRC's Public Document

Room, except as follows.

If the enclosures contain information that you or

your contractors believe to be proprietary, you must apply in writing to

this office, within twenty-five days of the date of this letter, to withhold

l

such information from public disclosure. The application must include a full

statement of the reasons for which the information is considered proprietary,

and should be prepared so that proprietary information identified in the

application is contained in an enclosure to the application.

l

Q

810413 0030

.

.

s

Northern States Power

-2

March 9, 1981

Company

We will gladly-discuss any questions you have concerning this

inspection.

Sincerely,

RFLO O

w

R. F. Heishman, Chief

Reactor Operations and

Nuclear Support Branch

Enclosures:

1.

Appendix A, Notice

of Violation

2.

IE Inspection Reports

No. 50-282/81-01 and

No. 50-306/81-01

cc w/encls:

F. P. Tierney, Jr.,

Plant Manager