b c li" ""%,
UNITED STAV2S y.- _.,
NUCLEAR REGULATORY COMMISSION
$g
- E REGloN IV S,%
/
611 RYAN PLAZA oRIVE. SUITE 1000 ARLINGTON. TEXAS 76011 January 23, 1981 In Reply Refer To:
RIV Docket Nos. 50-458/IE Circular No. 81-01 v
50-459/IE Circular No. 81-01 g
Ir q/,s 0.[ J o 1,,.\\JN' q
2-FED 0 31981 * ;
Gulf States Utilities u 5 -s *** ^
Attn-Dr. E. Linn Draper, Jr.
9 Vice President - Technology
,E Post Office Fox 2951 4
\\
Beaumont, Texas 77704
^
g Gentlemen:
The enclosed IE Circular No. 81-01 contains recommendations that may be applicable to your facilities with regard to design problems associated with the subject indicating pushbutton switches. Should you have any questions regarding this circular or the recommendations contained therein, please contact this office.
Sincerely /,
~
, _ y,.
(
- r1 V. Seyfrit i
Director
Enclosures:
1.
IE Circular No. 81-01 2.
_ist of Recently issued IE Circulars i
82oneon p
-. - __ - ---~.-
4 I
i SSINS No.:
6830 Accession No.:
8008220280 UNITED STATES NUCLEAR REGULATORY COMMISSION OFFICE OF INSPECTION AND ENFORCEMENT WASHINGTON, D. C. 20555 1
l IE Circular No. 81-01 Date: Janua ry 23, 1981 Page 1 of 4 l
\\
DESIGN PROBLEMS INVOLVING INDICATING PUSHBUTTON I
SWITCHES MANUFACTURED BY HONEYWELL INCORPORATED
Background:
By letter dated September 18, 1980 (J. M. Curran to R. H. Engelken), Southern d
California Edison Company (SCE) notified NRC of design problems involving certain indicating pushbutton switches. The subject switches are of the type designated as Series 2 indicating pushbutton switches that are manufactured by the Micro Switch Division of Honeywell Incorporated. The switches identified by 5ct as having design deficiencies are used on the containment isolation panels at San Onofre Unit 1 (Docket No. 50-206).
SCE identified two problems with the subject switche both of which manifest themselves during relamring:
(1) a short circuit may be induced; and (2) the circuit controlled by the switch may inadvertently be actuated.
Although the specificity of this circular is restricted to the previously ment 1oned Series 2 switches the deficiencies cited may be common to other indicating pushbutton switches. Accordingly, holders of operating licenses and construction permits should scrutinize the design of other indicating pushbutton switches in their facilities for susceptiblity to the above problems.
By letter dated October 10, 1980 (J. G. Haynes to 2. H. Engelken), SCE submitted a detailed followup report addressing the defective switches. Sections of the SLE report containing relevant information have been excerpted and included in the paragraphs that follow. Sections so excerpted are identified by quotation marks.
Discursion:
The SCE report provided the following details of the problems previously mentioned:
2 "1.
The design of indicating pushbutton switches is such that during insertion of the lamp assembly into the switch housing, shorting could occur between the metallic plunger and.the energized indicator lamp connection inside the switch assembly. Since the metal plunger is connected to the cabinet ground through the switch housing, the control circuit could be short circuited, causing failure of the control circuit if it is anergized.
IEC No. 81-01 Janua ry 23, 1981 Page 2 of 4 "2.
The design of the lamp assembly is such that to lock the switch into place after relamping will cause actuation of the switch resulting in operation of the control circuit if it is energized. Since the current containment isolation system operational design requires that the power supply to the containment isolation panels remain energized during relamping, the potential exists for operating containment isolation valves during the lamp replacement."
To circumvent the preceding problems, SCE, in cooperation with Honeywell Incorporated, is implementing the following corrective actions.
"1.
The metallic plunger is being redesigned to solve the short circuit problem discussed in Item 1 above. The design modification involves providing a plastic tip on the plunger.
The plastic tip will provide isolation between the metallic plunger and energized indicator lamp connection inside the switch assembly and this will avoid short circuit problems. A prototype modified switch assembly was received on September 20, 1980 and successfully tested. Accordingly, the manufacturer is developing the necessary tooling for production purposes.
It is expected that the modified switch assemblies can be delivered and installed prior to return to power operation from the current outage.
"2.
The indicating pushbutton lamp assembly system is being redesigned to solve the switch actuation problem discussed in Item 2 above.
The design modification will permit relamping with the power supply energized, without causing switch actuation.
It is expected that the system will be redesigned and the current switches replaced during the next scheduled cold shutdown of sufficient duration following return to power operation from the current outage."
In addition, SCE has instructed its station personnel on procedural steps to be followed when changing lamps. The procedural steps currently in effect at San Onofre Unit 1 for relamping the indicating push button switches address the potential for shorting or for inadvertently actuating the control circuit as follows:
"1.
Containment Isolation Valves on Non-essential Systems All automatic containment isolation valves are included in this ca tego ry.
When replacement of a burned out lamp is necessary, the power supply of the circuit of the valve will be opened and the associated valve will close if open or will be de-energized in the closed position if already closed. The burned out lamp will be replaced and the power supply to the circuit will be closed permitting the valve to be reopened or re-energized in the closed position.
IEC No. 81-01 Janua ry 23, 1981 Page 3 of 4 "2.
Remote Manual Containmera Isolation Valves on Essential Systems The systems in this category include the Chemical Volume and Control Letdown System, Reactor Coolant Pump Seal Water Return System, Turbine Plant Cooling Water Supply and Return System, and Pressurizer Relief Tank hitrogen Supply System. The containment isolation valves on these systems are normally open during operation and may be required to be open during accident conditions.
"If it is necessary to replace burned out lamps after the metallic plunger has been redesigned as described in corrective action 1 above, the following steps will be taken:
"1.
The touch plate with the burned out lamp will be removed and lamps replaced.
"2.
The glass cover on the EFA relay (panels behind north vertical board) associated with the valve in question will be removed and the relay held in place by depressing the insulated portion of the spring loaded relay plunger.
"3.
The touch plate with the replaced lamps will be inserted into the switch chassis.
"4.
The 'open' switch of the valve in_ question will be depressed to assure that the circuit has been reset and the glass cover replaced on the HFA relay.
"If it is necessary to replace burned out lamps before the metallic plun-ger is redesigned, the replacement will be performed during an outage of sufficient duration when the affected system and valve can be removed from service. At that time, the procedural steps to be followed are identical to those established for the automatic containment isolation valves on non-essential systems discussed above. Until such time as the lamp can be re-placed, the position of the affected valve can be determined by examining the system flow, pressure and temperature process instrumentation."
Recommended Actions for Holders of Construction Permits or Operating Licenses:
1.
Determine whether your facility uses the subject Series 2 indicating push-button switches in any safety-related function.
If there are no indicating pushbutton switches of this type in your facility, you need not pursue this matter further.
2.
If the subject switches are used to perform safety-related functions at your facility,'either replace them with qualified units or modify them to
IEC No. 81-01 Janua ry 23, 1981 Page 4 of 4 eliminate the deficiencies. Holders of operating licenses should take the appropriate action as soon as practical; construction permit holders should take the appropriate action prior to startup.
(If the switches are to be modified, contact Honeywell Incorporated for assistance.)
3.
Until the appropriate corrective action is completed, the following interim measures should be taken:
If the design of the affected equipment permits its switch assembly to a.
be de-energized for relamping, verify that the procedures specify that power is to be removed from the switch assembly during relamping.
If the procedures do not so specify, revise them to include such a provision.
b.
If the design of the affected equipment does not permit its switch assembly to be de-energized for relamping, verify that the operator can determine the status of the affected equipment by alternate Towards this end, implement procedures to enable the operator means.
to determine the status of the affected equipment by alternate means (e.g., acceptable method for inferring the position of a valve could include system flow, pressure, or temperature measurements).
If-titernate status indication methods'are not available, relamping should be deferred until the next outage during which time the e ffected equipment can be removed from service. However, during the resulting blind time, rf;id administrative controls should be implemented to provide the operator with reliable status information.
No written response to this circular is required. If you require additional information with regard to this subject, please contact the appropriate NRC Regional Office.
IE Circular No. 81-01 January 23, 1981 RECENTLY ISSL'ED IE CIRCULARS Circular Subject Date Issued To No.
Issued 80-17 Fuel Pin Damage Due to 7/23/80 All holders of PWR Operating Water Jet from Baffle Licenses (OLs) and PWR Plate Corner Construction Permits (cps) 80-18 10 CFR 50.59 Safety 8/22/80 All power reactor facilities Evaluations for Changes to with an Operating License (OL)
Radioactive Waste or a Construction Permit (CP)
Treatment Systems 80-19 Noncompliance with 8/26/80 All medical licensees License Requirements for Medical Licensees 30-20 Changes in Safe-Slab 8/21/80 All Part 50 and Part 70 Dimensions fuel facility licensees 80-21 Regulation of Refueling 9/10/80 All holders of a power reactor Crews Operating License (0L) or 30-22 Confirmation of employee 10/2/80 All holders of a power reactor qualifications Operating License (OL)or Construction Permit (CP),
architect-engineering companies and nuclear steam system suppli ers 80-23 Potential Defects in 10/31/80 All power reactor facilities Beloit Power Systems with Operating License (OL)
Emergency Generators or Construction Permit (CP) 30-24 AECL Teletherapy Unit 12/2/80 All teletherapy licensees Malfunction Enclosure
-- ___