ML19345C383

From kanterella
Jump to navigation Jump to search
Advises of Requirements That Must Be Met Re NRC Review of Special Low Power Test Program & Emergency Procedures for Selected Transients & Accidents
ML19345C383
Person / Time
Site: Summer South Carolina Electric & Gas Company icon.png
Issue date: 11/20/1980
From: Tedesco R
Office of Nuclear Reactor Regulation
To: Nichols T
SOUTH CAROLINA ELECTRIC & GAS CO.
References
NUDOCS 8012040582
Download: ML19345C383 (2)


Text

.

jgy e

pc m'o,}

[

UNITED STATES fjt r,

p, NUCLEAR REGULATORY COMMISSION y

-rq a

WASHINGTON. D. C. 20655 8

o*%

  • J' y

N DockeY N. 50-395 s

fi y

x g,

y R:45 y~

Sa NOV 2 01980 eFN a:!

sm et Mr. T. C. Nichols, Jr.

zWe 3-sm Vice President 3 Group Executive E

LTe Nuclear Operations lQ lN South Carolina Electric & Gas Company y

'm P. O. Box 764 Columbia, South Carolina-29281

Dear Mr. Nichols:

SUBJECT:

NRC REVIEW SCHEDULAR REQUIREMENTS FOR SPECIAL LOW POWER TEST PROGRAM AND EMERGENCY PROCEDURES To accomplish timely review of your application, it is necessary that the following schedular requirements be met. These requirements specifically relate to NRC review cf your Special Low Power Test Program and Emergency Procedures for selected transients and accidents. The following lead times must be met if our evaluations are to be completed on a schedule consistent with your schedule for performing tests and proceeding with the power ascension program abova 5% of full power.

1.

Procedures for conducting the Special Low Power Test Program must be submitted at least 4 weeks prior to authorization to perfom the test.

2.

Revised emergency procedures prepared in accordance with staff coments must be submitted at le ' seven weeks prior to completing our review; procedures walk-throughs in your control room must be completed at least 2 weeks prior to issuance of a full power operating license.

3.

The results of the Special Low Power Test Program must be submitted for NRC review 2 weeks prior to proceeding above 5% of full power.

Implicit in the above requirements is the assumption that NRC requests for any additional informatior, on the above matters will be answered in 1 -

1 1/2 weeks.

t Sincerely, dh Robert L. Tidesco Assistant Director for Licensing Division of Licensing cc: See next page I

8012040582

[

., _II Mr. T. C. Nichols, Jr.

Vice President & Group Executive NOV 20 msg Nuclear Operations South Carolina Electric & Gas Company P. O. Box 764 Columbia, South Carolina 29281 cc: Mr. William A. Williams, Jr.

Vice President South Carolina Public Service Authority 223 North Live Oak Drive Moncks Corner, South Carolina 29461 J. B. Knotts, Jr., Esq.

Debevoise & Liberman 120017th Street, N. W.

Washington, D. C.

20036 Mr. Mark B. Whitaker, Jr.

Group Manager - Nuclear Engineering & Licensing South Carolina Electric & Gas Company P. O. Box 764 Columbia, South Carolina 29218 Mr. Brett Allen Bursey Route 1 Box 93C Little Mountain, South Carolina 29076 Resident Inspector / Summer NPS c/o U. S. NRC Route 1, Box 64 Jenkinsville, South Carolina 29065 l