Responds to NRC Re Noncompliance in Submitting Emergency Plan.Plan Was Forwarded on 810402.Delay Attributed to Refueling Outage & ASLB Hearings on Site Liquefaction. Implementing Procedures Submitted by 810501
ML19345G722
Person / Time
Site: La Crosse File:Dairyland Power Cooperative icon.png
Issue date: 04/06/1981
From: Linder F
DAIRYLAND POWER COOPERATIVE
To: James Keppler
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
Shared Package
ML19345G721 List:
References
LAC-7455, NUDOCS 8104220166
Download: ML19345G722 (2)


Text

o*p-?

\\

~

a=

i.,

i fD DA/RYLAND LJ h

/W COOPERAT/VE

  • PO box 817 2615 EAST AV SOUTH = LA CROSSE WISCONSIN 54601 (608) 788-4000 April 6, 1981 In reply, please refer to LAC-7455

)

DOCKET NO. 50-409 Mr. James G.

Keppler, Director p

q gg,g, U.

S. Nuclear Regulatory Commission Sg DI' Directorate of Regulatory Operations Region III 3/D bAO '

799 Roosevelt Road U

0 Glen Ellyn, IL 60137 p/5R&PLJbb/

SUBJECT:

DAIRYIAND POWER COOPERATIVE l

gg_7 LA CROSSE BOILING WATER REACTOR (LACBWR)

PROVISIONAL OPERATING LICENSE NO. DPR-45 /hsYf File EMERGENCY PLAN

Reference:

(1) NRC Letter, Keppler to Lin$er dated March 12, 1981 (2) DPC Letter, Linder to risenhut LAC-7446, dated April 2, 1981

Dear Mr. Keppler:

Your letter (Reference 1) informed us of an apparent non-compliance of our activities with regard to 10 CFR 50.54 (u).

This letter con-stitutes the written statement with regard to your " Notice of Violation" contained in Appendix A to Reference 1.

Enforcement Item As a result of an attempted Emergency Plan Revieu conducted on March 2, 1981, and in accordance uith the interim Enforcement Policy 45 FR 66754 (October 7, lu80), the following violation uas identified:

10 CFR 50. 5 4 (u ) states:

"Within 60 days after the effective date of this amendment (November 3, 1980) each nuclear pouer reactor licensee shall submit to the NRC plans for coping uith emergencies that meet standards in 50.47(b) and the requirements of Appendix E of this part."

Contrary to the above, emergency plans due January 2, 1981, have not been submitted.

DPC Respo.1se Our letter (Reference 2) forwarded ten (10) copies of the upgraded radiological emergency response plan for LACBWR to the NRC Office of Nuclear Reactor Regulation.

It was emphasized in our letter 8104220 M g

g est

s' s.

Mr. James G. Keppler, Director LAC-7455 U.

S. Nuclear Regulatory Commission April 6, 1981 Directorate of Regulatory Operations page 2 that the reason for the delay was attributed to a refueling outage and ASLB hearings on site liquifaction.

The recent termination of the Health and Safety Supervisor was also a factor in the delay.

It should be noted that Revision 1 of NUREG-0654/ FEMA-REP-1 was forwarded to us on December 9, 1980.

Our letter (Reference 1) also discussed advisories which were sent to the NRC regarding our progress and further expressed our opinion that the current NRC-approved emergency plan and implementing pro-cedules for LACBWR provide appropriate protective measures in the event of a radiological emergency.

This plan was used for a joint State, local, county and plant drill on May 11, 1979.

We have estimated that full implementation of the upgraded plan,.( / [/.9##

and procedures cannot be accomplished prior to June 1,198L.

s Implementing procedures will be submitted by May 1, 1981.

If there are any questions concerning this response, please con-tact us.

Very truly yours, DAIRYLAND POWER COOPERATIVF

[

v Frank Linder, General Manager FL:RES:dh cc - NRC Resident Inspectors I