Notice of Violation from Insp on 810319,25 & 26
ML19347F716
Person / Time
Site: Byron  Constellation icon.png
Issue date: 04/13/1981
From: Norelius C
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML19347F713 List:
References
50-454-81-03, 50-454-81-3, 50-455-81-03, 50-455-81-3, NUDOCS 8105260104
Download: ML19347F716 (1)


Text

- _ _

t Appendix A ~

NOTICE OF VIOLATION Commonwealth Edison Company-Docket No. 50-154 Docket No. 50-455 i

As a result.of the inspection conducted on March 19, 25 and 26, 1981, and-

'in'accordance with Interim Enforcement Policy 45 FR 66754 (October 7, 1980),

the following violation was identified:

10 CFR 50, Appendix.B. Criterion IX, states.in part that, " Measures shall.

r be established to assure that special processes including....... and non-destructive testing', are controlled........using qualified procedures in accordance with applicable codes, standards....... and other special requirements."

~

i ASME Code Section V, 1974 Edition,' Summer 1975 Addenda, which is the applic--

able Code Feverning radiography for the Byron Station primary coolant system states in paragraph T-262.3(b) "If more than one penetrameter is used, one shall be in the lightest area.of the radiograph and the other.in the darkest.

Paragraph T-262.4 states "If the weld reinforcement' and/or backing strip are not removed, a shim of material radiographically similar to the weld metal shall be placed under the penetrameter." Pittsburgh Testing Laboratory (PTL)'-

procedure QC-RT-1 governs this work, was approved by the -licensee, and reads exactly as the Code.

Contrary to the above requirements, the weld reinforcement had not been removed on Weld No. FW-45 in spool piece IH-CAE-4 and the radiographic:

I film did not indicate a shim was used under either of the two penetrameters i-shown.

,This is Severity Level V violation (Supplement II).

I Pursuant to the provisions of 10 CFR 2.201, you are required.to submit to this office within twenty-five days of the date of this Notice a written statement or explanation in reply, incitding for each item of noncompliance:

[

(1) corrective action taken and the results achieved; (2) corrective action to be taken to avoid further noncompliance; and (3) the date when full com-pliance will be achieved. Under the-authority of Section 182 of the Ataic Energy Act of 1954, as amended, this response shall be submitted under oath-or affirmation.

1 Dated I3[D d.*f,.Mo M i

'C. E. Norelius, Acting Director l

Division of Engineering and l

Technice". Inspection 8105260/0Y i