Responds to Re Request for Relief from CP Item 3.E.7 Which Requires Nonradiological Environ Monitoring of Aquatic & Terrestrial Ecology.Request Granted Conditional Upon Commitment to Continue Preoperational Monitoring
ML19347E975
Person / Time
Site: Callaway  
Issue date: 05/12/1981
From: Tedesco R
Office of Nuclear Reactor Regulation
To: Bryan J
UNION ELECTRIC CO.
References
NUDOCS 8105140449
Download: ML19347E975 (3)


Text

O

.f s'o, UNITED STATES

'i.

NUCLEAR REGULATORY COMMISSION

,, (

g-WASHINGTON. D. C. 20555 gv,/

4

++.

  • MAY 121981 Docket Nos.:

STN 50-483 and STN 50-486 O

2s 4

Mr. John K. Bryan Vice President Db dy-Union Electric Company Ig l T.

j b o.5 Yg' 1901 Gratiot Street 9

E P. O. Box 149 St. Louis, Misouri 63166 48

Dear Mr. Bryan:

Subject:

Temination of Non-Radiological Environmental Monitoring Required in the Construction Permit for Callaway Nuclear Plant In your letter dated April 22,1981 (J. K. Bryan to H. R. Denton), you requested relief froci Construction Permit item 3.E.(7) that requires non-radiological environmental monitoring of aquatic and terrestrial ecology of the Callaway 5,ite vicinity.

You request relief on the following bases:

(1) project construction-related impacts already have occurred and have not been adverse; (2) the volume of data colle:ted thus far (through 1980) is comprehensive and sufficient to characterize the aquatic and terrestrial ecology; (3) preoperational studies of river fish populations will continue under the NPDES permit, and operational monitorine will include fish impingement and entrainment; (4) operation of Callaway vill have minimal environmental impact.

We have r xamined the request and data and find that termination of the Construr tion Permit-required studies is acceptable. During the November 1980 site v' sit, NRC and ANL staff members inspected the on-site construction areas, the ar eas disturbed at the river bank (intake and discharge), and the Logan Creel crossings (pipelines and bridges). Construction-related impacts appear to have been minimal. The Creek banks appeared to be stable, vegetated, and witn few indications of erosion. Reports on these activities were submitteo to NRC in 1975 and 1976, with additional data included in the Environmental Report-Operating License (ER-OL) stage.

The data collected and submitted to NRC are adequate to characterize the ecology and to perform the present Operating Licenst.-Environmental Impact Statement (0L-EIS) review.

These data include: pre-operational monitoring through 1980; the ER-OL stage; Revision to the ER-OL (submitted on February 6, 1981); and three submittals (of February 6, March 10, March 31,1981) in response to NRC requests for additional information.

8 1 0g;1 4 g

l l

Mr. John X. Bryan 14AY 121981 L

The acceptability of your request also is based on your commitment to continue. pre-operational monitoring of fishes and ichthyoplankton in both the Missouri River and Logan Creek under the State NPDES permit. You further stated (in your February 6,1981 response) that this monitoring will clarify the significance of Mollie Dozier Chute (in the river) for fishes by sampling in and near the Chute. These commitments under the NPDES and the Permit requirements for operational monitoring of entrainment and impingement will provide a continuing data base for impact assessment.

It should be noted that the need for further terrestrial monitoring during station operation is being reviewed in the OL-EIS preparation now under way.

Sincerely, E " A' Robert L. Tedesco, Assistant Director for Licensing Division of Licensing cc: See next page I

~ ~.

Mr. - J. K. Bryan Vice President - Nuclear Union Electric Company P. O. Box 149 St. Louis, Missouri '63166 cc: Mr. Nicholas A. Petrick Mr. William'Hansen Executive Director - SNUPPS Resident Inspector /Callaway NPS 5 Choke Cherry Road c/o USNRC Rockville, Maryland 20850 Steedman, Missouri 65077 Gerald Charnoff, Esq.

Shaw, Pittman, Potts &

Trowbridge 1800 M Street, N. W.

Washington, D. C.

20036 Mr. J. E. Birk Assistant to the General Counsel Union Electric Company P. O. Box 149 St. Louis, Missouri 63166 Dr. Vern Starks Route 1, Box 863 Ketchikan, Alaska 99901

=

Ms. TrevaHearn, Assistant General Counsel Missouri Public Service Connission P. O. Box 360 Jefferson City, Missouri 65102 Mr. 3. F. Schnell Manager-Nuclear Engineering Union Electric Company P. O. Box 149 St. Louis, Missouri 63166 l

[

-